Shared Services Joint Committee, Friday 27 June 2025 at 10.00am

The Future Model for ICT: Programme Gemini Update

Approved Committee 1 paper

Shared Services Joint Committee approved this item on Friday 27 June 2025. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That the Joint Committee notes the progress made and current status of the Phase 1 Gemini Programme and recommends to the Cabinet of Cheshire West and Chester Council and the Corporate Policy Committee of Cheshire East Council, (subject to consultation with unions and staff), to approve a move away from the Retained Shared Service model by 2027 (or sooner) via the delivery of Gemini Phase 2 programme and the ultimate disaggregation of the Retained Shared Service for ICT.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Shared Services Joint Committee

Recommendations

2.1That Shared Services Joint Committee notes the progress made and current status of the Phase 1 Gemini Programme and recommends to the Cabinet of Cheshire West and Chester Council and the Corporate Policy Committee of Cheshire East Council, (subject to consultation with unions and staff), to approve a move away from the Retained Shared Service model by 2027 (or sooner) via the delivery of Gemini Phase 2 programme and the ultimate disaggregation of the Retained Shared Service for ICT.

Reasons for recommendations

3.1In accordance with the Terms of Reference, the Shared Services Joint Committee is responsible for overseeing changes and projects and changes to shared services and ensuring that there are robust plans for any disaggregation of services and that there is a smooth transition into the separate arrangements.

OFFICIAL 3.2 The Shared Services Joint Committee is not the ultimate decision making body and so the recommendations set out in this report must be routed through the Shared Services Joint Committee for a decision by each Council’s executive (Cabinet or Committee).

Background

4.1Following comprehensive joint work by both councils, on 26 January 2023 the Shared Services Joint Committee recommended that their constituent councils proceed with a hybrid model for ICT.

4.2The recommendation to move to a new model for ICT Services was agreed at Cheshire East Councils Corporate Policy Committee on 9 February 2023, and Cheshire West and Chester Cabinet on 8 February 2023.

4.3This new model involved separating much of the ICT Shared Service and retaining a smaller shared service to support hosting, security, and networks. It was noted that with a hybrid model there was greater chance of the two councils fully aligning their ICT functions, while still securing economies of scale for shared infrastructure. This in turn enables the ICT offer to be fully responsive and more efficient.

4.4It was agreed that the Shared Services Joint Committee would play a key role in providing oversight throughout the programme and that a joint scrutiny task group would be established. When mobilised, the Gemini Programme assumed a separation of most ICT functions and the retention of a smaller shared service for hosting and networks (the Retained Shared Service). At the time, this included a shared data centre (Kelly House) which hosted several systems and a shared network.

4.5It was acknowledged that there would be a need to review the longer-term future of the Retained Shared Service in line with the latest technology trends, council objectives and available financial resources. The review, to provide clarity on the longer-term future of the Retained Shared Service, was commissioned and undertaken in early 2024, approved by the Gemini Programme Board and shared with Members at the informal meeting of the Shared Services Joint Committee on 15 March 2024 and by a confidential report at the meeting on 20 September 2024. The review concluded that an on-premises data centre is no longer the optimum hosting platform that both councils should invest in. It also concluded that

OFFICIAL a shared network, as currently delivered, is not a long-term viable model for delivery due to advances in connectivity services and technology and the changing nature of how the councils want to operate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Future Model for ICT: Programme Gemini UpdateMinutes 215 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. The Future Model for ICT: Programme Gemini UpdateThis decision
  2. The Future Model for ICT: Retained Shared Service and Gemini Phase 2Approved
  3. The Future Model for ICT: Programme Gemini UpdateNoted
  4. The Future Model for ICT: Shared Service ReviewApproved

More from Cheshire East Shared Services Joint Committee

All decisions
MeetingDecisionOutcome
27 Jun 2025 Appointment of ChairThat Councillor Jill Rhodes be appointed as chair for the 2025/26 municipal year. Decided Open
27 Jun 2025 Appointment of Vice ChairThat Councillor Carol Gahan be appointed as vice-chair for the 2025/26 municipal year. Decided Open
27 Jun 2025 Minutes of Previous MeetingThat the minutes of the meeting held on 25 April 2025 be approved as a correct record. Approved Open
27 Jun 2025 Shared Services Business Plans 2024-25 - End of Year ReportThat the Joint Committee note the Shared Services performance for 2024/25. Noted Open
24 Nov 2023 Minutes of Previous meetingThat the minutes of the meeting held on Friday 30 June 2023 be approved as a correct record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies