Budget Approval and Acceptance of DfT Grant for the Middlewich Eastern Bypass

Approved Committee 2 papers

AI summaryCheshire East’s Corporate Policy Committee unanimously recommended that Full Council accept the remaining £23.304m Department for Transport grant and increase the Middlewich Eastern Bypass budget from £97.94m to £107.67m [D]

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedAccept grant and increase scheme budget [D]
Money£23.304m grant; £107.67m budget [D]Budget rises £9.73m from £97.94m [D]
What happens nextFull Council to consider [D]Sign and return the DfT Grant Letter [D]
Who it affectsMiddlewich Eastern Bypass scheme [D]DfT grant supports scheme delivery [D]

What was decided

The committee unanimously recommended that Full Council accept the remaining £23.304m DfT grant, payable over 26/27 and 27/28, for scheme delivery when received. The recommendation would authorise the council’s Executive Director of Resources and Section 151 Officer to accept £22.876m in 26/27 and £0.428m in 27/28, and to sign and return the Grant Letter to the DfT.

The committee recommended approval of a supplementary capital estimate for the remaining grant and an increase in the Middlewich Eastern Bypass allocation from £97.94m to £107.67m for the Capital Programme. The decision links the £9.73m increase to £1m from the 2025/26 Local Transport Fund and a request for a minimum of £5.54m from the Local Transport Capital Grant. It also provides for a supplementary capital estimate or virement to the scheme.

It recommended allocating £1.24m of surplus held within the Congleton Link Road major highways scheme to the project through a supplementary capital estimate or virement. Any future proceeds from sales of land and property acquired in addition to land acquired under the Compulsory Purchase Order during scheme development would also be allocated to the Middlewich Eastern Bypass project.

Why

The remaining DfT grant is for delivery of the Middlewich Eastern Bypass, when received.

The revised Middlewich Eastern Bypass allocation is for inclusion in the Council’s Capital Programme.

The Congleton Link Road contribution uses money already held as a £1.24m surplus in that major highways scheme.

What happens next

Full Council is asked to consider the committee’s recommendation.

The recommendation would authorise the council’s Executive Director of Resources and Section 151 Officer to accept the grant allocation and sign and return the Grant Letter to the DfT.

A request for a minimum of £5.54m Local Transport Capital Grant allocation is to be made to the Shadow Board of the new Combined Authority in the near future. Supplementary capital estimates or virements would apply the £1m Local Transport Fund allocation and £1.24m Congleton Link Road surplus. Any future sale proceeds would be allocated to the project.

The money

  • £23.304m Remaining DfT grant for scheme delivery, payable over 26/27 and 27/28
  • £22.876m DfT grant allocation in 26/27 towards the Middlewich Eastern Bypass
  • £0.428m DfT grant allocation in 27/28 towards the Middlewich Eastern Bypass
  • £107.67m New Middlewich Eastern Bypass allocation, up from £97.94m, for the Capital Programme
  • £9.73m Increase in the allocated Middlewich Eastern Bypass budget
  • £1m 2025/26 Local Transport Fund allocation towards the increase
  • £5.54m Minimum Local Transport Capital Grant allocation requested from the Shadow Board
  • £1.24m Congleton Link Road major highways scheme surplus allocated to the project

Options considered

  • Chosen: Accept the remaining DfT grant. For delivery of the scheme, when received
  • Chosen: Authorise the Executive Director of Resources and Section 151 Officer to accept the grant and sign the Grant Letter
  • Chosen: Approve a supplementary capital estimate for the remaining grant
  • Chosen: Increase the Middlewich Eastern Bypass allocation from £97.94m to £107.67m. For inclusion in the Council’s Capital Programme
  • Chosen: Allocate £1.24m of Congleton Link Road surplus to the project. The money is a surplus within the Congleton Link Road major highways scheme
  • Chosen: Allocate future land and property sale proceeds to the Middlewich Eastern Bypass project

Implications

  • Financial: The Capital Programme allocation for the Middlewich Eastern Bypass would rise from £97.94m to £107.67m.
  • Financial: The remaining DfT grant would provide £23.304m over 26/27 and 27/28.
  • Financial: The decision links the £9.73m increase to £1m from the 2025/26 Local Transport Fund and a request for a minimum of £5.54m from the Local Transport Capital Grant.
  • Financial: A £1.24m surplus from the Congleton Link Road major highways scheme would be moved to the bypass.
  • Legal: The Executive Director of Resources and Section 151 Officer would be authorised to sign and return the Grant Letter to the DfT.
  • Other: A request for a minimum of £5.54m would be made to the Shadow Board of the new Combined Authority in the near future.
  • Other: Any future proceeds from sales of additional land and property would be allocated to the bypass.

Who and where

  • Middlewich Eastern Bypass project
  • Congleton Link Road major highways scheme
  • Cheshire East Council
  • Full Council
  • Shadow Board of the new Combined Authority

Timeline

  • 2025-11-27: Corporate Policy Committee unanimously recommends the changes to Full Council
  • 2025/26: £1m allocated from the Local Transport Fund towards the £9.73m increase
  • 26/27: £22.876m DfT grant allocation payable towards the Middlewich Eastern Bypass
  • 27/28: £0.428m DfT grant allocation payable towards the Middlewich Eastern Bypass
  • when received: Remaining grant is to be spent on delivery of the scheme
  • in the near future: Request a minimum of £5.54m Local Transport Capital Grant allocation from the Shadow Board
  • future: Proceeds from sales of additional land and property are allocated to the Middlewich Eastern Bypass

Plain English for the jargon

  • DfT: Department for Transport [D]
  • MEB: Middlewich Eastern Bypass [D]
  • Section 151 Officer: Officer authorised to accept the grant and sign the Grant Letter with the Executive Director of Resources [D]
  • Local Transport Fund: 2025/26 source of £1m towards the bypass budget increase [D]
  • Local Transport Capital Grant: Grant for which a minimum of £5.54m allocation is requested [D]
  • Shadow Board of the new Combined Authority: Body asked for the Local Transport Capital Grant allocation [D]
  • Supplementary capital estimate: Additional budget authorisation for the remaining grant or reallocated money [D]
  • Virement: Movement of allocated money to the bypass scheme [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item61

Resolved

RESOLVED (unanimously): That the Corporate Policy Committee recommend to Full Council 1. To accept the remaining £23.304m grant monies payable over 26/27 and 27/28 from the Department for Transport to be spent on the delivery of the scheme, when received to: a) Authorise the Executive Director of Resources and Section 151 Officer to: i. accept the DfT Grant allocation of £22.876m in 26/27 and £0.428m in 27/28. towards the MEB. ii. sign and return the Grant Letter by the DfT Page 276 2. to approve a supplementary capital estimate for remaining grant monies. 3. to approve an increase in the allocated budget for the MEB from £97.94m to £107.67m for inclusion on the Council’s Capital Programme. To agree that the increase of £9.73m be obtained from allocations from the 2025/26 Local Transport Fund of £1m and a request to the Shadow Board of the new Combined Authority in the near future for a minimum of £5.54m allocation of the Local Transport Capital Grant as detailed in the report and to authorise a supplementary capital estimate/ virement of the monies to the scheme. 4. to allocate £1.24m surplus monies contained within the Congleton Link Road major highways scheme towards the project and authorise a supplementary capital estimate / virement of the monies to the scheme. 5. to allocate any future proceeds from the sale of the land and property acquired in addition to the land acquired under the Compulsory Purchase Order during scheme development to the MEB project.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Corporate Policy Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Alternative Scheme OptionsAppendix 2 95 KB Copy on its way
PDF
Budget Approval and Acceptance of DfT Grant for the Middlewich Eastern BypassMinutes 284 KB Copy on its way

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Budget Approval and Acceptance of DfT Grant for the Middlewich Eastern BypassThis decision
  2. Recommendations from Corporate Policy Committee: Budget Approval and acceptance of DfT Grant for the Middlewich Eastern BypassApproved

More from Cheshire East Corporate Policy Committee

All decisions
MeetingDecisionOutcome
30 Apr 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 19 March 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Apr 2026 Adlington New Town - response to Government consultationIt was agreed that officers should explore further the word-limit constraint and the option to submit supporting docu... Agreed Open
30 Apr 2026 Housing Enforcement PolicyRESOLVED (by majority): That the Corporate Policy Committee 1. Approve the revised Housing Enforcement Policy. 2. Aut... Approved Open
30 Apr 2026 The future potential growth of Crewe - an overviewIt was agreed that consideration should be given to a borough-wide Annual Statement Position report, covering current... Agreed Open
30 Apr 2026 Senior Management Structure - Children's ServicesRESOLVED (unanimously): That the Corporate Policy Committee recommend that full Council: 1. Agree the proposed change... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies