What was decided
The committee unanimously recommended that Full Council accept the remaining £23.304m DfT grant, payable over 26/27 and 27/28, for scheme delivery when received. The recommendation would authorise the council’s Executive Director of Resources and Section 151 Officer to accept £22.876m in 26/27 and £0.428m in 27/28, and to sign and return the Grant Letter to the DfT.
The committee recommended approval of a supplementary capital estimate for the remaining grant and an increase in the Middlewich Eastern Bypass allocation from £97.94m to £107.67m for the Capital Programme. The decision links the £9.73m increase to £1m from the 2025/26 Local Transport Fund and a request for a minimum of £5.54m from the Local Transport Capital Grant. It also provides for a supplementary capital estimate or virement to the scheme.
It recommended allocating £1.24m of surplus held within the Congleton Link Road major highways scheme to the project through a supplementary capital estimate or virement. Any future proceeds from sales of land and property acquired in addition to land acquired under the Compulsory Purchase Order during scheme development would also be allocated to the Middlewich Eastern Bypass project.
Why
The remaining DfT grant is for delivery of the Middlewich Eastern Bypass, when received.
The revised Middlewich Eastern Bypass allocation is for inclusion in the Council’s Capital Programme.
The Congleton Link Road contribution uses money already held as a £1.24m surplus in that major highways scheme.
What happens next
Full Council is asked to consider the committee’s recommendation.
The recommendation would authorise the council’s Executive Director of Resources and Section 151 Officer to accept the grant allocation and sign and return the Grant Letter to the DfT.
A request for a minimum of £5.54m Local Transport Capital Grant allocation is to be made to the Shadow Board of the new Combined Authority in the near future. Supplementary capital estimates or virements would apply the £1m Local Transport Fund allocation and £1.24m Congleton Link Road surplus. Any future sale proceeds would be allocated to the project.
The money
- £23.304m Remaining DfT grant for scheme delivery, payable over 26/27 and 27/28
- £22.876m DfT grant allocation in 26/27 towards the Middlewich Eastern Bypass
- £0.428m DfT grant allocation in 27/28 towards the Middlewich Eastern Bypass
- £107.67m New Middlewich Eastern Bypass allocation, up from £97.94m, for the Capital Programme
- £9.73m Increase in the allocated Middlewich Eastern Bypass budget
- £1m 2025/26 Local Transport Fund allocation towards the increase
- £5.54m Minimum Local Transport Capital Grant allocation requested from the Shadow Board
- £1.24m Congleton Link Road major highways scheme surplus allocated to the project
Options considered
- Chosen: Accept the remaining DfT grant. For delivery of the scheme, when received
- Chosen: Authorise the Executive Director of Resources and Section 151 Officer to accept the grant and sign the Grant Letter
- Chosen: Approve a supplementary capital estimate for the remaining grant
- Chosen: Increase the Middlewich Eastern Bypass allocation from £97.94m to £107.67m. For inclusion in the Council’s Capital Programme
- Chosen: Allocate £1.24m of Congleton Link Road surplus to the project. The money is a surplus within the Congleton Link Road major highways scheme
- Chosen: Allocate future land and property sale proceeds to the Middlewich Eastern Bypass project
Implications
- Financial: The Capital Programme allocation for the Middlewich Eastern Bypass would rise from £97.94m to £107.67m.
- Financial: The remaining DfT grant would provide £23.304m over 26/27 and 27/28.
- Financial: The decision links the £9.73m increase to £1m from the 2025/26 Local Transport Fund and a request for a minimum of £5.54m from the Local Transport Capital Grant.
- Financial: A £1.24m surplus from the Congleton Link Road major highways scheme would be moved to the bypass.
- Legal: The Executive Director of Resources and Section 151 Officer would be authorised to sign and return the Grant Letter to the DfT.
- Other: A request for a minimum of £5.54m would be made to the Shadow Board of the new Combined Authority in the near future.
- Other: Any future proceeds from sales of additional land and property would be allocated to the bypass.
Who and where
- Middlewich Eastern Bypass project
- Congleton Link Road major highways scheme
- Cheshire East Council
- Full Council
- Shadow Board of the new Combined Authority
Timeline
- 2025-11-27: Corporate Policy Committee unanimously recommends the changes to Full Council
- 2025/26: £1m allocated from the Local Transport Fund towards the £9.73m increase
- 26/27: £22.876m DfT grant allocation payable towards the Middlewich Eastern Bypass
- 27/28: £0.428m DfT grant allocation payable towards the Middlewich Eastern Bypass
- when received: Remaining grant is to be spent on delivery of the scheme
- in the near future: Request a minimum of £5.54m Local Transport Capital Grant allocation from the Shadow Board
- future: Proceeds from sales of additional land and property are allocated to the Middlewich Eastern Bypass
Plain English for the jargon
- DfT: Department for Transport [D]
- MEB: Middlewich Eastern Bypass [D]
- Section 151 Officer: Officer authorised to accept the grant and sign the Grant Letter with the Executive Director of Resources [D]
- Local Transport Fund: 2025/26 source of £1m towards the bypass budget increase [D]
- Local Transport Capital Grant: Grant for which a minimum of £5.54m allocation is requested [D]
- Shadow Board of the new Combined Authority: Body asked for the Local Transport Capital Grant allocation [D]
- Supplementary capital estimate: Additional budget authorisation for the remaining grant or reallocated money [D]
- Virement: Movement of allocated money to the bypass scheme [D]