AI summaryCheshire East's Economy and Growth Committee approved by majority a reallocation of Crewe Towns Fund money, cutting Valley Brook Green Corridor by up to £1.25m and increasing four other projects. £0.186m is held as contingency, and the Flag Lane Baths school plan is dropped.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSix project budgets changed, Flag Lane Baths plan dropped
MoneyReallocations within £22.9m grant£0.186m held as programme contingency
What happens nextFlag Lane Baths to be remarketedHead of Estates to lead disposal process
Who it affectsCrewe Towns Fund projectsSix projects plus Flag Lane Baths site
What was decided
Approved by majority reallocation of Towns Fund grant between six projects, reducing Valley Brook Green Corridor by up to £1.25m and increasing the budgets of Cumberland Arena, Warm & Healthy Homes, Repurposing Our High Streets and Crewe YouthZone. Report P10
Noted that £0.186m Towns Fund grant remains unallocated and is to be managed as a programme-level contingency budget. Report P13
Dropped the Alternative Provision School plan for the former Flag Lane Baths and delegated authority to the Head of Estates to market the site and dispose of the property. Report P17, P19, P46
Why
MHCLG has simplified Towns Fund requirements, removing the need for its approval of budget changes, which opened an opportunity to reallocate funds to evolving programme priorities. Report P5, P6
The Valley Brook Green Corridor highways elements were unaffordable, freeing up to £1.25m that other projects were invited to bid for at the Town Board meetings of 5 December 2025 and 9 January 2026. Report P25, P26
There is insufficient funding and no confirmed Department for Education timeline to take forward the Alternative Provision School at the former Flag Lane Baths. Report P19, P46
What happens next
Officers will adjust the Medium Term Financial Strategy and amend grant agreements and contracts to reflect the new allocations, with capital virements between fully funded projects. Report P11, P12, P60
A marketing exercise will be undertaken to identify potential uses and developers for the former Flag Lane Baths site, in line with Section 123 of the Local Government Act 1972. Report P17, P52, P54
The Executive Director Place and the Executive Director Resources (S151 Officer) are delegated authority to approve future Towns Fund reallocations between existing projects, to be reported back to the committee. Report P14, P15, P16
The money
£1.25m Reduction to Valley Brook Green Corridor, from £3.339m to £2.089m Report P10, P25
£0.519m Increase to Cumberland Arena, from £3.093m to £3.612m Report P10
£0.207m Increase to Warm & Healthy Homes, from £2.126m to £2.333m Report P10
£0.02m Increase to Repurposing Our High Streets, from £1.132m to £1.152m Report P10
£0.318m Increase to Crewe YouthZone total, from £5.830m to £6.148m Report P10
£0.28m Increase to Crewe YouthZone (The Dome) at Oak Street, from £4.639m to £4.919m Report P10
£0.038m Increase to Crewe Youth Club at Mirion Street, from £1.19m to £1.228m Report P10
£22.9m Total Towns Fund grant allocated by Government in 2021 Report P2, P18
£0.186m Towns Fund grant held as programme-level contingency Report P13, P28
£1,353,000 Cheshire East Council funding previously reallocated from Crewe Youth Zone to Flag Lane Baths Report P45
Options considered
Chosen: Reallocate Towns Fund grant to six projects as recommended by Crewe Town Board. Additional funding will deliver specific extra benefits within the original project business cases and within required timescales Report P30, P10
Rejected: Increase Pocket Parks budget to upgrade another Pocket Park at King George V playing fields. Extends the project beyond the original business case and does not represent the best value for money Report P49
Rejected: Increase allocations to extend the scope of enhancements for the projects in this report. Either extends beyond the original business case or does not represent the best value for money Report P50
Rejected: Increase allocations to provide additional contingency for current project scope. May not represent the best value for money, but a programme-level contingency is being retained instead Report P51
Implications
Financial: Reallocations are funded from within the £22.9m Towns Fund grant with no net impact on the council's Medium Term Financial Strategy; £0.186m is held as programme contingency. Report P11, P13, P57, P60
Legal: MHCLG approval is no longer required for budget changes; disposal of the former Flag Lane Baths must comply with Section 123 of the Local Government Act 1972 on best consideration. Report P5, P52, P54
Equalities: The reallocation secures equalities benefits for users of the Crewe YouthZone, particularly young people and those with special educational needs and disabilities. Report P72, P75
Climate: The reduced scope of the Valley Brook Green Corridor should lead to lower future maintenance and upkeep revenue costs for the council. Report P59
Risk: Without reallocation, the council could face having to return funds to government; project-level contingencies may be insufficient, justifying the new programme-level contingency. Report P43, P57, P63
Who and where
Users of Crewe YouthZone (The Dome) at Oak Street, particularly young people and those with SEND Report P10, P37, P72, P75
Users of Crewe Youth Club at Mirion Street Report P10, P41
Users of Cumberland Arena, including changing rooms, common areas and car park Report P10, P32, P33, P34
Households eligible for loft insulation under the Warm & Healthy Homes project Report P10, P35
Crewe high street businesses receiving advice and grant support from April 2026 to March 2027 Report P10, P36
Valley Brook Green Corridor project, with the highways elements removed and the budget reduced Report P25
Children & Families Committee and Environment & Communities Committee, whose linked projects are affected Report P66, P67
Timeline
2021: Government allocated £22.9m Towns Fund grant to support Crewe regeneration projects Report P2, P18
25 September 2024: Economy & Growth Committee delegated authority to explore options for the former Flag Lane Baths and approved £1,353,000 reallocation from Crewe Youth Zone Report P45
5 December 2025: Crewe Town Board was advised that the Valley Brook Green Corridor highways element was unaffordable, freeing up to £1.25m Report P25
9 January 2026: Crewe Town Board considered proposals from other projects for the freed-up funding Report P26
16 February 2026: Children & Families Committee received an update on the former Flag Lane Baths and the Alternative Provision School proposal Report P19, P91
10 March 2026: Economy and Growth Committee approved the reallocations and the Flag Lane Baths disposal plan
April 2026, March 2027: Period for business advice and support to grant applicants under Repurposing Our High Streets Report P36
Plain English for the jargon
Towns Fund: Government regeneration grant programme, now officially known as the Local Regeneration Fund
MTFS: Medium Term Financial Strategy, the council's financial planning document
MHCLG: Ministry of Housing, Communities and Local Government, the government funder
Town Board: Crewe Town Board, the independent body overseeing the Towns Fund programme
S151 Officer: The council's Chief Finance Officer, appointed under section 151 of the Local Government Act 1972
Section 123: Section 123 of the Local Government Act 1972, requiring best consideration when disposing of council land
SEND: Special educational needs and disabilities
DfE: Department for Education
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item35
Resolved
RESOLVED (by majority): That the Committee 1 approve the following changes to Towns Fund project capital grant allocations: a) reduce the allocation for Valley Brook Green Corridor by up to £1.25m from £3.339m to £2. 089m; b) increase the allocation for Cumberland Arena by £0.519m from £3.093m to £3. 612m; c) increase the allocation for Warm & Healthy Homes by up to £0.207m from £2.126m to £2. 333m; d) increase the allocation for Repurposing Our High Streets by up to £0.02m from £1.132m to £1. 152m; e) increase the allocation for Crewe YouthZone by £0.318m from £5.830m to £6.148m, noting that this comprises an increase of £0.28m for Crewe YouthZone (‘The Dome’) at Oak Street from £4.639m to £4.919m and an increase of £0.038m for Crewe Youth Club at Mirion Street from £1.19m to £1.228m. 2 approve adjustments to the council’s Medium Term ... view the full minutes text for item 35.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
2 A comprehensive programme of regeneration is already underway in Crewe town centre, building on initial investment by the council in 2015 and including funding secured from the Government’s Ministry of Housing, Communities and Local Government (MHCLG), notably the Towns Fund, which is overseen by the independent Crewe Town Board with the support of the council as accountable body and programme manager.
3 In 2021, the Government allocated £22.9m to support a range of regeneration projects in Crewe. This report relates to six of those projects: Valley Brook Green Corridor, Cumberland Arena, Warm &
OFFICIAL Healthy Homes, Repurposing Our High Streets and Crewe Youth Zone (comprising The Dome YouthZone and Crewe Youth Club).
4 MHCLG has previously approved three ‘Project Adjustment Requests’ proposed by Crewe Town Board and council, to allow the reallocation of grant funding within the £22.9m budget
5 MHCLG has recently simplified its requirements in relation to the Towns Fund (which is now officially known as the Local Regeneration Fund). This includes removing the need to seek approval of MHCLG for changes to project budgets and KPIs.
6 As project delivery has progressed, there is an opportunity for funding to be reallocated to address evolving programme and project priorities.
7 This committee has previously agreed, due to rising costs and lack of other funding, to withdraw Towns Fund grant funding for the Flag Lane Baths project which had been led by a third party with plans for a community facility. The committee agreed to consider options for its redevelopment for a new Alternative Provision School and develop a business case to be reported back to the committee in due course. It is now evident that there is insufficient funding and no confirmed timeline from the Government’s Department for Education (DfE) to bring this proposed use forward, so the council needs to consider alternative options for the building and site.
Recommendations
The Economy & Growth Committee is recommended to:
1. Approve the following changes to Towns Fund project capital grant allocations:
a) reduce the allocation for Valley Brook Green Corridor by up to £1.25m from £3.339m to £2.089m; b) increase the allocation for Cumberland Arena by £0.519m from £3.093m to £3.612m; c) increase the allocation for Warm & Healthy Homes by up to £0.207m from £2.126m to £2.333m; d) increase the allocation for Repurposing Our High Streets by up to £0.02m from £1.132m to £1.152m; e) increase the allocation for Crewe YouthZone by £0.318m from £5.830m to £6.148m, noting that this comprises an increase of £0.28m for Crewe YouthZone (‘The Dome’) at Oak Street from £4.639m to £4.919m and an increase of £0.038m for Crewe Youth Club at Mirion Street from £1.19m to £1.228m.
2. Approve adjustments to the council’s Medium Term Financial Strategy (MTFS) that reflect the recommendations above and note there is no net impact on the MTFS.
3. Authorise any necessary amendments to grant agreements and contracts to reflect the budgetary changes proposed.
4. Note that £0.186m Towns Fund grant remains unallocated at present and is to be managed as a programme-level contingency budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Third Financial Review of 2025/26RESOLVED (Unanimously): That the Committee 1 note the overall Council’s Financial position as described within the Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.