Internal Audit Plan 2026-27

Approved Finance 3 papers

AI summaryCheshire East Audit and Governance Committee approves the Internal Audit Plan for 2026/27, which sets out the year's risk based audit work and supports the Annual Governance Statement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal Audit Plan 2026/27 approved
MoneyNot stated
What happens nextPlan implemented and monitoredProgress and revisions reported to Committee
Who it affectsCouncil governance and controlsAnnual internal audit opinion and AGS

What was decided

The Committee approved the Internal Audit Plan 2026/27 by majority. Report P4

Members were asked to consider whether the scale, resources and balance of non-assurance work were sufficient under GIAS. Report P10, P11, P12, P13

Why

Approval of an annual risk based internal audit plan is a statutory requirement under the Accounts and Audit Regulations 2015 and is needed to comply with the Global Internal Audit Standards in the UK Public Sector. Report P5, P20, P21

The plan underpins the annual internal audit opinion used to inform the Annual Governance Statement and supports the Council's objective as an effective and enabling organisation. Report P1, P2, P14

Approving the plan falls within the Committee's Terms of Reference. Report P15

What happens next

The plan will be implemented based on current known resources, with work detailed in Appendix B and methodology in Appendix A. Report P7, P8, P46, P47

Progress updates and any significant revisions will be brought back to the Committee, in line with the requirement that the plan is dynamic and responsive. Report P9

The team will support the vacancy management factor in 2026/27 and review skills and capacity, including where external specialist support may be needed. Report P25, P28

Options considered

  • Chosen: Approve the Internal Audit Plan 2026/27. Statutory requirement under the Accounts and Audit Regulations 2015 and GIAS; needed to deliver the annual audit opinion. Report P4, P5, P17
  • Rejected: Do nothing. Would leave the Council in breach of the Accounts and Audit Regulations 2015 and non compliant with GIAS, and would leave the Committee without an annual plan to review. Report P17, P18

Implications

  • Legal: All principal local authorities must make proper provision for internal audit under the 1972 Local Government Act (S151) and the Accounts and Audit Regulations 2015. Report P20
  • Risk: The plan is designed to support the Council in identifying and managing risks and improving governance and the control environment. Report P29
  • Staffing: The plan is based on current known resources; the team supports the vacancy management factor, with a review of skills, capacity and structure planned, and possible procurement of specialist support. Report P24, P25, P28
  • Financial: The S151 Officer notes the Committee should ensure the function has the necessary resources; any imbalance between plan and resources, or need for significant changes, will be reported back to the Committee. Report P23, P26
  • Equalities: No direct implications for equality, diversity and inclusion. Report P34
  • Climate: No direct implications for climate change. Report P36

Who and where

  • Cheshire East Council as a whole, through its governance, risk and internal control arrangements Report P1, P2
  • The Audit and Governance Committee, which oversees internal audit activity Report P30
  • The Internal Audit team, in terms of workload, skills and capacity Report P28

Timeline

  • 2026/27: Period covered by the approved Internal Audit Plan Report P4, P7
  • 11/03/26: Statutory officers and consultees sent and returned their comments on the plan Report P39, P40, P42, P43

Plain English for the jargon

  • GIAS: Global Internal Audit Standards in the UK Public Sector, the standards with which the plan must comply.
  • AGS: Annual Governance Statement, which is informed by the annual internal audit opinion.
  • S151 Officer: The council officer with statutory finance responsibilities under section 151 of the Local Government Act 1972.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

RESOLVED (by majority): That the Audit and Governance Committee 1. Approve the Internal Audit Plan 2026/27.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Audit and Governance Committee

Executive summary

2 The preparation and delivery of the annual Internal Audit Plan, annual opinion on the arrangements for governance, risk and internal control, and the assurances these provide to the Annual Governance Statement (AGS) are key indicators and contributors for the Council’s corporate objective as an effective and enabling organisation.

3 The Council’s Internal Audit Charter, which has been developed to ensure compliance with the Global Internal Audit Standards in the UK Public Sector (GIAS), requires the preparation of a risk based internal audit plan which considers the need to produce an annual internal audit opinion, and supports achievement of the organisation’s objectives.

Recommendations

The Audit and Governance Committee is recommended to:

1. Approve the Internal Audit Plan 2026/27.

OFFICIAL Background 4 All principal local authorities subject to the Accounts and Audit Regulations 2015 must make provision for internal audit in accordance with the relevant standards, now GIAS. These standards require the chief audit executive (Head of Audit, Risk and Assurance) to create an internal audit plan that supports the achievement of the organisation’s objectives.

5 The plan must be based on a documented assessment of the organisation’s strategies, objective and risks, and be informed by input from the board, senior management and the chief audit executive’s understanding of the organisation, in terms of governance, risk and internal control. This assessment should be performed at least annually.

6 The plan is produced based on the known, current, resource available. In developing the plan, we have looked to recognise the context of continuing strategic change, development and improvement required by the Council and to provide assurance that previously identified significant control weaknesses have been effectively and efficiently addressed and improved.

7 The planning methodology and resource calculation is detailed in Appendix A. The detail of work proposed is set out in Appendix B.

8 The plan must be dynamic and responsive to changes in the organisation’s business operations, risks, internal control and organisational culture. Progress updates, consideration of the ongoing priorities for internal audit and where necessary, significant revisions to the plan will be brought back to the Audit and Governance Committee. By working closely with services to regularly assess areas of risk and weakness we will ensure that Internal Audit continues to add value to the organisation in an efficient and effective manner.

9 In accordance with the Internal Audit Charter, the Committee is asked to review and approve the proposed internal plan 2026/27. In doing so, Members should consider whether:

(a) The scale and breadth of activity is sufficient to allow Internal Audit to provide an independent and objective audit opinion that can be used to inform the AGS.

(b) The level of resources in any way limits the scope of Internal Audit or prejudices the ability to deliver a service consistent with the GIAS.

(c) The level of non-assurance work has an adverse impact on the core assurance work Consultation and Engagement 10 In preparing the Internal Audit Plan 2026/27, consultation has been undertaken to identify the expectations of senior management, external audit, and other key stakeholders (as detailed in Appendix A).

Reasons for recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Internal Audit Plan 2026-27Appendix A 12 pages Download
PDF
for Internal Audit Plan 2026-27Appendix B 211 KB Download
PDF
Internal Audit Plan 2026-27Minutes 145 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Internal Audit Plan 2026-27This decision
  2. Internal Audit Opinion 2025-26Noted
  3. Internal Audit Plan 2025-26 - UpdateNoted
  4. Internal Audit Plan 2025-26Approved
  5. Internal Audit Plan 2024-25 - Progress UpdateNoted
  6. Internal Audit Annual Opinion Report 2023/24Noted

More from Cheshire East Audit and Governance Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Minutes of Previous MeetingThat the minutes of the previous meeting be approved as a correct record . Approved Open
27 Jul 2026 Audit and Governance Committee Action LogThat the action log and updates received be noted. Noted Open
27 Jul 2026 Draft Annual Governance Statement 2025-26That the Audit and Governance Committee received and reviewed the draft AGS 2025/26, noting that the final proposed A... Approved Open
27 Jul 2026 Internal Audit Opinion 2025-26RESOLVED That the Audit and Governance Committee 1. Noted and considered the contents of the Internal Audit Annual Op... Noted Open
27 Jul 2026 Final Outturn and Draft Statement of Accounts 2025/26That the Audit and Governance Committee 1. Noted the summarised position of the accounts for year ended 31st March 20... Noted Open