Local Transport Delivery Plan - Consolidated Funding
ApprovedCommittee1 paper
AI summaryCheshire East Highways and Transport Committee endorses draft Local Transport Delivery Plan for 2026/27 to 2029/30 and recommends Full Council approve supplementary capital and revenue estimates for the new consolidated transport funding.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAuthorises officers to accept grants and recommend spend to Full Council
MoneyNot stated
What happens nextFinal plan to DfT by 18 September 2026Further report due before final submission
Who it affectsNot stated
What was decided
The committee authorised the Executive Director of Resources and the Section 151 officer to accept the Integrated Transport Settlement and Local Bus Fund allocations and to sign and return any Grant Acceptance Letter or Memorandum of Understanding by the required deadlines. Report P4
The committee endorsed the draft 2026/27 to 2029/30 Local Transport Delivery programme as set out in Appendix 4, and recommended to Full Council that supplementary capital and revenue estimates for these grants be approved. Report P5, P6
Authority for commissioning bus services using Local Bus Grant and external funding was delegated to the Executive Director of Place, in consultation with the Cabinet Member for Highways and Transport. Report P9
Why
In December 2025 the Department for Transport told local transport authorities that funding would change, with allocations passed through the Cheshire and Warrington Combined Authority and a draft Local Transport Delivery Plan required to access funding for 2026/27. Report P1, P11
The consolidated settlement brings together several existing transport budgets including the Integrated Transport Block, Bus Service Improvement Plan and Active Travel funds, and is described in the report as a significant uplift on core funding in recent years. Report P10, P16, P17
The draft programme is built around Local Transport Plan priorities, the Local Plan, BSIP, Active Travel Strategy, Highways Asset Management Plan and Rural Action Plan, with projects phased by readiness and match funding opportunities. Report P20, P21, P22
What happens next
A further report on the final Local Transport Delivery Plan will be brought back for decision before the plan is submitted to the Department for Transport by 18 September 2026. Report P3, P8, P14, P25
Further discussions and agreements with the Cheshire and Warrington Combined Authority are required before the final version of the plan is submitted. Report P8
A programme management function will be established for the 2026/27 onwards transport programme, with risk assessment principles embedded, and the Local Transport Delivery Plan is to be reviewed annually under DfT guidance. Report P39
The money
166.96 Total estimated capital spend in Appendix 4 draft programme Report P136
13.36 Total estimated revenue spend in Appendix 4 draft programme Report P136
Options considered
Chosen: Prepare a draft Local Transport Delivery Plan as set out in Appendix 4. Required by the Department for Transport to access core capital and revenue transport funding for Cheshire East Report P30, P6
Rejected: No other options were considered. Preparation of an LTDP has been mandated by the Department for Transport Report P30
Implications
Legal: Decisions must be made within statutory powers under the Highways Act 1980, the Local Transport Act 2008 and the Local Government Act 1972, and in accordance with the Council's Constitution, including Finance and Contract Procedure Rules. Report P33, P34
Financial: The Council must comply with the terms and conditions of any consolidated transport funding received, including monitoring, reporting, eligible expenditure, audit and clawback provisions, with non-compliance potentially leading to penalties or repayment of grant. Report P35
Financial: Changes to the council's capital programme will be subject to appropriate approval routes, and the Section 151 officer must be consulted on financial assurance. Report P37, P9
Staffing: Delivery of the transport programmes will use existing Council staff, with supply chain partners brought in for specific skills or to address resource constraints. Report P37
Risk: There is a general risk of judicial review of significant local authority decisions, to be mitigated by clear evidence-based decision-making and adherence to statutory and policy frameworks. Report P36
Equalities: Equality impact assessments will be carried out for schemes or programmes as they are developed, with accessibility for all community members described as central to the investment programme. Report P49
Climate: The programme supports decarbonisation through investment in walking, cycling, public transport and electric vehicle infrastructure, with carbon and environmental aspects of larger schemes assessed using government appraisal guidance. Report P51, P52, P43
Who and where
Cheshire East Council, as the local transport authority Report P11, P15
Cheshire and Warrington Combined Authority, which will receive and pass on transport funding Report P11, P17
Department for Transport, which is requiring the Local Transport Delivery Plan Report P11, P12
Bus passengers and bus service users in Cheshire East Report P44, P78, P79
Active travel users, including walkers and cyclists Report P43, P80
Residents in rural areas, who may benefit from improved transport inclusion Report P44, P50
Highway users, given the highways maintenance capital allocation Report P78, P89
Timeline
December 2025: Department for Transport wrote to local transport authorities about the change to consolidated funding Report P1, P11
3rd March 2026: Combined Authority received the Memorandum of Understanding and Grant Determination Letter Report P37
10th March 2026: Shadow Board of the Combined Authority approved a paper setting out principles for transport funding Report P17
20th March 2026: Deadline for submission of draft Local Transport Delivery Plan to the Department for Transport Report P7, P13
2 April 2026: Date of Highways and Transport Committee meeting where this decision was taken Report P46
18th September 2026: Deadline for submission of the final Local Transport Delivery Plan to the Department for Transport Report P3, P14, P25
May 2027: Expected date for election of a mayor for Cheshire and Warrington, after which Bus Grant revenue will move into a Mayoral Transport Fund Report P17
Plain English for the jargon
LTDP: Local Transport Delivery Plan, the document required by the Department for Transport to set out how consolidated transport funding will be deployed
LTP: Local Transport Plan, the statutory policy document that sets transport priorities for the area
ITB: Integrated Transport Block, the previous direct grant for smaller highways and transport schemes, now replaced by Local Transport Grant capital
HMB: Highways Maintenance Block, a former grant stream now combined into the Highways Maintenance allocation
BSIP: Bus Service Improvement Plan, the previous programme of bus funding, now replaced by Bus Grant
LEVI: Local Electric Vehicle Infrastructure, a fund supporting on-street and hub electric vehicle charging
LCWIP: Local Cycling and Walking Infrastructure Plan, used to assess Active Travel funding allocations
Section 151 officer: The local authority officer with statutory responsibility for financial administration and proper accounting
Mayoral Transport Fund: Combined funding pot, including Bus Grant revenue, expected to be created once a mayor for Cheshire and Warrington is elected
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item47
Resolved
(By Majority) That the Highways and Transport committee 1.Authorise the Executive Director of Resources and the Section 151 officer to a) Accept the Integrated Transport Settlement and Local Bus Fund allocations to Cheshire East Council. b) Sign and return any Grant Acceptance Letter and/or Memorandum of Understanding for these grants by the necessary deadlines. 2. Recommend approval of Supplementary Capital and Revenue Expenditure estimates for these grants to Full Council. 3. Endorse the draft local transport delivery programme, as summarised in Appendix 4 of the report. 4. Note that the Executive Director of Place, in consultation with the Section 151 officer, authorised the submission of the draft transport programme for 2026/27 to 2029/30 to the Department for Transport, to meet the DfT’s deadline of 20th March 2026, to secure transport funding allocations for 2026/27. 5. Note that further discussions and agreements will be required with the Cheshire & Warrington Combined Authority before a final version of the Local Transport Delivery Plan is submitted to the DfT by September 2026. 6. Agree to delegate authority for commissioning of bus services using Local Bus Grant and external funding to the Executive Director of Place, in consultation with the Cabinet Member for Highways and Transport. ... view the full minutes text for item 47.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
3 In December 2025, Department for Transport (DfT) wrote to all local transport authorities in England, advising that the government is changing the way transport funding is allocated. Funding allocations for 2026/27 year are expected to be passed through to the local authorities from the Cheshire and Warrington Combined Authority.
OFFICIAL 4 DfT guidance explains that a Local Transport Delivery Plan (LTDP) should be prepared, consistent with priorities defined in our Local Transport Plan and other relevant policies. To develop a draft Local Transport Delivery Plan for Cheshire & Warrington, each council has compiled a 4-year programme for its own area, to be collated into an area-wide plan at Combined Authority level.
5 This report seeks endorsement of a draft 2026/27 to 2029/30 programme for Cheshire East (see Appendix 4), enabling the Council to draw down funding for 2026/27. A further report will be prepared for decision on the final Local Transport Delivery Plan, prior to submitting this to Government before their deadline of 18th September 2026.
Recommendations
The Highways and Transport committee is recommended to: 1. Authorise the Executive Director of Resources and the Section 151 officer to a) Accept the Integrated Transport Settlement and Local Bus Fund allocations to Cheshire East Council. b) Sign and return any Grant Acceptance Letter and/or Memorandum of Understanding for these grants by the necessary deadlines.
2. Recommend approval of Supplementary Capital and Revenue Expenditure estimates for these grants to Full Council.
3. Endorse the draft local transport delivery programme, as summarised in Appendix 4. Members should note that there is scope for further changes to the delivery programme, especially in future years, as the Council’s and Combined Authority investment priorities develop.
4. Note that the Executive Director of Place, in consultation with the Section 151 officer, authorised the submission of the draft transport programme for 2026/27 to 2029/30 to the Department for Transport, to meet the DfT’s deadline of 20th March 2026, to secure transport funding allocations for 2026/27.
5. Note that further discussions and agreements will be required with the Cheshire & Warrington Combined Authority before a final version of the Local Transport Delivery Plan is submitted to the DfT by September 2026.
6. Delegate authority for commissioning of bus services using Local Bus Grant and external funding to the Executive Director of Place, in consultation with the Cabinet Member for Highways and Transport. 7. Upon receipt of funding as part of the consolidated settlement to the Cheshire & Warrington Combined Authority, authorise the Executive Director of Place, in consultation with the Cabinet Member for Highways and Transport, to make all necessary arrangements to delivery to 2026/27 transport programmes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Third Financial Review of 2025/26(By Majority) That the Highways and Transport Committee 1. Note the overall Council’s Financial position as described...
Ward Member Budget Scheme UpdateRESOLVED (By Majority) That the Highways and Transport committee Note the progress made to date on the operation of t...
Local Transport Plan - Approval(By Majority) That the Highways and Transport committee 1. Approve the Local Transport Plan (LTP) strategy (Appendix ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.