Resolved
That Council approve the Supplementary Capital Estimate over £1,000,000 as set out in Annex 1, Section 3, Table 5 to the report as follows: Environment and Communities £m Capricorn Access Bridge 2.280
AI summaryCouncil approves £2.280m Supplementary Capital Estimate for feasibility and enabling works on a bridge over a wildlife corridor at the Capricorn local plan site, funded by S106 contributions.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That Council approve the Supplementary Capital Estimate over £1,000,000 as set out in Annex 1, Section 3, Table 5 to the report as follows: Environment and Communities £m Capricorn Access Bridge 2.280
That Council approves the Supplementary Capital Estimate Request over £1,000,000 as per Annex 1, Section 3, Table 5
Link to Finance Sub-Committee Report and Annexes 1 and 2: - Finance Sub Committee 27 April 2026 - Fourth Financial Review 2025/26
Extract from the Minutes of the Finance Sub Committee meeting held on 27 April 2026
57 FOURTH FINANCIAL REVIEW 2025/26
The Committee considered the report on the Fourth Financial Review for 2025/26.
During consideration of the report the Sub Committee raised concerns on the significant and growing SEND overspend, including an unexpected additional £7m pressure. It was explained that this had been driven by higher than forecast demand for EHCP assessments influenced by the anticipated national SEND reforms due in 2029 and by the reliance on independent and non-maintained special schools due to insufficient local provision. Forecasting issues were partly attributed to system upgrades which had improved visibility of pressures rather than creating them.
It was noted that a £0.26m overspend was being reported in SEND transport and it was asked why these costs were not more predictable. It was confirmed that SEND transport pressures were now feeding into future budget planning and that additional transport costs had arisen from statutory school transport duties with transport provision based on distance, age, safety of route and SEND status.
Concerns were raised over continued underspends in the capital programme and the re-profiling of schemes across years. Officers confirmed that movements between financial reports (FR3 to FR4) captured grant timing changes. Work was underway to ensure that no Government grant funding was lost. The Sub Committee emphasised the need for greater member scrutiny and clarity over the capital programmes’ relationship with the revenue budget.
OFFICIAL Reference was made to the Transformation Programme, and concerns were raised on the rising costs and uncertainty of delivery of the promised savings. Officers acknowledged the delays to the Target Operating Model and attributed this to slippage rather than abandonment. The Programme was currently focusing on management span and layers, reduction of use of agency staff, sickness absence and productivity improvements. The savings had been reprofiled into future years with the current year risks flagged as ‘red’.
The Sub Committee was being asked to recommend to Council the approval of a Supplementary Capital Estimate of £2.280m for the feasibility and enabling works for a new structure over the wildlife corridor to allow development of the Capricorn local plan site, with the funding from S106 contributions. It was confirmed that the proposals met the legal requirements for the use of S106 monies. Members noted historic delays to the site and the 10-year deadline to spend the funds.
RESOLVED: That the Sub Committee
1 note the factors leading to a forecast balanced position and note the contents of Annex 1, Section 2 which details progress on the delivery of the MTFS approved budget policy change items, the RAG ratings and the latest forecasts and note the actions to be taken to address any adverse variances from the approved budget.
2 note the in-year forecast capital spending of £137.915m against an original capital budget (at outturn) of £208.491m.
3 note the approved Supplementary Capital Estimates and Capital Virements up to £500,000 as per Annex 1, Section 3, Table 3.
4 note the Capital Virements above £500,000 up to and including £5,000,000 to be approved in accordance with the Council’s Constitution as per Annex 1, Section 3, Table 4.
5 Recommend to Council to approve the Supplementary Capital Estimate Request over £1,000,000 as per Annex 1, Section 3, Table 5.
6 note the Capital Budget Reductions as per Annex 1, Section 3, Table 6.
7 note the available reserves position as per Annex 1, Section 4.
OFFICIAL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Section 3 Table 5Appendix 1 | 86 KB | Download |
PDF |
Recommendation from Finance Sub Committee: Fourth Financial Review 2025/26 Approval of Supplementary Capital EstimateMinutes | 126 KB | DownloadRead as text |
Follow Council at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Minutes of Previous MeetingThat the minutes of the meetings held on 13 May 2026 be approved as a correct record, subject to following amendment:... | Approved | Open |
| 15 Jul 2026 | Recommendation from Cabinet: Final Outturn 2025/26 Approval of Supplementary Revenue and Capital EstimatesRESOLVED (by majority): That Council 1 approve the Supplementary Revenue Estimate requests for allocation of addition... | Approved | Open |
| 15 Jul 2026 | Appointment of Director of Law and Governance (Monitoring Officer)RESOLVED (by majority): That Council approve the appointment of [name removed] as the Director of Law and Governance ... | Approved | Open |
| 15 Jul 2026 | Approval of Absence from Council MeetingsRESOLVED (unanimously): That Council approve Councillor David Brown’s absence from Council meetings for a period of o... | Approved | Open |
| 15 Jul 2026 | Notices of MotionThat the Motion be referred to the Licensing Committee. 2 Peak Cluster Proposed by Councillor L Smetham and Seconded ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.