RESOLVED – 1) That the Business Plan Monitoring Statement report be noted. 2) That the Chair of Development Control Committee and the Executive Member for Development and Regeneration be invited to a future meeting of the Panel to discuss the performance of the Development and Regeneration Directorate.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report to Environment and Community Overview and Scrutiny Panel
Environment and Community Overview and Scrutiny Panel First Quarter Business Plan Monitoring Reports BUSINESS PLAN MONITORING STATEMENT FOR THE STREETSCENE, NEIGHBOURHOODS AND ENVIRONMENT DIRECTORATE
FOR THE PERIOD APRIL TO JUNE 2006
1. KEY MESSAGES
Streetscene, Neighbourhoods and Environment is a new Directorate constituted from former Environmental Services and Public Space Services Units and the Community Safety elements of the former Corporate Policy Unit.
The Directorates core service developments are:
Implementation of the Clean Neighbourhoods and Environment Act from Spring 2006. (Link to Corporate Strategy Outcome 5.1)
Progress-The provisions have been adopted by report to Executive Cabinet. The enforcement procedures and fixed penalty regime are being revised for a phased introduction over 2006- action needs to be taken to secure this continued implementation through the PCSO pilot.
Implement a recycling cost share agreement with the County Council and successfully deliver Chorley Borough Council’s elements of the contract. Project incorporating an Annual update of eligible properties for claims. (Link to Corporate Strategy Outcome 6.1)
Progress- The cost share agreement has been agreed and signed. This is a 10 year agreement from 2004 between Chorley Council and Lancashire County Council which supports the provision of the enhanced recycling service in Chorley. The final part of the implementation for Chorley was the introduction of the textile recycling service. There is a remaining obligation which has been previously reported which is the introduction of kitchen waste collections to non- garden properties. This will be introduced as part of the new service from April 2009 or later subject to the provision of in vessel composting facilities at Leyland Waste Technology Park.
Deliver improving levels of Customer Satisfaction with the waste and recycling service (Link to Corporate Strategy Outcome 6.1)
Progress- Surrogate measures of satisfaction show general improvement-see later comments about the missed bin score. Clearly satisfaction levels have declined following the introduction of the enhanced recycling service and an action plan is in place to improve this. Included in this is the delivery of the wind resistant sacks and the securing of some additional investment in plant and equipment from Cleanaway which has been divorced temporarily from the Chorley Council element of the partnership plan due to delays in the approval of capital schemes.
Establish 24 Hour reception points for stray dogs (Legislative)
Progress- no action has been taken on this as the requirement has not been passed to Local Authorities due to legislative delays. The responsibility will pass when DEFRA and the Home Office have agreed the necessary finance transfer, probably from April 2007. Assist with the preparation of pandemic flu precautions and controls (infectious disease control element) (Legislative)
Progress- several multi agency table-top exercises have taken place to exercise the control plan. There have been several alerts concerning unexplained deaths of migratory birds in the spring, however all these have proved inconsequential.
Undertake update and screening assessment of Air Quality- 2006/2007 and implement any 12 month action plans which may arise from the finding of screening assessment (Legislative)
Progress- Traffic and modelling data has been updated in order to undertake an update of the current assessment for 2006. Some of this data modelling and the predictions were tested as part of the Tarmac application for Euxton sand quarry. The update itself should be completed for November 2006. The update is essentially a table top exercise and relies on surrogate and modelled data with a very limited amount of actual measurement due to the very high cost of gathering and validating this. The update will be subject to validation by the University of the West of England.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Community Overview and Scrutiny Panel at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of Chair for the MeetingRESOLVED that Councillor Adrian Lowe be appointed to Chair this meeting of the Panel. The Panel Members wished it to ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.