Environment Overview and Scrutiny Business Plan Monitoring Statements Second Quarter 2006/07
1 Contents
Development and Regeneration Business Plan Monitoring Statement
Leisure and Cultural Services Business Plan Monitoring Statement
Housing Services Business Plan Monitoring Statement
Streetscene, Neighbourhoods and Environment Business Plan Monitoring Statement
Note of Clarification
Key Performance Indicators:
Symbols and Colours are used to provide a quick guide to how Service Units are performing against Key Performance Indicators:
= Gree Performance is five percent or more above the n KPI target set for this indicator
= Performance is on track and within the five Blue KPI percent tolerance set for this indicator.
= Red Performance is 5% or more below target. KPI
NB. The tolerances for Budget spend are calculated differently to all other indicators, as these need to be more sensitive to changes in performance and this is a plan is best indicator. Red Triangle performance is 2% or more outside of the target (100%). Blue Circle performance is between 2% and 1% outside of the target. Green Star performance is within 1% of Target
For further information on the way in which Performance Symbols are calculated please contact Sarah Dobson (01257 515325) in Policy and Performance.
2 BUSINESS PLAN MONITORING STATEMENT FOR THE DEVELOPMENT AND REGENERATION DIRECTORATE
FOR THE PERIOD JULY TO SEPTEMBER 2006
1. KEY MESSAGES
All key projects set out in the Business Plan are on track. An agreement has been reached with GONW as to how to take forward the Local Development Framework preferred options documents.
Development Control Performance – An action plan has been put in place with regards major applications.
The e-planning project is now well underway. Linked with this is Business Process Re-engineering and our current processes are being scrutinised in order to establish how they can be improved.
SERVICE PERFORMANCE INDICATORS CURRENT FORECAST POSITION OUTTURN
Number of green PI’s 4 Number of blue PI’s 0 Number of red PI’s 2 Number of PI’s not yet measured 1
2. BUDGET UPDATE
DEVELOPMENT & REGENERATION
SEPTEMBER 2006 £'000 £'000
ORIGINAL CASH BUDGET 891
Add Adjustments for In year cash movements
Slippage from 2005/2006 - Use of AMF Reserve Virements for other Services Private Lifeline Alarms (41) Asset Maintenance 5 Transfer from contingency - Adjustments To External Recharges 16
ADJUSTED CASH BUDGET 871
Less Corporate Savings - Vacancy savings (30) Less Corporate Savings - Hospitality (1)
CURRENT CASH BUDGET 840
FORECAST
3 EXPENDITURE
Legal Fees invoice paid twice in 2005/06, corrected in 2006/07 (6) Salary savings for the financial year 2006/2007 (40) Peter Coxhead salary to 24/11/06.(finishing date) No budget provision 25
Expenditure under (-) or over (+) current cash budget (21)
INCOME Shortfall on income compared to profile as at 30th Sept 2006: Planning Application Fees (42) Building Control Plans Fees 13 Building Control Inspection Fees 50
Income under (+)/ over (-) achieved 21
FORECAST CASH OUTTURN 2006/2007 840
Key Assumptions Two vacant posts remain vacant for remainder of 2006/2007: Housing Needs and Investment Manager Urban Designer/Conservation Officer Key Issues/Variables
Key Actions An overview of the Building Control Income Jane Meek to promote the BC function to the commercial market
3. SERVICE DEVELOPMENTS
Economic Regeneration Strategy – An LSP workshop event is due to be held on 27 November to help develop an action plan.
Strategic Regional Site – LEX is now completed and is due to open in November.
Town Centre Strategy – The Strategy and Action Plan are due to go to Executive Cabinet in October and project plans for each key action are being developed.
Transport Accessibility Plan – Work has commenced with Lancashire County Council on an accessibility plan.
Prevention of Homelessness Strategy is currently being developed. This will then be sent out for consultation in October.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Business Plan Monitoring Statement: Second QuarterReport | 805 KB | DownloadRead as text |
Follow Environment and Community Overview and Scrutiny Panel at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Mar 2008 | Appointment of Chair for the MeetingRESOLVED that Councillor Adrian Lowe be appointed to Chair this meeting of the Panel. The Panel Members wished it to ... | Agreed | Open |
| 17 Mar 2008 | MinutesRESOLVED – That the of the meeting of the Environment and Community Overview and Scrutiny Panel held on 24 January be... | Decided | Open |
| 17 Mar 2008 | Scrutiny Inquiry - Chorley Town Centre Audit and Design StrategyNoted | Noted | Open |
| 17 Mar 2008 | Business Plan Monitoring Statements - 1 October 2007 to 31 December 2007Noted | Noted | Open |
| 17 Mar 2008 | Overview and Scrutiny Work Programme 2007/08RESOLVED – That the Programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.