Chorley Council Housing Stock Transfer Highlight Report
PROJECT DOCUMENTATION
HIGHLIGHT REPORT
Chorley Council Housing Stock Transfer
Version: 16
Date: 03/01/07
This Project utilises Chorley Borough Councils Project Management Methodology
Author: Helen Schofield
Project Manager: Helen Schofield
Programme Board: Housing Transfer Negotiating Group
Page 1 Chorley Council Housing Stock Transfer Highlight Report
Date of Report 03/01/07
Period Covered
From September 2005 to December 2006
Overall Project Status G
A positive ballot result was achieved on August 8th with 69.6% of tenants voting, and 63.1% of those who voted, voted ‘Yes’. The result was accepted and approval given to proceed with the transfer (subject to contract and Secretary of State’s consent) and the post ballot arrangements by the Executive Cabinet on August 24th and full Council on 19 September 2006.
The post ballot stage is proceeding to plan with no exception reports to date. All current indications point to the project remaining on track with completion of transfer taking place by the target date of 26 March 2007.
Budget Status G
The post ballot budget has now been agreed by the Council and Section 25 consent for the set up costs loan to CCH has been approved by the Secretary of State for Communities and Local Government.
Spent this period Spent to date Balance 91,000 359,215 1,116,785 This includes interest on the loan and non-recoverable VAT and is the total of both budgets.
Schedule Status G
The project plan is currently on track, with all items/tasks assigned.
Products Completed G
• Pre ballot and ballot stage complete • Stage 2 ended 8th August • Positive ballot result achieved • • Stock condition survey completed by FPD Savills • Implications of stock condition successfully incorporated in draft business plan • • Environmental survey commissioned – to include asbestos • Survey ready in draft form • Classification of HRA nearing completion • Draft report on future arrangement for Homelessness Service issued • Homelessness report has been reviewed and now completed – been reviewed by Councils consultants, awaiting comments from the Director Of Finance • • Repository now on netstore for all documents
Page 2 Chorley Council Housing Stock Transfer Highlight Report
• Disengagement issues identified and meeting held on 21st April – updates have now been collated and a more detailed approach will be taken at the Disengagement Sub Group • Post ballot consultants for Council have now been appointed – Lead are Enterprise BWNL and Legal are Trowers and Hamlins. Tribal and Wright Hassall have been retained as the lead and legal advisors respectively to CCH
• 1st post ballot report went to the Exec Cabinet on 24th August • A Housing Transfer Committee has been set up to meet on the same day as the HTNG meetings. • Negotiating structures have been drawn up and staffing arrangements set up • Extra sub groups have been established – Asset, Disengagement and Finance and are due to meet monthly • CCH has also established extra groups – Project Management Board, CCH/Adactus liaison group, engagement group and finance group • The Corporate Team has gained an ICT Project Manager, a Corporate Transfer Accountant and the part time Project Assistant’s role has become a full time Project Officer.
• The Section 25 letter has now been sent • VAT Advisor has now been appointed - PWC • Draft environmental survey has been received, reviewed by Trowers and Hamlins and a second draft has now been requested from RPS in light of their comments. • Risk management consultant to be appointed. Tenders have gone out. • 1st draft of the Transfer Agreement has been discussed by the Council • Review of post ballot stage by Audit Commission has started – HS has sent documents etc. and interviews are being arranged with the Audit Commission.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Stock Transfer: Project HIghlights ReportReport | 271 KB | DownloadRead as text |
Follow Housing Transfer Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2007 | Exclusion of Press and PublicRESOLVED – that the press and public be excluded from the meeting during the consideration of the following items of ... | Decided | Open |
| 22 Mar 2007 | Adjournment of MeetingRESOLVED – That the meeting be adjourned to resume at 2.00pm on Friday, 23 March 2007 to consider (i) an update on th... | Agreed | Open |
| 22 Mar 2007 | Transfer Completion ArrangementsRESOLVED – (1) That, subject to Resolution (2) below, approval be given to the transfer of the Council’s housing stoc... | Approved | Open |
| 21 Feb 2007 | Housing Stock Transfer - Projects Highlight reportRESOLVED – That the report be noted. | Noted | Open |
| 21 Feb 2007 | Exclusion of Press and PublicRESOLVED – That the press and public be excluded from the meeting for the following items of business on the ground t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.