Resolved
RESOLVED – That the current practices and procedures continue and the report be noted.
Overview and Scrutiny Committee noted this item on Tuesday 20 February 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the current practices and procedures continue and the report be noted.
4. There are three BVPI’s relating to planning applications and these are set out as follows: -
Best Value Performance Indicator Target
109a Major Planning Applications 60% of applications within 13 weeks
109b Minor Planning Applications 65% of applications within 8 weeks
109c Other Planning Applications 80% of applications within 8 weeks
Figures on planning applications are reported to the Department of Communities and Local Government (DCLG) through the Councils PS1/PS2 returns on planning applications. The DCLG requires 100% compliance with these targets. Failure to meet any of the three targets would result in: -
i. The Council becoming a standards authority which may involve intervention from appointed Inspectors; Continued.... ii. Impact on the amount of Planning Delivery Grant (PDG) that the Council will receive. Although this will change after March 2007 there is no indication as yet what criteria will be considered in assessing PDG monies.
iii. Impact on CPA re-assessment
5. Since March 2004 the Council has met with all the required BVPI’s relating to planning applications. This has had the effect of securing PDG monies, which has assisted the Council in improving performance and also funded the E-planning project, which is fundamental in providing full e-access to planning applications for the Chorley community. This is due to go live in April 2007.
6. Major applications which are the more complex ones are defined as: -
i. Applications for at least 10 new residential units;
ii. Residential sites of 0.5 hectares or more;
iii. The creation of or change of use of 1,000 sq metres or more of non-residential gross floorspace;
iv. And non-residential sites of over 1 hectare in size.
7. There is limited time available to deal with planning applications. For the majority of applications this is 8 weeks. Major planning applications, which are the more complex cases, have 13 weeks in which to be determined. During the process of dealing with an application it may become apparent that further information or amendments are necessary before it may be considered acceptable. For example it is a requirement under the Habitats Directive that where there is a potential for protected species to be affected that an appropriate ecological study must be provided with the application. This cannot be conditioned through a planning permission and certain studies such as for Great Crested Newts and bats can only be conducted at certain times of the year.
8. In such circumstances the applicants are advised to withdraw the application or it will be refused on the basis of lack of information or an unacceptable scheme. This is not an unusual situation and all Local Planning Authorities apply the same practice. Most applicants prefer to withdraw the application and then re-submit with all the appropriate detail. To defer the applications until all the information has been submitted is not an advisable option as this would take those applications over the 8 or 13-week period and therefore miss the target date. There is no opportunity to “stop the clock ticking” in such circumstances and to do so would leave the Council open to criticism which may impact on PDG awards where BVPI’s have been qualified and meeting the actual BVPI’s themselves.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Services Best Value Performance Indicators-Decisions on Major Planning ApplicationsDecisions | 456 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of meeting Thursday, 26 March 2026 of Overview and Scrutiny CommitteeResolved (unanimously): That the minutes of the meeting held on Thursday, 26 March 2026 be approved a correct record ... | Approved | Open |
| 2 Jul 2026 | Minutes of the Overview and Scrutiny Performance Panel held on Thursday, 25 June 2026Resolved (unanimously) – That the minutes of the Overview and Scrutiny Performance Panel, held on Thursday, 25 June 2... | Noted | Open |
| 2 Jul 2026 | Notice of Executive DecisionsResolved (unanimously) – That the latest Notice of Executive Decisions July 2026 be noted. | Noted | Open |
| 2 Jul 2026 | Chorley Leisure Scrutiny UpdateResolved (unanimously – 1. That the Executive Member for Early Intervention and the officers be thanked for their att... | Decided | Open |
| 2 Jul 2026 | Update from the Representative on the LCC Health and Adult Social Care Scrutiny CommitteeResolved (unanimously) – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.