Business Plan Monitoring Statements - 1 April to 31 June 2007

Noted Scrutiny 3 papers

Environment and Community Overview and Scrutiny Panel noted this item on Thursday 13 September 2007. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

The Panel received the first quarter Business Plan Monitoring Statements for the period 1 April 2007 to 30 June 2007 relating to the undermentioned Directorates whose service and function all fall within the remit and area of responsibility of the Panel. ? Leisure and Culture ? Development and Regeneration ? Streetscene, Neighbourhoods and Environment Further to Minute 07.ECS.11 the Director of Finance attended the meeting to answer Members’ questions specifically on the process changes and their effect on the system of payment of invoices. Over the previous Monitoring Statements the Panel had noticed that the performance target for the processing of invoices within 30 working days for many Directorates had not been achieved and that immediate action was required to improve performance. The Director of Finance informed the Panel of the process of the payment of invoices moving away from the previous paper system to a new e-enabling process. There was now a change in emphasis in terms of financial control and it had taken time for key members of staff to become acquainted with the new system. Staff were now trained up and there was a now a marked improvement in performance. In relation to the Business Plan Monitoring Statement for Leisure and Culture, Members asked questions regarding the transfer of community centres into community management and that the Tatton Community Centre had now been transferred even though it had not met the scheduled date of 1 September 2007. There would be other transfers taking place including Eaves Green and Gillibrand. The Director of Development and Regeneration presented the Panel with her Business Plan for her Directorate. The Director notified Members of the impact on her Directorate of the vacant posts and the progress on filling these posts. Some of the vacancies had been filled and those posts currently being advertised, an encouraging response had been received. The Director of Streetscene, Neighbourhoods and Environment circulated his Business Improvement Plan Monitoring Statements for his Directorate. The Director highlighted the area of performance below target, indicating missed collections per 100,000, percentage racist and offensive graffiti removed within two working days, percentage of graffiti removed within 28 working days and sickness absence. Action Plans had been compiled to address these issues. Members noted that two working groups had been established to find improvements in customer satisfaction with kerbside recycling and cleanliness of the Borough. Service Improvement Plans had been prepared, with the Working Groups required to report by 30 November with a thorough review of satisfaction and dissatisfaction issues with recommendations for improvements. Some Members expressed concern at the emptying of some litter bins in the Borough as some had been found to be overflowing. The mechanism for reporting the emptying of litter bins was not working satisfactorily and schedules had not been adhered to. These concerns would be subject to the review of satisfaction and dissatisfaction. RESOLVED – 1) That the report be noted. 2) That the Director of Finance submits a report later in the Municipal Year on the performance of the processing ...
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Environment and Community Overview and Scrutiny Panel

BUSINESS IMPROVEMENT PLAN MONITORING STATEMENT FOR THE STREETSCENE, NEIGHBOURHOODS AND ENVIRONMENT DIRECTORATE

FOR THE PERIOD APRIL - JUNE 2007. 1. KEY MESSAGES

Significant progress has been made on most of SNED's key tasks as shown below The key projects are important for the successful delivery of the Council's Corporate Strategy, however most of the SNED workforce are engaged in "Business as usual" activities. These activities also contribute greatly to service improvement and a large number of incremental improvements and other achievements can be recorded which are not necessarily manifest in general performance monitoring activity and which would otherwise go unacknowledged. Amongst these I include:

The delivery of a large number of Capital schemes to provide improved play opportunities, cemetery development, woodland management, and highway safety improvements. Completion of the Chapel St. paving project. A range of Public Health regulatory functions contributing to reduced incidence of infectious disease, pollution, workplace safety improvements and food safety. Moving forward 20 alley gating schemes due for completion in 2007-8. The development of the Town's floral bedding displays and Gold Medal achievement at Southport flower show. Maintenance of grass cutting standards during the wettest year in living memory. SNED's contribution to improved customer service by helping to develop the service of the Contact Centre and designing and trialing for commission later this year a mobile working solution to information management and use in the support of neighbourhood environmental improvement.

BP_Monitoring_Template 06 2. BUDGET UPDATE

£'000 £'000

ORIGINAL CASH BUDGET 4,988

Add Adjustments for In year cash movements Slippage from 2006/2007 - - Use of AMF Reserve Virements from other Services - Transfer Christmas Lights budget from CUDLS 20

ADJUSTED CASH BUDGET 5,008

Less Corporate Savings - Vacancy savings

CURRENT CASH BUDGET 5,008

FORECAST

EXPENDITURE Target Bonus recycling contract 30 DPE cash collection costs 38 Protected Salary payments 11 PILON, severance pay and settlement costs 39 Town Centre paving: general repairs 8 Scrutiny Inquiry - Neighbourhood Working 5 Land drainage works: Whittle le Woods drain 5

CPSREP/86792JM2 Expenditure under (-) or over (+) current cash budget 136

INCOME Reduction in lost car parking income following delay in Market Walk project (178) Grounds Maintenance charges to Parish Councils (10) Town Centre paving: S106 contribution (8)

Income under (+)/ over (-) achieved (196)

FORECAST CASH OUTTURN 2007/2008 4,948

Key Assumptions Reduction in lost car parking income following delay in contract start for Market Walk Phase 2. Assumed start date for development to be 1 January 2008. Saving to be offset by increase in cost of Net Financing.

Key Issues/Variables Tonnages of recyclate collected expected to be higher than budgeted. Town Centre paving general repairs financed by S106 contribution. High demand for pest control services necessitating employment of external contract staff. Financial effect to be quantified. Cost of Land drainage works may be recharged to contractor if liability can be proved.

Key Actions Closely monitor tonnages of recyclate collected and report financial effect on recycling bonus payments Monitor pest control costs and income and report adverse variances as soon as possible.

CPSREP/86792JM2 3. SERVICE DEVELOPMENTS

Neighbourhood management and engagement strategy

The Scrutiny Inquiry has completed all its evidence hearings and visits and agreement reached on a proposition to be put forward to recommend a mechanism for neighbourhood working in Chorley.

Town Centre car parking

Proposals have been written and accepted to resolve the issue of shortage of car parking space during the construction of Market Walk 2 and the new registry office. Alterations to tariffs, re-marking and minor works to car parks will produce additional spaces equivalent to those lost during construction.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BP Monitoring ReportSNED June 2007Report 478 KB DownloadRead as text
PDF
Business Plan Monitoring Statements: 1 April to 31 June 2007Report 507 KB Download
PDF
DevelopmentRegenerationReport 411 KB Download

At this meeting

Whole meeting
19MinutesAgreed
21Business Plan Monitoring Statements - 1 April to 31 June 2007This decision
22Overview and Scrutiny Work ProgrammeNoted

Who was there

12 of 22 attended
GM
Councillor Greg MorganChair, present
NB
Nora BallCommittee Member, apologies
JB
Judith BoothmanCommittee Member, present
MC
Magda Cullens (profile used as a Councillor)Committee Member, present
MD
Mike Devaney (profile used for Cllr)Committee Member, present
DD
Councillor Doreen DickinsonCommittee Member, present
AG
Anthony GeeCommittee Member, present
CH
Catherine HoyleCommittee Member, expected
KI
Councillor Keith IddonCommittee Member, present
MA
Councillor Margaret Ann IddonCommittee Member, apologies
KJ
Kevin JoyceCommittee Member, present
RL
Councillor Roy LeesCommittee Member, apologies

All 22 on the meeting page

On this subject at Chorley

Search all
  1. Business Plan Monitoring Statements - 1 April to 31 June 2007This decision
  2. Business Plan Project Update Quarter One 2025/26Noted
  3. Business Plan Update 2024/25Noted
  4. Consideration of Revision to the Statement of Licensing Policy for Pavement Licences under the Business and Planning Act 2020Noted
  5. Business Plan Update 2023/24Noted
  6. Business Plans Update 2022-23Noted

More from Chorley Environment and Community Overview and Scrutiny Panel

All decisions
MeetingDecisionOutcome
17 Mar 2008 Appointment of Chair for the MeetingRESOLVED that Councillor Adrian Lowe be appointed to Chair this meeting of the Panel. The Panel Members wished it to ... Agreed Open
17 Mar 2008 MinutesRESOLVED – That the of the meeting of the Environment and Community Overview and Scrutiny Panel held on 24 January be... Decided Open
17 Mar 2008 Scrutiny Inquiry - Chorley Town Centre Audit and Design StrategyNoted Noted Open
17 Mar 2008 Business Plan Monitoring Statements - 1 October 2007 to 31 December 2007Noted Noted Open
17 Mar 2008 Overview and Scrutiny Work Programme 2007/08RESOLVED – That the Programme be noted. Noted Open