The Chair accepted as urgent, consideration of this item, not included on the agenda in order for members of the Committee to receive clarification on the Council’s shared financial service arrangements with South Ribble. The Assistant Chief Executive (Business Transformation and Improvement) clarified the proposals for Chorley and South Ribble Councils to share financial services. He clarified the robustness of the projected financial arrangements and explained the proposed joint working arrangements will be delivered as well as the contingency plans in the event of the joint working arrangements not being realised. A report will shortly be submitted to the December Executive Cabinet setting out the proposals and arrangements.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report of Meeting Date Deputy Chief Executive/Executive Director – Corporate & Customer and the Assistant Chief Executive Overview and Scrutiny Committee 1October 2007 (Business Transformation and Improvement)
DRAFT CAPITAL PROGRAMME MONITORING 2007/08
PURPOSE OF REPORT 1. To update members on the progress of the 2007/08 Capital Programme, and to seek member support and approval for a number of recommendations from the Corporate Improvement Board.
RECOMMENDATION(S)
2. That the revised capital programme for 2007/08 in the sum of £8,673,310 be approved
EXECUTIVE SUMMARY OF REPORT 3. This report seeks approval to requested amendments and additions to the 2007/08 capital programme following a recent monitoring exercise and Corporate Improvement Board meeting.
REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted) 4. To ensure that the Capital Programme reflects and is capable of assisting the delivery of the Council’s corporate priorities
ALTERNATIVE OPTIONS CONSIDERED AND REJECTED 5. None
CORPORATE PRIORITIES
6. This report relates to the following Strategic Objectives:
Put Chorley at the heart of regional a Improved access to public services a economic development in the central Lancashire sub region Improving equality of opportunity a Develop the character and feel of a and life chance Chorley as a good place to live Involving People in their a Ensure Chorley is a performing a Communities Organisation
Updated Template July 2007 BACKGROUND
7. On 28th June 2007 Executive Cabinet approved the 2007/08 capital budget of £8,383,450. The programme is now forecast to be £8,798,310 and significant reasons for this increase are given below. A detailed analysis of the programme showing the changes is shown at Appendix 1.
CAPITAL PROGRAMME MONITORING 2007/08
8. The latest Capital Programme forecast for 2007/08 shows a increase in the programme of £414,860 to £8,673,310. The principal reasons for this are: (a) Capitalised Restructuring Costs. An increased cost of £599,940 is largely associated with ongoing restructures. An application to CLG to have these costs capitalised will be submitted but we will not know whether we have been successful until later in the year. There is a small risk to the Council if approval is not received but if this the case the Council has the option of amortising the costs into the revenue account thereby replacing the capitalisation costs. The restructuring which result in the capitalisation cost will generate significant savings (b) Thin Client. There has been some re-phasing of the thin client budget but due to the fact that we are able to use existing kit to host thin client we are not required to replace all our kit at once. This will result in an estimated in year saving of £248,850 (c) There is a requirement to fund the cost of repairs at Cotswold House. This is a term of the contract with CCH and a condition survey has highlighted urgent works. It is intended to use the Regional Housing Pot Capital Grant budget to finance the estimated £40,000 repair cost (d) An increase of £55,000 is required to fund the staff costs associated with the Home Improvement Agency administration of grants. Again the Regional Housing Pot Capital Grant budget will be used to fund this expenditure. (e) The net decrease of £95,000 in the Regional Housing Pot Capital Grant budget leaves £693,000 remaining. (f) We have received government grant of £26,760 for Building Safer Communities and members will be informed of the way this money is proposed to be spent at the next Executive Cabinet meeting. (g) As a term of the contract, inflation needs to be added to the budget of £200,000 for Leisure Centre Capital Investment. This has been calculated at £39,470 for three years starting 2005/06.
HOW ARE WE PERFORMING?
9. High level monitoring of the capital programme is carried out through 3 performance indicators, which have been described in previous Executive Cabinet reports. Table I lists these and shows targets and current performance.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Chorley Leisure Scrutiny UpdateResolved (unanimously – 1. That the Executive Member for Early Intervention and the officers be thanked for their att...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.