Resolved
RESOLVED – That the report be noted.
Audit Committee (now Governance Committee) noted this item on Thursday 17 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted.
Data Quality Action Plan 2007/08
Action Responsibility Comments Date Status Update
Provide briefings on data quality to Members of the Audit Sarah Dobson/ Gary Ongoing A briefing has been th Committee. (R1) Hall arranged on the 17 January 2008. th To strengthen arrangements for planning and monitoring Sarah Dobson/ Gary Ongoing 17 January 2008 improvements in data quality: Hall • Develop the action plan component of the current data Update paper quality strategy as a separate and formal strategy which sets out objectives for improving data quality, agreed in conjunction with services areas and supported by specific targets. • Provide periodic reports on the progress on implementing the strategy to the Audit Committee. (R2) In revising the data quality strategy develop the policy component Sarah Dobson Jan 2008 Briefings have been as a separate document to provide more detail for service areas given to strategy group on requirements for each stage of data collection, collation and and key officers on reporting. This should include: arrangements for third • Greater clarity on arrangements that need to be put in party reporting. place for ensuring the quality of data for third parties • The checks and reviews of data validity expected to be Meetings have been undertaken in service areas (R3) held with directors to identify all instances of third party reporting. Data Quality Action Plan 2007/08
Action Responsibility Comments Date Status Update Strengthen internal processes for ensuring data quality by: Sarah Dobson • Agreeing and implementing a programme of periodic reviews of the security of Performance Plus. • Investigating the potential for integrating service based systems with Performance Plus as part of the data quality strategy and ensuring that any actions identified by this review are reflected in the implementation plan. (R4) Strengthen arrangements for ensuring the quality of data provided Sarah Dobson Jan 2008 All instances of data by third parties by: Directors sharing have been • Undertaking a systematic review of all instances of data mapped and protocols sharing have been produced for • Ensuring that the arrangements, as set out in the data the majority, with quality policy, are in place for instances of data sharing. ongoing work to produce (R5) the remaining instances. Put arrangements in place which Sarah Dobson A new dialogue has • Systematically identify all new starters with responsibility been developing which for data quality. identifies new starters • Ensure that new starters for data quality consistently with data quality receive appropriate training within an agreed period of responsibilities. These their start date with the Council. are then flagged up to policy and performance who then identify training needs. As part of personal development reviews for relevant staff, Sarah Dobson/ Rik include: Sterken • Data quality objectives that link to the objectives defined in the data quality strategy • An assessment of progress/performance against these objectives in subsequent reviews. (R7) Improve the survey packs issued to Neighbourhood Officers at the Chris Sinnott/Simon start of each BVPI199 survey period by including: Clark • Guidance on the number of transects by land use type Data Quality Action Plan 2007/08
Action Responsibility Comments Date Status Update they will have to review in their neighbourhoods within that survey period. • A reminder of the need to ensure even distribution of reviews throughout the week and avoid weekends. Develop a two page short guide to the steps to take to ensure Sarah Dobson Jan 2008 good data quality
Undertake data quality spot checks on a quarterly basis Directorate Data Ongoing Ongoing Quality Leads Sarah Dobson/ Dawn Highton Revise the data quality strategy Sarah Dobson Jan 2008 Underway
Develop detailed procedures for all Community and Corporate Sarah Dobson/ Chris Jan 2008 Underway Strategy Indicators Sinnott/ Claire Thompson/ Directors
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Data Quality Action Plan 2007 08_Report | 29 KB | DownloadRead as text |
PDF |
Data QualityReport | 159 KB | Download |
Follow Audit Committee (now Governance Committee) at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Mar 2012 | Internal Audit Plan 2012 -13RESOLVED – That the report be noted. | Noted | Open |
| 15 Mar 2012 | Anti Fraud Corruption PoliciesRESOLVED – 1. That the report be noted. 2. That the Chair of Audit Committee write to all Members of the Council to e... | Noted | Open |
| 15 Mar 2012 | Audit Committee Update 2011/12RESOLVED – That the report be noted. | Noted | Open |
| 15 Mar 2012 | Strategic risk update reportRESOLVED – That the report be noted. | Noted | Open |
| 19 Jan 2012 | Annual Audit Letter 2010/11RESOLVED – That the Audit Letter for 2010/11, as presented by the Audit Commission, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.