10/00792/FULMAJ - Parcel L Buckshaw Avenue, Buckshaw Village, Lancashire

Approved Planning 3 papers

Development Control Committee approved this item on Tuesday 16 November 2010. Below is the council's own wording, with the papers it was decided on.

Item212g

Resolved

Permit full planning permission subject to conditions. It was proposed by Councillor Ralph Snape, seconded by Councillor Simon Moulton and subsequently unanimously RESOLVED – To permit full planning permission subject to the following conditions: 1. The proposed development must be begun not later than three years from the date of this permission. Reason: Required to be imposed by Section 51 of the Planning and Compulsory Purchase Act 2004. 2. The development hereby permitted shall be carried out in accordance with the following approved plans: Drawing Number: Stamp Dated: Title: 410/SL01 1 November 2010 Site Location Plan 410/PL 01 1 November 2010 Planning Layout 293/10/ED/11 1 November 2010 Development Plan 410/RSL 01 1 November 2010 Refuse Strategy Layout 410/BTL 01 1 November 2010 Boundary Treatments Layout 410/ML 01 1 November 2010 Materials Layout 410/T/MAL/01 2 September 2010 Malvern Plans and Elevations 410/T/KNI/01 2 September 2010 Knightsbridge Plans and Elevations 410/T/HAR/01 2 September 2010 Harrow Plans and Elevations 410/T/LYM/01 2 September 2010 Lymington Plans and Elevations 410/T/RAV/01 2 September 2010 Ravenfield Plans and Elevations 410/T/ASC/01 2 September 2010 Ascot Plans and Elevations 410/T/ALD/01 2 September 2010 Alderney (brick option) Plans and Elevations 410/T/ALD/02 2 September 2010 Alderney (render option) Plans and Elevations WF01 Rev A 2 September 2010 Walls and Fences H5463-G01 1 November 2010 Triple Detached Garage – Typical Elevations H5463-G01 1 November 2010 Triple Detached Garage – Typical Plans, Elevations & Roof Plan H5463-G01 1 November 2010 Single Detached Garage – Typical Plans, Elevations & Roof Plan H5463-G03 1 November 2010 Double Detached Garage – Typical Plans, Elevations & Roof Plan H5463-G02 1 November 2010 Twin Detached Garage - Typical Plans, Elevations & Roof Plan H5463/G05 1 November 2010 Site Specific Garage Details – Typical Plans & Elevations H5463/G04 1 November 2010 Twin Double Garage – Typical Plans & Elevations H5463/G06 1 November 2010 Site Specific Garage Details – Typical Plans & Elevations 3. The development hereby permitted shall only be carried out in conformity with the proposed ground and building slab levels shown on approved plan Drawing Number 293/10/ED/11. Reason: To protect the appearance of the locality and in the interests of the amenities of local residents and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review . 4. No dwelling shall be occupied until all fences and walls shown in the approved details to bound its plot, have been erected in conformity with the approved details. Other fences and walls shown in the approved details shall have been erected in conformity with the approved details prior to substantial completion of the development. Reason: To ensure a visually satisfactory form of development, to provide reasonable standards of privacy to residents and in accordance with Policy No.HS4 of the Adopted Chorley Borough Local Plan Review. 5. Surface water must drain separate from the foul and no surface water will be permitted to discharge to the foul sewerage system. Reason: To secure proper drainage and in ... view the full minutes text for item 212g
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Development Control Committee

Item 10/00792/FULMAJ

Case Officer Caron Taylor

Ward Astley And Buckshaw

Proposal Erection of 42 No 2 and 2½ storey dwellings

Location Parcel L Buckshaw Avenue Buckshaw Village Lancashire

Applicant Barratt Homes (Manchester)

Consultation expiry: 11 November 2010

Application expiry: 2 December 2010

Proposal 1. This application is for 42 No. 2 and 2½ storey dwellings.

Recommendation 2. It is recommended that this application is granted planning permission, subject to conditions.

Main Issues 3. The main issues for consideration in respect of this planning application are: • Principle of the proposal • Appearance, layout and scale • Access and parking • Impact on neighbour amenity

History • 97/509/OUT: Outline application for mixed use development (granted in 1999) • 02/748/OUT: Modification of conditions on outline permission for mixed use development

Representations 4. Three objections been received to the application on the grounds that the access to the site is via Aycliffe Drive and it will increase the amount of traffic going past the primary school and have safety implications as it is a narrow road. They believe the main access should be through the parcel to the south off Buckshaw Avenue as Aycliffe Drive is not a sufficient size of road.

5. An additional letter has also been received making comments on the application. They request that Aycliffe Drive is not used by construction traffic, but the developer is required to build an alternative temporary access road and that construction is limited to weekdays only as the site is in a residential area.

Consultations 6. Lancashire County Council Highways – state the layout includes some newer ideas that could be worked up, but also includes some problem areas. These included the shared surface areas, the parking to plots 1 and 2 and the 80m long straight road serving plots 1-7 will encourage high speeds. The private driveway also serves six properties which is not acceptable. They also state some driveways are too short. Amended plans have been received in response to these comments.

7. Environment Agency – has no objection in principle and state the site has been previously remediated and accepted as validated by BAe Systems as part of Area 10 of the site. 8. United Utilities – no objection subject to conditions being added to ay permission.

9. Chorley Council Waste Management – have no objections. They are satisfied with the refuse strategy layout.

10. Environmental Protection – Have no objection or comments to make on the application.

Assessment

Principle of the development 11. The principle of housing on this site has already been established by the original outline permission for the whole of Buckshaw.

Appearance, Layout and Scale 12. The parcel is located on the edge of the residential element of Buckshaw Village to the east of the Primary School currently under construction. The west of the site bounds with an area of public open space, a parcel that has been constructed by Barrett Homes (Aycliffe Drive) and part of Parcel to J that has yet to be constructed but has permission and will be developed by David Wilson Homes. To the north and east of the parcel is a raised landscape mound that will remain as public open space. To the south is the remaining part of parcel L that will be developed by Redrow but is not yet the subject of a reserved matters application.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10/00792/FULMAJ: Parcel L Buckshaw Avenue, Buckshaw Village, LancashireReport 54 KB DownloadRead as text
PDF
1000792FULMAJ(1).pdfReport 207 KB Download
PDF
1000792FULMAJ(2).pdfReport 235 KB Download

At this meeting

Whole meeting

Who was there

12 of 18 attended
HH
Councillor Harold HeatonChair, present
GR
Councillor Geoffrey RussellVice-Chair, present
AB
Councillor Alistair BradleyCommittee Member, present
HC
Councillor Henry CaunceCommittee Member, present
AC
Councillor Alan CullensCommittee Member, present
DD
Councillor David DickinsonCommittee Member, present
CF
Councillor Christopher FranceCommittee Member, present
RL
Councillor Roy LeesCommittee Member, present
JM
Councillor June MolyneauxCommittee Member, present
SM
Councillor Simon MoultonCommittee Member, present
MM
Councillor Michael MuncasterCommittee Member, present
RS
Councillor Ralph Snape MBECommittee Member, present

All 18 on the meeting page

On this subject at Chorley

Search all
  1. 10/00792/FULMAJ - Parcel L Buckshaw Avenue, Buckshaw Village, LancashireThis decision
  2. 20/01141/FULMAJ - Former BAE Site Group 1, Parcel C1, And C2, Central Avenue, Buckshaw VillageAgreed
  3. 14/00177/FULMAJ - Parcel H3 Group 1, west of Central Avenue and south of Worden Brook, Euxton Lane, EuxtonDecided
  4. 12/00658/FULMAJ - Parcel L Buckshaw Avenue Buckshaw Village LancashireDecided
  5. 11/00879/FULMAJ - Land south of Parcel 7 and Parcel F Buckshaw, Euxton Lane, EuxtonApproved
  6. 10/01012/FULMAJ - Parcel J and L Buckshaw Avenue, Buckshaw VillageApproved

More from Chorley Development Control Committee

All decisions
MeetingDecisionOutcome
16 Jul 2019 Minutes of meeting Tuesday, 18 June 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 18 June 2019 be approved as a correct record... Approved Open
16 Jul 2019 19/00417/FULMAJ - Land Adjoining Cuerden Residential Park, Nell Lane, CuerdenFull planning permission granted, subject to conditions and a Section 106 legal agreement. Agreed Open
16 Jul 2019 19/00325/FUL - Playing Field, Kem Mill Lane, Whittle-le-WoodsFull planning permission granted, subject to conditions. Decided Open
18 Jun 2019 Minutes of meeting Tuesday, 21 May 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 21 May 2019 be approved as a correct record ... Approved Open
18 Jun 2019 18/00108/FULMAJ - Chorley Rugby Union Club, Chancery Road, Astley Village, ChorleyFull planning permission granted, subject to conditions and a supplemental Section 106 Agreement. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies