Central Lancashire Strategic Planning Joint Advisory Committee decided this item on Tuesday 15 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved – ( i ) That the joint be supported; and (ii) that each District Council be requested to provide Kezia Henderson, joint LDF Officer Team member, information identifying non-Planning resources used, for inclusion with the LDS document.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report to Central Lancashire Strategic Planning Joint Advisory Committee
Purpose of report
1. To inform members of the outcome of progress in preparing a joint Local Development Scheme (LDS).
2. To outline the key timescales of the Local Development Framework (LDF) over the next three years.
RECOMMENDATION(S)
3. That the attached joint Scheme be supported.
EXECUTIVE SUMMARY OF REPORT
4. The LDS is the timetable for the production of the LDF. It identifies a series of milestones for the production of the various planning documents (including the proposed Community Infrastructure Levy Charging Schedule) and sets out the various community engagement/preparation stages.
5. The LDS also includes the risks and resources in producing an LDF and the link between the old style Local Plans with their 'saved policies' and the documents in preparation.
6. It is a statutory requirement to produce an LDS and intended to remain so with the enactment of the Localism Bill.
REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted)
7. To make Members aware of the LDS and the timescales for the production of the LDF, over the next three years.
ALTERNATIVE OPTIONS CONSIDERED AND REJECTED
8. None as it is a required document.
Central Lancashire Local Development Framework Report Local Development Scheme March 2011 BACKGROUND
What is a Local Development Scheme?
9. The LDS is the business plan for the production of an LDF. It identifies and sets out the timescales for the production of Development Plan Documents (DPD's) and can include as is proposed here timescales for the production of Supplementary Planning Documents (SPD's) and other associated planning documents such as the Community Infrastructure Levy Charging Schedule. The LDS covers a three year period and should ideally be updated annually to provide realistic and up to date timescales. Once agreed the LDS is a publicly available document, which will be placed on the Councils' websites, as well as in paper form, if requested in that format.
10. There are currently three LDS's – one for each of the Central Lancashire District Councils.
• Chorley's LDS currently runs from 2009 to 2012 • South Ribble's LDS currently runs from 2007 to 2012 • Preston's LDS currently runs from 2007 - 2010
However, due to recent planning changes at the national level there have been a number of delays in the production of the LDF documents and as a result all three LDS's need to be updated.
What has been carried out so far?
11. A draft joint LDS for the three teams has now been produced, covering the period up until 2014 – see attached Appendix 1. This document is intended to replace the three individual LDS's and provide an update of the timescales for the production of the documents, the level of staff resources available, a risk assessment of meeting the timescales and preparation progress.
12. This document would be the first joint LDS for the three authorities and has been produced arising out of joint working on the Core Strategy and forthcoming Supplementary Planning Documents (SPD's).
KEY ISSUES
13. The LDS provides a timescale for the continuing production of the Core Strategy. The key milestones including its submission by the end of March 2011, the examination hearings during June 2011 and adoption in November 2011 is the timetable previously agreed with Members.
14. The LDS also provides timescales for the three individual Site Allocation and Development Management Policies DPD's. However, the timescales for the production of these DPD's varies between authority and as such the periods of community engagement would occur at different times of the year, as a result it is likely there would be individual examinations.
15. Included within the LDS are potential timescales for the proposed Community Infrastructure Levy Charging Schedule, which if accepted, is likely to be out for draft consultation in September/October 2011, examination in February 2012 and adoption in June 2012.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Lancashire Strategic Planning Joint Advisory Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.