Resolved
RESOLVED – That 1 Members note the new format of the Strategic Risk Register. 2 Members note the strategic risks, actions in progress and actions planned to further mitigate the strategic risks as set out in Appendix 1 of the report.
Audit Committee (now Governance Committee) noted this item on Thursday 17 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That 1 Members note the new format of the Strategic Risk Register. 2 Members note the strategic risks, actions in progress and actions planned to further mitigate the strategic risks as set out in Appendix 1 of the report.
11. The management of risk is clearly embedded within the Council. While the Strategic Risk Register sets out the Council’s main strategic risks there are a number of other processes that contribute to effective risk management at all levels of the organisation. These include our Business Improvement Planning process, programme and project management and Partnerships Framework. This is described in more detail in the Council’s risk management framework.
SUMMARY OF CHANGES
12. The focus and format of the SRR has been revised in order to cut down on duplication and focus more on the strategic risks to the organisation and the delivery of its functions rather than risks in not delivering the Corporate Strategy which are monitored more effectively through project and business plan risk registers.
13. The result it a more focused SRR which has identified ten risks that could impact (both positively and negatively) on the Council as a whole and therefore need to be managed strategically.
14. Responsibility for the SRR has also moved from the Shared Assurance Service to the Policy team in order for it to be better aligned to strategy and policy development.
HOW THE RISKS ARE SCORED
15. The risks identified in the register have been scored on a 3 x 3 matrix, reflecting the likelihood of the risk occurring against the impact of it on the organisation if it did happen. The resulting score out of 9 is used to aid in prioritising the risk and the actions that are planned to mitigated them.
Likelihood High 4 7 9 of Medium 2 5 8 Occurrence Low 1 3 6 Noticeable Significant Critical Impact on Business
16. Each entry within the register is scored to provide an assessment of the residual level of risk, that is the score taking into account the ‘controls in place’.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 661 KB | Download |
PDF |
Refresh of the Council's Strategic Risk RegisterReport | 532 KB | DownloadRead as text |
Follow Audit Committee (now Governance Committee) at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Mar 2012 | Internal Audit Plan 2012 -13RESOLVED – That the report be noted. | Noted | Open |
| 15 Mar 2012 | Anti Fraud Corruption PoliciesRESOLVED – 1. That the report be noted. 2. That the Chair of Audit Committee write to all Members of the Council to e... | Noted | Open |
| 15 Mar 2012 | Audit Committee Update 2011/12RESOLVED – That the report be noted. | Noted | Open |
| 15 Mar 2012 | Strategic risk update reportRESOLVED – That the report be noted. | Noted | Open |
| 19 Jan 2012 | Annual Audit Letter 2010/11RESOLVED – That the Audit Letter for 2010/11, as presented by the Audit Commission, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.