REPORT OF AUDIT COMMITTEE
GENERAL REPORT
1. This report summarises briefly the items considered and decisions taken by the Audit Committee at its meeting on 20 January 2011.
Annual Audit Letter, 2009/10
2. The Engagement Lead and Audit Manager from the Audit Commission attended the meeting to present the Annual Audit Letter, which summarised the findings of the Audit Commission’s audit of the Council’s accounts for 2009/10 and its assessment of the authority’s arrangements to secure value for money in its use of resources.
3. The only issues identified by the Audit Commission were primarily of a minor nature, involving mainly classification issues.
4. The auditors acknowledged the Council’s maintained high performance in a difficult economic environment, continuing to deliver significant efficiencies whilst achieving an increase in customer satisfaction scores. The auditors are also aware of the Council’s plans to address the implications of the spending review and have reminded the authority of the need to continually review priorities, service standards and the methods of service delivery.
5. The Audit Commission has, consequently, issued an unqualified opinion on the Council’s Financial Statements for 2009/10 and an unqualified value for money conclusion, being satisfied that the Council has adequate arrangements in place.
Audit Plan for 2010/11
6. The Committee received and considered a document from the Audit Commission which outlined the work the Commission propose to undertake for the audit of the Council’s 2010/11 financial statements and value for money conclusion, as based on the Commission’s risk based approach to audit planning.
7. The Commission’s scrutiny of the Council’s arrangements be secure economy, efficiency and effectiveness will take into account the Council’s arrangements for:
• securing financial resilience by managing its financial risks;
• challenging priorities and resources and improving productivity and efficiency.
8. A rebate has already been allowed on the Audit Commission’s original scale fees for its 2010/11 audit, but the Commission envisaged that a further reduction of 1.5% would be made at the conclusion of a consultation exercise.
9. Chorley Council will be required to prepare the financial statements for 2010/11 by 30 June 2011, following which the Audit Commission will expect to complete its audit and issue an opinion and value for money conclusion by 30 September 2011.
Future External Audit Arrangements
10. The Engagement Lead with the Audit Commission updated the Committee on the likely impact on future external audits of the Council’s accounts of the Government’s plans to abolish the Audit Commission. 11. We were told that the original timetable has been delayed and that it is unlikely that the Audit Commission will be abolished until December 2013 at the earliest.
12. The implementation of the new audit framework will require legislation and a Parliamentary Select Committee has been established to examine and make recommendations on future audit criteria and framework. Whilst the Council will ultimately be able to select its own external auditors, the procurement of a new audit service will, as yet, be unnecessary until the new framework and procedures have been agreed. In the interim, the Audit Commission will continue to work positively with Chorley Council on the audit of its accounts up to at least 2011/12.
Treasury Management Activity 2010/11
13. The Committee received for information a report of the Director of Transformation on the Councils Treasury Management activity and performance up to 30 September 2010 which had been presented to the Executive Cabinet meeting on 11 November 2010.
14. The report confirmed that the Council continues to comply with the prudential indicators specified in the adopted Treasury and Investment Strategies and that investments continue to be made with only highly rated institutions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit CommitteeReport | 56 KB | DownloadRead as text |
PDF |
AuditCmtteeToFollowReport | 58 KB | Download |
Follow Council at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesApproved, as amended. | Approved | Open |
| 22 Sep 2026 | Executive CabinetNoted. | Noted | Open |
| 22 Sep 2026 | Audit and Governance CommitteeNoted. | Noted | Open |
| 22 Sep 2026 | Audit and Governance Committee Annual ReportNoted. | Noted | Open |
| 22 Sep 2026 | Proposed updates and changes to the Council's constitutionTo approve the proposed changes in Appendix 1 that fall outside of that delegation, for consideration by Council at i... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.