Resolved
Full planning permission granted subject to conditions
Development Control Committee decided this item on Tuesday 24 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Full planning permission granted subject to conditions
Item 4j 12/00188/FULMAJ
Case Officer Caron Taylor
Ward Euxton South
Proposal Section 73 application to vary conditions 1, 2, 3, 4, 6, 8, 9, 10, 11, 12, 13, 15, 16, 17, 18, 21, 22, 24, 25, 29, 30, 31 and 32 of planning permission 11/00238/FULMAJ to allow changes to the phasing of the development, an increase in the finished floor level of the Fleet Garage and Stores building, a reduction in the landscaping scheme relating to the Fleet Garage and Stores building and changes to the sustainable resources condition.
Location International Fire Training Centre Washington Hall West Way Euxton Chorley
Applicant Lancashire Fire And Rescue Service
Consultation expiry: 21 March 2012
Application expiry: 22 May 2012
Proposal 1. Section 73 application to vary conditions 1, 2, 3, 4, 6, 8, 9, 10, 11, 12, 13, 15, 16, 17, 18, 21, 22, 24, 25, 29, 30, 31 and 32 of planning permission 11/00238/FULMAJ to allow changes to the phasing of the development, an increase in the finished floor level of the Fleet Garage and Stores building, a reduction in the landscaping scheme relating to the Fleet Garage and Stores building and changes to the sustainable resources condition.
2. In June 2011 permission was granted for the redevelopment of Washington Hall Fire Training Centre (part outline and part full application). A ten year permission was granted to allow the site to be redeveloped in phases. This application is for amendments to this permission.
Recommendation 3. It is recommended that this application is granted planning approval.
Main Issues 4. The redevelopment of the site has already been found to be acceptable by the earlier permission, this report will therefore consider whether the proposed changes are acceptable.
Representations 5. No letters of representation have been received.
Assessment Assessment of Changes to the Scheme. 6. A large number of conditions need to be amended as many of the conditions on the existing permission refer to specific plan numbers and these will change if new plans are permitted.
7. Apart from changes to the plan numbers, the changes are as follows: • changes to the phasing of the development; • increase in the finished floor level of the Fleet Garage and Stores building; • reduction in the landscaping scheme relating to the Fleet Garage and Stores building; • changes to the sustainable resources condition Phasing 8. In terms of phasing (condition 4), Phase 1 will remain as originally approved.
9. Phase 2-A will be changed however so that although half of Washington Hall will be demolished and the new Fleet Garage and Stores Building constructed, the widening of the access to the site will not take place until Phase 4, in addition although most of the Fleet Garage and Stores Building will be constructed the last two bays will not be constructed as part of this phase, but will be extended later.
10. The reminder of Washington Hall will be demolished as originally permitted as part of Phase 2-B but it is not proposed to construct the associated car park until Phase 5.
11. There is no proposed change to Phase 3 which will still be for demolition of the existing fleet garage and construction of the new Fire Station (the Fire Station was permitted under a separate planning permission).
12. As part of Phase 4 the Urban Search and Rescue Building (USAR) will be constructed as originally planned and Minerva buildings will be constructed. The access way into the site will be widened at this stage.
13. The change from previously permitted to Phase 5 is the construction of the car park that was previously to be implemented as part of Phase 2 and the extension of the Fleet Garage and Stores Building.
14. There is no proposed change to Phase 6.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
12/00188/FULMAJ: International Fire Training Centre, Washington Hall, West Way, Euxton, ChorleyReport | 133 KB | DownloadRead as text |
PDF |
12/00188/FULMAJ: Washington Hall ElevationsReport | 513 KB | Download |
PDF |
12/00188/FULMAJ: Washington Hall Landscaping PlanReport | 3.4 MB | Download |
PDF |
12/00188/FULMAJ: Washington Hall MasterplanReport | 3 MB | Download |
PDF |
12/00188/FULMAJ: Washington Hall location planPlan | 95 KB | Download |
Follow Development Control Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2019 | Minutes of meeting Tuesday, 18 June 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 18 June 2019 be approved as a correct record... | Approved | Open |
| 16 Jul 2019 | 19/00417/FULMAJ - Land Adjoining Cuerden Residential Park, Nell Lane, CuerdenFull planning permission granted, subject to conditions and a Section 106 legal agreement. | Agreed | Open |
| 16 Jul 2019 | 19/00325/FUL - Playing Field, Kem Mill Lane, Whittle-le-WoodsFull planning permission granted, subject to conditions. | Decided | Open |
| 18 Jun 2019 | Minutes of meeting Tuesday, 21 May 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 21 May 2019 be approved as a correct record ... | Approved | Open |
| 18 Jun 2019 | 18/00108/FULMAJ - Chorley Rugby Union Club, Chancery Road, Astley Village, ChorleyFull planning permission granted, subject to conditions and a supplemental Section 106 Agreement. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.