Resolved
Planning permission granted subject to an associated Section 106 Legal Agreement and conditions
Development Control Committee agreed this item on Tuesday 10 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Planning permission granted subject to an associated Section 106 Legal Agreement and conditions
Item 4f 12/00475/FULMAJ
Case Officer [name removed] Astley And Buckshaw
Proposal Section 73 application to vary condition 18 (southern boundary treatment) attached to planning approval 09/00095/FULMAJ
Location Group 1 Euxton Lane Euxton Lancashire
Applicant BAE Systems (Property & Environmental Services)
Consultation expiry: 21 June 2012
Application expiry: 9 August 2012
Proposal 1. The application is a S73 application to vary condition 18 of planning approval 09/00095/FULMAJ. Full planning permission was granted in December 2009 for land reclamation and remediation earthworks to create a development platform at Group 1, Buckshaw Village.
2. Condition 18 related to the landscaping treatment along the boundary of the site with the railway line. This application seeks to vary this condition. Recommendation 3. It is recommended that this application is granted conditional planning approval subject to the associated Section 106 Agreement
Main Issues 4. The main issues for consideration in respect of this planning application are: • Principle of the development • Background information • Condition 18 • S106 Agreement
Representations 5. 2 letters of objection have been received which raise the following issues: The height, scale and appearance of what is proposed The impact on residential properties in terms of light, loss of privacy, overlooking and disturbance Damage relating to wind blowing across the site Loss of value of properties Impact on wildlife Assessment Principle of the development 6. The site is located to the south west of Buckshaw Village and forms part of the former Royal Ordnance Site. The site is known as Group 1 and was formally a munitions factory occupying 54.34 hectares.
7. Planning permission was granted for land reclamation and remediation earthworks to create a development platform at Group 1, Buckshaw Village in December 2009. The site is the last remaining part of the Royal Ordnance Factory.
8. The principle of the development was established with the grant of planning permission in December 2009. This application purely relates to the specific details of the proposals.
Background Information 9. When the Royal Ordnance Factory was fully operational it occupied an area of 350 hectares. In 1997 following the progressive demise of the industrial industry a Masterplan for the whole site was developed. From this Masterplan a number of developments have occurred including Buckshaw Village which occupies the core of the factory site, over 170 hectares.
10. The redevelopment of Group 1 has always been envisaged however the site did not form part of the main Buckshaw Village Masterplan as it was, until recently, still operational. When the Chorley Local Plan was adopted in 2003 the whole of Buckshaw Village was allocated under Policy GN2. Policy GN2 states that that high quality and phased development will be permitted for purposes appropriate to the concept of an Urban Village.
11. This part of the Royal Ordnance Factory (Group 1) handled the most volatile explosives and is therefore the most contaminated high risk area. The approval at this site relates to the enabling works required to create development platforms across the site for future development projects. In accordance with Government advice the redevelopment of previously developed sites is central to achieving the Government’s objective of ensuring sustainable development and minimises the need to develop Greenfield sites.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
12-00475-FULMAJ location plan.pdfPlan | 6.1 MB | Download |
PDF |
12/00475/FULMAJ -Group 1 Euxton Lane Euxton LancashireReport | 144 KB | DownloadRead as text |
Follow Development Control Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2019 | Minutes of meeting Tuesday, 18 June 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 18 June 2019 be approved as a correct record... | Approved | Open |
| 16 Jul 2019 | 19/00417/FULMAJ - Land Adjoining Cuerden Residential Park, Nell Lane, CuerdenFull planning permission granted, subject to conditions and a Section 106 legal agreement. | Agreed | Open |
| 16 Jul 2019 | 19/00325/FUL - Playing Field, Kem Mill Lane, Whittle-le-WoodsFull planning permission granted, subject to conditions. | Decided | Open |
| 18 Jun 2019 | Minutes of meeting Tuesday, 21 May 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 21 May 2019 be approved as a correct record ... | Approved | Open |
| 18 Jun 2019 | 18/00108/FULMAJ - Chorley Rugby Union Club, Chancery Road, Astley Village, ChorleyFull planning permission granted, subject to conditions and a supplemental Section 106 Agreement. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.