RESOLVED 1. That the information in the report be noted. 2. That clarification be sought as to whether or not the original developer retains the responsibility of the Bond and Section 38 Agreement. 3. That relations with Lancashire County Council be improved upon around maintaining accurate records on the progress of actions contained with Section 38 Agreements across the Borough.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report to Overview and Scrutiny Task Group - Adoption of Estates
Adoptions Scrutiny – Chorley Borough Council (progress as at 5th October 2012)
Development Comments Next action required by Buckshaw Village This development comprises of many phases with a number of contractors to negotiate and liaise with. The sites are interrelated and some sites are landlocked by others and can only progress once others have been completed. Developers are Redrow/Barratt/Persimmon/David Wilson Homes.
Phase 1 - Central Avenue is now adopted (2011).
The following update relates to Phase 2 - Buckshaw Avenue:
The Design team has provided the cost breakdown for the pelican crossing on Central Avenue and the Developer Support team has forwarded this to the Redrow and Barratt developer for payment.
The other issues remaining are the bus shelters (these are on order), minor resurfacing and some swales on Central Avenue need attention as the levels are not allowing water to drain. Redrow and Barratt
There are also some third party land drainage issues with water discharging onto the highway. Redrow and Barratt
Once Buckshaw Avenue is adopted this should release smaller sections of road such as the cul-de-sacs off the main road. These will be the next to All developers progress.
Regular inspections are taking place by Developer Support with defects being flagged up with the relevant developer, within appropriate timescales.
Gillibrands North Progressing well, overall, with Redrow. There is a need to re-site a street light Redrow which has been erected in the wrong location and another column which is bent. All other remedial works are complete and that takes adoption to approx 1 halfway through the site.
Adactus Housing have approached us regarding their 2/3 parcels of land so Adactus Housing these need progressing via short-form Section 38. These parcels are land- locking other areas and so it will be very beneficial to move these forward. Advice has been given to Adactus on how to proceed. Gillibrands South Taylor Wimpey hold the key to the rest of the site as they are the lead Taylor Wimpey developer. There are issues with the sewers and the pumping station. Once the Taylor Wimpey site is completed this unlocks the rest of the site.
Fairview, Adlington The developer, Persimmon Homes, had used a non-standard material on the Developer Support team road and the Developer Support team raised the skid resistance as an issue. The developer undertook skid tests and the results have recently been received by the Developer Support team. The results have yet to be analysed.
The site has no Section 38 Agreement in place. A short-form S38 will be Persimmon Homes required. Persimmon Homes need to undertake various tests and provide test certificates. Kittiwake Road, All roads are adopted No further action required Heapey
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Task Group - Adoption of Estates at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.