RESOLVED – that the Executive Leader and the Chief Executive be asked to develop mechanisms to ensure there is strategic consideration of highway and transport matters where LCC is asking for the borough’s input and ideas for future schemes.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
4. In its terms of reference, the overview and scrutiny performance panel agreed that at each meeting, as well as considering performance reports, the panel have the opportunity to focus in on any specific area of service delivery. The panel have identified the trial re-opening of Market St as a key project for further scrutiny at the September meeting.
5. This report provides contextual information relating to the trial re-opening of Market St. This will enable the panel and relevant officers and Members to prepare in advance of the meeting. PERFORMANCE CONTEXT
TRIAL RE-OPENING OF MARKET STREET
6. The trial re-opening of Market Street is a key project in this year’s corporate strategy, identified in order to re-vitalise the top end of Market St with the aim of attracting more shoppers and boosting trade in the area. The scope of the project is to design and deliver a workable scheme for a trial period of 12 months that will address the highways requirements of Lancashire County Council as Highway Authority and complement the associated future public realm improvements.
7. Chorley Council is leading the project as a key stakeholder and coordinator of the Town Centre Team. Lancashire County council are the highways authority and need to approval all works to be carried out. Pendle Engineering Services are a third party contractor for Chorley Council to provide engineering and highways expertise and will draw up the design for the scheme.
Budget
8. This project has a budget estimate of £47,000 which comprises as follows: - £5,000 Scheme Design, funded from Economic Development mainstream budget - £42,000 Scheme Delivery, Monitoring and Evaluation, funded from £300,000 Town Centre Reserve
Timescales
9. The table below sets out the timescales as defined at project initiation:
Task Timescale Draft scheme design Nov 2012 Public consultation Nov 2012 Executive Cabinet Session Nov 2012 Safety Audit Dec 2012 LCC Authorise Experimental Order May 2013 Procurement to deliver work June 2013 LCC places Experimental Order advert June 2013 Deliver Works August 2013 Monitor and Evaluate September 2013
Project progress
10. The table below provides a summary of the project status and brief description of project performance for each reporting period since project initiation.
Reporting RAG Description period status Quarter 3 Green Initial design and consultation complete 2012/13 with minor amends. LCC to approve experimental order Quarter 4 Amber Lancashire County Council recommend 2012/13 changes to the scheme. Redesign of amended scheme and submit for safety audit. Quarter 1 Amber Lancashire County Council take 2013/14 responsibility for finalising the design and delivering the scheme. Jacobs Consulting instructed to carry out a further safety audit.
11. Following a successful start to the project, the rating was changed to Amber at Quarter 4 2012/13 as an early warning of potential issues or problems that may impact on the project being delivered to time and budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Performance Focus: Customer and DigitalResolved (unanimously): 1. That the Executive Member and officers be thanked for their attendance; 2. That ... view t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.