Resolved
RESOLVED – That the progress of City Deal had been noted.
Central Lancashire Strategic Planning Joint Advisory Committee noted this item on Tuesday 28 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the progress of City Deal had been noted.
Infrastructure delivery to the end of Year 1
4.1Positive early progress through 2014/15 has continued through Quarter Four. The delivery of strategic highway infrastructure and public transport and local centres has been achieved against the agreed programme over the Quarter and over Year One. Work in delivering the transport and public realm schemes continues at pace, with the following progress reported:
Golden Way (North) dualling works completed in March and under budget by circa. £740k (a 25% saving on the target cost) Preparatory tree clearance works carried out on Golden Way (South) A new route for the completion of Penwortham Bypass approved in March Consultation on widening options along A582 completed in March Works begun in January on the new A59 access for the Enterprise Zone Plans published for public consultation for improvements in Bamber Bridge (continuing from October), New Hall Lane and Broughton (both in March) Works began in February on Phase 2 of the Fishergate shared space scheme and Cannon Street public realm works.
Monitoring Outputs in Year 1 4.2 Work has been carried out by Local Partners to complete the 10 year output targets and the 2014/15 Annual Monitoring Report to be included in the City Deal Monitoring Return to Government. This sets out a range of information relating to delivery, receipts, expenditure and completions. Two sets of monitoring outputs are to be prepared annually:
Firstly, a Core Output data set, to include housing units (consented and completed), commercial floor space (consented and completed), private sector investment and jobs accommodated Secondly, a Supporting Output data set to include metrics to track planning consents, development activity on specific sites (including HCA sites), retail vacancy outputs, and outputs to monitor progress with transport and community outputs.
4.3The table below shows progress against Year 1 Core Output targets, which are the key Government performance measures.
Core outputs - 2014/15 Target Actual Variance Comments Total number of Housing 6,590 6,501 -89 Only 1 major site units consented for planning requires planning * permission.
Total number of Housing 338 980 +642 Includes 98 empty units completed homes brought back into use and 215 office units converted to residential Commercial floorspace 44,000 19,442 -24,558 Awaiting next phase consented (sq m) development of Preston East sites. Commercial floorspace 21,928 3,338 -18,590 This mainly relates to completed (sq m) one site where development options have been drawn up. Early stage negotiations are underway. Jobs accommodated - Via commercial 86 77 -9 floorspace completions** - Construction jobs n/a 226 n/a These jobs are connected to Capital associated with the Investment** * infrastructure build programme Public Sector Investment £18.59m £18.067 - (to support Infrastructure m £0.523m programme) Private Sector Investment £6.18m £5.543m - (to support infrastructure £0.637m programme) * Includes consents from previous years from City Deal sites that form the baseline position ** Gross jobs based on an average of 43 sq m per job, as per CLG guidance. An additional CLG methodology is used whereby a calculation is made based on additionality with job creation spread over a 3 year period which would generate 13 jobs *** Based on one job per £86,945 of capital investment
Housing outputs
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
City Deal UpdateReport | 190 KB | DownloadRead as text |
Follow Central Lancashire Strategic Planning Joint Advisory Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jun 2025 | Appointment of Chair for the MeetingResolved - That Councillor Alistair Bradley be appointed as Chair for the meeting. | Decided | Open |
| 9 Jun 2025 | Minutes of meeting Monday, 16 December 2024 of Central Lancashire Strategic Planning Joint Advisory CommitteeResolved – That the minutes of the last meeting, held on Monday 16 December 2024, be agreed as an accurate record. | Agreed | Open |
| 9 Jun 2025 | Exclusion of Press and PublicResolved - That the public be excluded from this meeting during consideration of the following items of business on t... | Decided | Open |
| 16 Dec 2024 | Appointment of Chair for the MeetingResolved - That Councillor Amber Afzal be appointed as Chair for the meeting. | Decided | Open |
| 16 Dec 2024 | Minutes of meeting Thursday, 26 September 2024 of Central Lancashire Strategic Planning Joint Advisory CommitteeResolved - That the minutes of the last meeting, held on Thursday, 26 September 2024, be noted and signed as a correc... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.