Appendix 1
Report of Meeting Date
Chief Executive Governance Committee 22nd June 2016
STRATEGIC RISK UPDATE REPORT
PURPOSE OF REPORT 1. The Strategic Risk Register (SRR) is the vehicle by which the Council aims to identify and address any potential risks to the organisation and the delivery of its functions which therefore need to be managed strategically.
2. This report provides members with an updated SRR which includes 15 strategic risks to the Council, including actions in progress as well as new actions planned to further mitigate identified risks.
RECOMMENDATION(S)
3. That members note the strategic risks, actions in progress and actions planned to further mitigate the strategic risks as set out in Appendix 1.
EXECUTIVE SUMMARY OF REPORT 4. The Council does not exist in a vacuum and the political, economic and financial environment in which it operates is constantly changing. The SRR is therefore a live document and needs to be updated to reflect any new or emerging strategic risks facing the Council.
5. This report contains the latest revision to the SRR for members’ information and comment.
6. The risk register is continually reviewed and currently, the majority of risk categories remain stable with five of these identified as ‘high risk’, six ‘medium risk’ and four ‘low risk'. One risk has been increased to the highest level to reflect the impact of recent budget cuts to partner services. One risk has reduced following successful work to manage high profile consultations that have now progressed to delivery stages.
Confidential report Yes No Please bold as appropriate
CORPORATE PRIORITIES
7. This report relates to the following Strategic Objectives:
Involving residents in improving their local A strong local economy area and equality of access for all Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area BACKGROUND
8. Risk management is a cornerstone of good corporate governance and the Council has established a system of risk management which involves the creation of risk registers at a strategic level, service level and individual project levels.
Compiling the Strategic Risk Register requires a collective effort involving chief officers and senior members to identify the key strategic risk issues facing the Council. Heads of Service are responsible for identifying, monitoring and mitigating service list level risk and once key projects have been identified the responsibility for managing these and compiling project risk registers lies with individual services. The process is described in more detail in the Council’s Risk Management Framework.
HOW THE RISKS ARE SCORED
9. The risks identified in the register have been scored on a 3 x 3 matrix, reflecting the likelihood of the risk occurring against the impact of it on the organisation if it did happen. The resulting score out of 9 is used to aid in prioritising the risk and the actions that are planned to mitigate them.
Likelihood High 4 7 9 of Medium 2 5 8 Occurrence Low 1 3 6 Noticeable Significant Critical Impact on Business
10. Each entry within the register is scored to provide an assessment of the residual level of risk, that is the score taking into account the ‘controls in place’.
11. Whatever level of residual risk remains it is essential that the controls identified are appropriate, working effectively and kept under review. SUMMARY OF THE RISKS
from May Change Matrix Score
2015 Risk Description of Risk No.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transformation StrategyAppendix 2 | 282 KB | Download |
PDF |
Strategic Risk Update ReportReport | 294 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.