RESOLVED – that approval be given to the following: 1. Slippage requests and other transfers to reserves as outlined in Appendix 2 of the report to finance expenditure on specific items or projects in 2016/17. 2. The set aside of £80,000 from the 2015/16 surplus on Market Walk and £70,000 from other in-year revenue underspends to fund the additional one-off costs of the new Management Structure. 3. The transfer of £50,000 from in-year revenue underspends to the Buildings Maintenance Fund to finance asset improvements in 2016/17. 4. The transfer of £0.415m underspend in respect of the Central Government Business Rates Retention (BRR) Levy Budget to the BRR Equalisation Reserve. 5. The financing of the 2015/16 Capital Programme to maximise the use of funding resources available to the Council.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To present the provisional revenue outturn figures for the Council as compared against the budgets and efficiency savings targets set for the financial year 2015/16.
2. To present the provisional outturn figures for the 2015/16 Capital Programme and update the Capital Programme for financial years 2016/17 to 2018/19 to take account of the re- phasing of expenditure from 2015/16 and other proposed budget changes.
3. The accounts are provisional at this stage and are also subject to final checking and scrutiny by the Council’s external auditor. Should there be any significant changes to the outturn as a result of this process a further report will be submitted to Executive Cabinet.
RECOMMENDATION(S)
4. Note the full year outturn position for the 2015/16 revenue budget and capital investment programme.
5. Request Council approval for slippage requests and other transfers to reserves outlined in Appendix 2 of the report to finance expenditure on specific items or projects in 2016/17.
6. Request Council approve the set aside of £80,000 from the 2015/16 surplus on Market Walk and £70,000 from other in-year revenue underspends to fund the additional one-off costs of the new Management Structure.
7. Request Council approve the transfer of £50,000 from in-year revenue underspends to the Buildings Maintenance Fund to finance asset improvements in 2016/17.
8. Note the 2015/16 outturn position on the Council's reserves.
9. Request Council approve transfer of the £0.415m underspend in respect of the Central Government Business Rates Retention (BRR) Levy Budget to the BRR Equalisation Reserve.
10. Note the impact of the final capital expenditure outturn and the re-phasing of capital budgets to 2016/17 and approve the additions and deletion to the 2015/16 capital budget outlined in paragraphs 96 to 99.
11. Request Council approval of the financing of the 2015/16 Capital Programme to maximise the use of funding resources available to the Council. EXECUTIVE SUMMARY OF REPORT
12. The Council’s overall savings target of £150k in 2015/16 from management of the establishment has been achieved.
13. There is a provisional underspend against the budget at year-end of £187k (as detailed in Appendix 1) which takes into account requests for slippage of committed items of £171k. The provisional underspend excludes any variances on investment items added to the budget in 2015/16. Details of the balances remaining at year end are shown in Appendix 2 and will be transferred into specific reserves and matched to expenditure in future years.
14. In the 2015/16 budget the expected net income from Market Walk after deducting financing costs is £0.929m. The final outturn position shows that the net income is £1.009m, the £80k surplus being driven by lower than budgeted financing costs.
15. The total BRR receipts for the 2015/16 are less than anticipated. This has been brought about as a result of the Valuation Office Agency appeals process and a decision made by the VOA, outwith this usual process, to significantly reduce the Rateable Value of the M6 Service Station at Charnock Richard and backdate this decision to 01/04/2010. The vagaries of the system mean that this reduction in financial performance actually creates an underspend of £0.415m against the anticipated budgeted position. This has been brought about by the fact that the Council does not need to pay as much BRR Levy payment to Central Government. The negative financial impact falls to the Council’s revenue account in two years’ time, being 2017/18. It is therefore recommended that the underspend in 2015/16 is transferred to the BRR Equalisation reserve to off-set this potential charge in 2017/18.
16. The capital outturn for 2015/16 is £4.019m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.