9. This note provides an update in relation to the review of CIL that was reported to the Joint Advisory Committee in July 2015. Since that report, which focused on the implications of policy changes in relation to the Code for Sustainable Homes, and recommended members to note that there was no immediate need to carry out a review, the government has commissioned its own review of the Community Infrastructure Levy and a decision on that is expected to be imminent.
10. The Community Infrastructure Levy for the three Central Lancashire authorities was adopted at various dates in July and August 2013 following an examination held in April 2013. The levy came into effect on 1st September 2013 in Chorley and South Ribble and on 30th September 2013 in Preston.
11. The National Planning Practice Guidance indicates that charging authorities must keep their charging schedules under review and should ensure that levy charges remain appropriate over time. For example charging schedules should take account of changes in market conditions, and remain relevant to the funding gap for the infrastructure needed to support the development of the area.
12. The guidance goes on to say that when reviewing their charging schedule, charging authorities should take account of the impact of revised levy rates on approved phased developments, as well as future planned development.
13. Charging authorities may revise their charging schedule in whole or in part. Any revisions must follow the same processes as the preparation, examination, approval and publication of a charging schedule (as specified under the Planning Act 2008, particularly sections 211- 214 as amended by the Localism Act 2011, and the levy Regulations).
14. Government does not prescribe when reviews should take place. However, in addition to taking account of market conditions and infrastructure needs, the guidance advises that charging authorities should also consider linking a review of their charging schedule to any substantive review of the evidence base for the relevant Local Plan. The Government suggests that even if the original charging schedule was not examined together with the relevant Plan, there may be advantages in coordinating the review of both.
CORE STRATEGY POLICY 27
15. The principle issue driving consideration of a review in 2015 was the alleged increase in costs of development that would arise from full implementation of the Code for Sustainable Homes as set out in Policy 27 of the Central Lancashire Core Strategy.
16. The issue of increasing costs arising from these increasing levels in housing was an issue before the Inspector who conducted the examination of the CIL charges in April 2013 and was also the subject of the Judicial Review brought by Fox Strategic Land and Property Limited, part of the Gladman group of companies.
17. From his report it was clear the Inspector’s expectation was that a review of CIL would be carried out to reflect the increasing costs to development arising from the introduction of Code level 6 from January 2016, and that review would be carried out in 2015.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CIL ReviewReport | 258 KB | DownloadRead as text |
Follow Central Lancashire Strategic Planning Joint Advisory Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jun 2025 | Appointment of Chair for the MeetingResolved - That Councillor Alistair Bradley be appointed as Chair for the meeting. | Decided | Open |
| 9 Jun 2025 | Minutes of meeting Monday, 16 December 2024 of Central Lancashire Strategic Planning Joint Advisory CommitteeResolved – That the minutes of the last meeting, held on Monday 16 December 2024, be agreed as an accurate record. | Agreed | Open |
| 9 Jun 2025 | Exclusion of Press and PublicResolved - That the public be excluded from this meeting during consideration of the following items of business on t... | Decided | Open |
| 16 Dec 2024 | Appointment of Chair for the MeetingResolved - That Councillor Amber Afzal be appointed as Chair for the meeting. | Decided | Open |
| 16 Dec 2024 | Minutes of meeting Thursday, 26 September 2024 of Central Lancashire Strategic Planning Joint Advisory CommitteeResolved - That the minutes of the last meeting, held on Thursday, 26 September 2024, be noted and signed as a correc... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.