Resolved

RESOLVED – that the minutes of the meeting of the Overview and Scrutiny Task Group - Rollout of Superfast Broadband by BT held on 22 March 2017 be approved as a correct record.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Overview and Scrutiny Task Group - Rollout of Superfast Broadband by BT

MINUTES OF OVERVIEW AND SCRUTINY TASK GROUP - ROLLOUT OF SUPERFAST BROADBAND BY BT

MEETING DATE Wednesday, 22 March 2017

MEMBERS PRESENT: Councillor Kim Snape (Chair) and Councillors Gordon France, Matthew Lynch, June Molyneaux, Alistair Morwood and Mark Perks

OFFICERS: Chris Sinnott (Director (Policy and Governance)), Ruth Rimmington (Democratic and Member Services Officer), Gemma Johnson (Project Manager, Lancashire Superfast Broadband) and Nick Kershaw (Project Officer, Lancashire Superfast Broadband)

APOLOGIES: Councillor John Dalton

17.SFB.1 Appointment of Chairperson

It was proposed and seconded that Councillor Kim Snape be appointed as Chairperson.

17.SFB.2 Apologies for absence

Councillor John Dalton.

17.SFB.3 Declarations of Any Interests

No declarations of any interests were received.

17.SFB.4 Scoping document

Members considered the scope of the inquiry and noted that it was envisaged that the inquiry would make its recommendations before the end of the municipal year.

An additional desired outcome was discussed: To make recommendations in line with the Council’s Digital Strategy.

Decision: The scoping document be noted and updated with the additional desired outcome.

17.SFB.5 Superfast Broadband Rollout

Gemma Johnson, Project Manager and Nick Kershaw, Project Officer from Lancashire Superfast Broadband delivered a presentation.

Superfast Lancashire was collaboration between Lancashire County Council (LCC), British Telecom (BT), Broadband Delivery UK (BDUK) and Blackburn with Darwen and Blackpool Councils.

Overview and Scrutiny Task Group - Rollout of Superfast Broadband by BT Wednesday, 22 March 2017 LCC had secured around £37 million of Public Sector Investment to intervene in ‘white’ areas (in additional to commercial rollout). A ‘white’ area was defined as having minimal coverage and open market review failure.

Contract One of the Superfast Lancashire programme consisted of 21% of the fibre rollout. 67% was BT/Openreach commercial fibre rollout and 9% was other operators’ high speed broadband services. This left 3% remaining.

Contract 2, referred to as the Superfast Extension Programme (SEP) would deliver a further 2% to achieve 99% coverage, leaving 1%. This final 1% would be addressed through future plans such as Gainshare Advance, and only when demand was identified.

There were main three types of technology used by BT: 1. Copper ADSL & ADSL2+ - Up to 20Mbps downstream and up to 2Mbps upstream. 2. FTTC (Fibre to the Cabinet) - Up to 80Mbps downstream and up to 20Mbps upstream. 3. FTTP (Fibre to the Premises) - Up to 330Mbps downstream and up to 30Mbps upstream

Superfast Lancashire enabled deployment to the final third of Lancashire that was not commercially viable for operators. By March 2016 it was planned that 97% of Lancashire homes and businesses would have access to broadband speeds above 24mbps, and 99% by March 2018. The 97% was achieved by June 2016. It was not cost effective to use public money to enable some rural areas.

In Phase One (Lancashire wide) 137,007 premises, 9,000+ eligible businesses (in the ‘white’ area) and 100+ business sites had access to Superfast Broadband. 454 Small Medium Enterprises (SMEs) had received business support related to the exploitation of Superfast Broadband access and 934 structures had been built and were providing service.

Work started in September 2016 on the Superfast Extension Project (SEP). There had been an additional £7.6m in external funding for this project which was expected to conclude by the end of December 2017. More than 11,000 extra homes would have access to fibre broadband through the project. The SEP would be more expensive as a result of delivery in the hardest to reach areas involving more build and use of Fibre to the Premise (FTTP).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Minutes of meeting Wednesday, 22 March 2017 of Overview and Scrutiny Task Group: Rollout of Superfast Broadband by BTMinutes 243 KB DownloadRead as text

At this meeting

Whole meeting
17.SFB.9Minutes of meeting Wednesday, 22 March 2017 of Overview and Scrutiny Task Group - Rollout of Superfast Broadband by BTThis decision
17.SFB.10Information requested from the Superfast Lancashire team and British TelecomNoted 17.SFB.11Update on the Council's Digital StrategyOn the agenda

Who was there

5 of 12 attended
KS
Councillor Kim SnapeChair, present
JM
Councillor June MolyneauxCommittee Member, present
AM
Councillor Alistair MorwoodCommittee Member, present
MP
Councillor Mark Perks B Ed (Hons)Committee Member, apologies
ML
Councillor Matthew LynchCommittee Member, apologies
SL
Councillor Sheila LongCommittee Member, expected
JD
Councillor John DaltonCommittee Member, present
GF
Councillor Gordon FranceCommittee Member, present
CS
Chris SinnottOfficer, in attendance
RH
Rebecca HuddlestonOfficer, in attendance
PH
Paul HeyworthOfficer, in attendance
RR
Ruth RimmingtonOfficer, in attendance

On this subject at Chorley

Search all
  1. Minutes of meeting Wednesday, 22 March 2017 of Overview and Scrutiny Task Group - Rollout of Superfast Broadband by BTThis decision
  2. Minutes of meeting Tuesday, 6 October 2026 of Planning CommitteeApproved
  3. Minutes of meeting Thursday, 9 July 2026 of Executive CabinetDecided
  4. Minutes of meeting Tuesday, 4 August 2026 of Planning CommitteeApproved
  5. Minutes of the last meeting held on Monday, 15 June 2026Approved
  6. Minutes of meeting Tuesday, 7 July 2026 of Planning CommitteeApproved

More from Chorley Overview and Scrutiny Task Group - Rollout of Superfast Broadband by BT

All decisions
MeetingDecisionOutcome
3 Apr 2017 Information requested from the Superfast Lancashire team and British TelecomThat the information be noted. Noted Open
22 Mar 2017 Scoping documentThe scoping document be noted and updated with the additional desired outcome. Noted Open