Resolved
RESOLVED – That the report be noted.
Governance Committee noted this item on Wednesday 24 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted.
Chorley Borough Council Civic Offices Union Street Chorley Grant Thornton UK LLP Lancashire 4 Hardman Square Spinningfields PR7 1AL Manchester M3 3EB T +44 (0) 161 953 6900 F +44 (0) 161 953 6901
12 December 2017 www.grant-thornton.co.uk
Dear Gary
Certification work for Chorley Borough Council for year ended 31 March 2017
We are required to certify the Housing Benefit subsidy claim submitted by Chorley Council ('the Council'). This certification typically takes place six to nine months after the claim period and represents a final but important part of the process to confirm the Council's entitlement to funding.
The Local Audit and Accountability Act 2014 gave the Secretary of State power to transfer Audit Commission responsibilities to other bodies. Public Sector Audit Appointments (PSAA) took on the transitional responsibilities for HB COUNT issued by the Audit Commission in February 2015.
We have certified the Housing Benefit subsidy claim for the financial year 2016/17 relating to subsidy of £25.3 million. Further details are set out in Appendix A.
We identified only minor issues from our certification work that we wish to highlight for your attention. The issues relate to: a miscoding between non-HRA rent rebates and rent allowance; and the incorrect inclusion of an uncashed payment
As a result of the issues identified, we reported our findings to the Department of Works and Pensions (DWP). The DWP may require the Council to undertake further work or provide assurances on the issues reported in our qualification letter.
The indicative fee for 2016/17 for the Council was based on the final 2014/15 certification fees, reflecting the amount of work required by the auditor to certify the Housing Benefit subsidy claim that year. The indicative scale fee set by PSAA for the Council for 2016/17 was £6,683. This is set out in more detail in Appendix B.
Yours sincerely
Grant Thornton UK LLP Appendix A - Details of claims and returns certified for 2016/17
Claim or Value Amended? Amendment Qualified? Comments return value
Housing £25,297,732 No 0 Yes See below for details. benefits subsidy claim
Findings from certification of housing benefits subsidy claim
Misclassification between cells Testing of the initial sample identified one case where the benefit type had been miscoded, when adjusting for a recovered overpayment of £36.17. The adjustment was recorded as non- HRA rent rebate expenditure rather than rent allowance. As eligible rents and benefit entitlement were correctly calculated and the total subsidy claimable remained the same, no additional testing was required and no amendment was made to the claim form. We did however include the issue in our qualification letter to the DWP.
Uncashed payments Testing of the prior year uncashed payment of £895 recorded on the claim actually related to an overpayment that did not occur. The Authority contacted the bank prior to the payment being made, but an overpayment had already been raised on the system. The system posting to remove the technical overpayment resulted in an incorrect entry being made to uncashed payments. The issue was included in the qualification letter. . Self-employed earnings As a result of errors in 2015-16 relating to self-employed earnings in rent allowance expenditure, further testing was required on income assessment. No issues were identified from this additional testing.
Recommended actions for officers We have no specific recommendation relating to the claim.
2 Appendix B: Fees for 2016/17 certification work
Claim or return 2014/15 2016/17 2016/17 Variance Explanation for variances fee (£) indicative actual fee between fee (£) (£) indicative fee and actual (£)
Housing benefits £8,910 £6,683 £6,683 £0 No variance between subsidy claim indicative fee and actual (BEN01)
Total £8,910 £6,683 £6,683 £0
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Chorley Certification Letter 2016/17Report | 311 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.