Resolved
RESOLVED – That the minutes of the Governance Committee meeting held on 24 January 2018 be confirmed as a correct record for signing by the Chair.
Governance Committee decided this item on Wednesday 21 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the minutes of the Governance Committee meeting held on 24 January 2018 be confirmed as a correct record for signing by the Chair.
MINUTES OF GOVERNANCE COMMITTEE
MEETING DATE Wednesday, 24 January 2018
MEMBERS PRESENT: Councillor Paul Leadbetter (Chair), Councillor Anthony Gee (Vice-Chair) and Councillors Jean Cronshaw, Alan Cullens, Gordon France, Danny Gee, Debra Platt and Kim Snape
OFFICERS: Gary Hall (Chief Executive/Statutory Finance Officer), Rebecca Huddleston (Director (Policy and Governance)), Chris Moister (Head of Legal, Democratic & HR Services/Monitoring Officer), Garry Barclay (Head of Shared Assurance Services), James Thomson (Principal Management Accountant), Michael Jackson (Principal Financial Accountant), Dawn Highton (Principal Auditor) and Dianne Scambler (Democratic and Member Services Officer)
APOLOGIES: None.
OTHER MEMBERS: Councillor Margaret France, Mark Heap (Grant Thornton UK LLP) and Simon Hardman (Grant Thornton UK LLP)
18.G.1 Declarations of Any Interests
There were no declarations of any interests.
18.G.2 Minutes of meeting Wednesday, 20 September 2017 of Governance Committee
RESOLVED – That the minutes of the Governance Committee meeting held on 20 September 2017 be confirmed as a correct record for signing by the Chair.
18.G.3 HCA Audit of Cotswold House Project
The Committee received a report of the Chief Finance Officer that updated on the Homes and Communities Agency (HCA) audit of the Cotswold House project, as well as lessons learnt and future actions. This would include any actions for the presumed audit of the Primrose Gardens project.
Chorley Council had received £658k allocation from the HCA towards the £858k refurbishment and extension of Cotswold House, with work beginning in August 2016. The initial tender for the work came in £200k under budget and in February 2017 the council received telephone confirmation that the project could carry out further works
Governance Committee Wednesday, 24 January 2018 to the building using the grant allocation. The second phase of work was carried out in June 2017.
The Council had received notification in June 17 that it had been selected from a list of projects in the North West of England to be subject of an audit. Grant Thornton where appointed as the auditors.
The audit findings gave ‘No’ answers to eight questions that had different severity ratings. Although the Council has the opportunity to respond, the likelihood is that the project is likely to receive a red grade for its audit. It should however be pointed out that red grades are common for a Local Authority undergoing its first audit.
It was noted that there had been no money expended on the project that did not meet the criteria outlined in the grant agreement and that the red grade likely to be received by the council is the result of the timing at which the funds were claimed. Although claimed through the HCA’s investment management system on the advice of the HCA’s Grant Manager, there appears to be a difference of opinion on what type of work constitutes the actual start time of the development.
The Council will receive confirmation of the audit in May 2018 and it is proposed that it is signed off by this Committee. Although the assumed red rating will result in a guaranteed audit of the Primrose Gardens development in September 2018, there is no indication that the red rating will result in funds being returned to the HCA.
Lessons learnt from the audit were provided within the report that would be improved upon for the audit of Primrose Gardens later in the year and Members were confident that the officers had done everything that they could to meet the audit’s requirements.
RESOLVED – That the report be noted.
18.G.4 Implications of revised CIPFA Prudential Code and Treasury Management Code
The Chief Finance Officer submitted a report that updated members on CIPFA’s changes to the Treasury Management Code and the proposals from DCLG to change the Prudential Framework of Capital Finance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of meeting Wednesday, 24 January 2018 of Governance CommitteeMinutes | 97 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.