Resolved
To approve the following variation to the programme (which has been included in Appendix B) £150,000 budget to be funded from reserves for capital works to upgrade and unify the network to include access points for improved Wi-Fi coverage.
Council approved this item on Tuesday 28 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve the following variation to the programme (which has been included in Appendix B) £150,000 budget to be funded from reserves for capital works to upgrade and unify the network to include access points for improved Wi-Fi coverage.
6. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
7. None
8. Based on the position as at 31st July 2021, there is a forecast change to the Capital Programme of £350k in terms of slippage across years and £699k increase in programme budgets as detailed in Appendix B.
Corporate priorities
9. The report relates to the following corporate priorities: (please bold all those applicable):
Involving residents in improving their local A strong local economy area and equality of access for all
Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area
Background to the report
10. The capital budget for 2021/22 was set at £38.1m at Council in February 2021. This was increased following approval of the outturn to £46.2m and following the changes detailed in this report now stands at £46.6m the detail of which is shown in Appendix B.
Capital programme
Key issues 11. The total cost of the Council’s capital investment programme for 2020/21 has increased over the quarter from £46.2 million, as approved by Cabinet in the 2020/21 Outturn Report on 17th June 2021, to £46.6 million at 31st July 2021; this includes the variations approved over the last 4 months and those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
12. The net increase in the programme of £0.349 million is detailed in Appendix B.
13. Variations made in respect of schemes that have been approved over the four months to 31st July have resulted in an increase of £0.699 million to the capital programme as follows:
Scheme Increase Increase Approved Date (Reduction) (Reduction) by approved 2021/22 2022/23 and future years £’000 £’000 Planning and Development
Yarrow Meadows (12) Chief 25th / The Willows / Executive/ August Various Play and Director of 2021 Open Space Finance Minor adjustments West Way 75 (note – Chief 25th of which 25 Executive/ August is a Director of 2021 movement Finance from below*) Customer and Digital
ICT Modernisation 150 Executive This report Cabinet / Council Commercial and Property
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 121 KB | Download |
PDF |
Appendix BAppendix B | 141 KB | Download |
PDF |
Capital Budget Monitoring Report 1Report | 284 KB | DownloadRead as text |
Follow Council at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesApproved, as amended. | Approved | Open |
| 22 Sep 2026 | Executive CabinetNoted. | Noted | Open |
| 22 Sep 2026 | Audit and Governance CommitteeNoted. | Noted | Open |
| 22 Sep 2026 | Audit and Governance Committee Annual ReportNoted. | Noted | Open |
| 22 Sep 2026 | Proposed updates and changes to the Council's constitutionTo approve the proposed changes in Appendix 1 that fall outside of that delegation, for consideration by Council at i... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.