Approval granted to the creation of a new capital budget of £340,646 to fund the cottage roof replacement. 2. Approval granted transfer £107,163 from the asset improvements capital budget to undertake associated refurbishment to the cottage 3. Approval granted to the variation of the contract with Bullen Construction to allow the work to be completed.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To agree a new budget to undertake necessary repairs to the cottage roof at the rear of Astley Hall.
Recommendations to Council
2. To agree a new capital budget of £340,646 to fund the cottage roof replacement.
3. To transfer £107,163 from the asset improvements capital budget to undertake associated refurbishment to the cottage
4. To agree the variation of the contract with Bullen Construction to allow the work to be completed.
Reasons for recommendations
5. The cottage roof is in need of urgent repair and a new budget is required to fund the work.
6. The contractor who has completed the renovations to the front of Astley Hall had tendered for this work.
7. Once the slates had been removed we identified a significant amount of structural repairs being required.
8. The value of this additional work would require a variation of the contract.
Other options considered and rejected
9. We cannot simply replace the tiles because the structural disrepair is significant and it would be unsafe to leave it in that condition. 10. We have considered re-tendering this as a separate package of works but this has been discounted because the original contract award included the project to repair the cottage roof.
11. We would incur significant cost if we were to demobilise the current contractor and in effect start again with the scaffolding works and prelims.
12. The repairs have had to be designed with listed building consent in mind and an independent structural engineer has assisted with the solution.
13. The costs submitted have been evaluated by our quantity surveyor and the costs have also been reviewed by our external project team to demonstrate value.
Executive summary
14. The cottage roof at the rear of Astley Hall is in a poor state of disrepair.
15. Work to repair the roof has previously been out to tender but on removing the slates it has become apparent that the amount of work needed is more than originally anticipated.
16. This report requests additional funding to allow the work to be completed so the cottage can be utilised again.
Corporate priorities
17. The report relates to the following corporate priorities:
Involving residents in improving their A strong local economy local area and equality of access for all
Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area
Background to the report
18. The cottage at the rear of Astley Hall has had significant issues with the roof. The building is home to the staff areas, art store and general stores.
19. With the work identified as a priority for the integrity of the building the work was put out to tender alongside the main renovations to provide best value and allow us to get the repairs done at a time when the Hall was due to be closed.
20. In the autumn, once the bat surveys were undertaken, the contractor was able to remove the roof tiles and additional work was identified as the state of repair was significantly worse than anticipated. 21. The extent of the disrepair can be seen here – while it doesn’t show the whole of the roof it equates to about 20% of the roof space on Astley Hall:
Budget and costings
Roof Replacement
22. The contractor submitted their price for the cottage roof repairs as part of a competitive tender process alongside the main renovation works. The breakdown of work included in the original tender was: Item Cost Works allocated to the cottage roof to include £63,136 removal, recover, insulation, leadwork and rainwater goods – this has been extracted from the original bill of quantities Provisional sum for repairs £11,500 Provisional sum for supply of slate £6,900 Allowance for scaffolding £29,343 Allowance for prelims £20,751 Total allocated for roof repairs £131,630
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.