Chorley Borough Council
Audit and Governance Committee, Wednesday 18 March 2026 at 2.30pm

Internal Audit Plan April - September 2026

Approved Finance 2 papers

AI summaryChorley Borough Council's Audit and Governance Committee has unanimously approved the Internal Audit Plan and performance indicators for April to September 2026, covering the council and Chorley Leisure Limited.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUnanimous approval by committee
Money75 audit days to CLLPlus 30 days bought-in resource for ICT
What happens nextPlan runs April to September 2026Then work plan reviewed for October to March 27
Who it affectsCouncil and Chorley Leisure LimitedAll audit engagements in the six-month period

What was decided

The committee approved the Internal Audit Plan and associated indicators. Report P5

Approval is required under the Global Internal Audit Standards in the UK Public Sector. Report P6

Why

The plan is the vehicle for identifying and prioritising audit workload and supports the council's objectives. Report P1, P14

Not approving the plan would mean non-compliance with professional standards. Report P7

The plan was built from council priorities, the corporate risk register, director engagement, and other assurance sources. Report P17

What happens next

The in-house team will deliver the plan, with external support bought in for specialist ICT engagements. Report P23

A revised needs analysis and stakeholder engagement will set the work plan for October 2026 to March 2027. Report P15

Performance indicators covering 90% targets for plan completion, satisfaction, and actions implemented will be monitored and reported to the committee. Report P25, P26

The money

  • 75 audit days Provided to Chorley Leisure Limited by the Internal Audit Service Report P21
  • 30 days Bought-in resource for specialist ICT engagements Report P23, P24

Options considered

  • Chosen: Approve the Internal Audit Plan and indicators. Required by Global Internal Audit Standards in the UK Public Sector Report P5, P6
  • Rejected: Do not approve the plan. Would lead to non-compliance with professional standards Report P7

Implications

  • Risk: The plan is risk-based and built from the corporate risk register and other assurance sources. Report P12, P17
  • Equalities: The report has no direct implications on equality and diversity. Report P30
  • Climate: The work does not impact the council's climate change and sustainability targets. Report P28
  • Staffing: The in-house team is 0.6 FTE Head of Audit and Risk, 0.8 FTE Senior Auditor, 2 FTE Auditor, and 1 FTE Trainee Auditor. Report P24

Who and where

  • Chorley Borough Council Report P18
  • Chorley Leisure Limited Report P21
  • Shared Senior Management Team, Directors and Heads of Service Report P11

Timeline

  • 13 February 2026: Report authored by the Head of Audit and Risk Report P39
  • April 2026 to September 2026: Internal Audit Plan period covered by this approval Report P15, P18
  • October 2026 to March 2027: Work plan to be set after revisiting audit needs analysis Report P15

Plain English for the jargon

  • FTE: Full-time equivalent, a measure of staff capacity
  • CLL: Chorley Leisure Limited
  • Global Internal Audit Standards: Professional standards for internal audit in the UK public sector
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66

Resolved

Resolved (unanimously): That the Internal Audit Plan and associated indicators be approved.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Audit and Governance Committee

Purpose of the report

1. This report sets out the programme of work to be undertaken by the Internal Audit Service. The Internal Audit Plan is the vehicle by which audit workload is identified and prioritised.

The main purposes of the report are to:

• Remind members of the respective roles of managers and Internal Audit to maintain a sound system of governance and internal control within the Council. • Provide details of the Internal Audit Plan and associated performance indicators.

Recommendations to Committee

2. That the Committee approve the Internal Audit Plan and associated indicators.

Reasons for recommendations

3. Audit and Governance Committee approval of the Internal Audit Plan is a requirement of the Global Internal Audit Standards in the UK Public Sector. Other options considered and rejected

4. To not approve the plan which would lead to a non-compliance with professional standards.

Corporate priorities

5. The report relates to the following corporate priority: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities

The Role of Management and Internal Audit

6. The responsibility for implementing a strong system of governance and internal control within the Council lies primarily with the Shared Senior Management Team. Directors and Heads of Service need to ensure that they maintain effective control procedures not least because services and business systems are subject to on-going change.

7. Internal Audit is an independent appraisal function whose core objective is to evaluate and report on the adequacy of the Council’s system of governance, risk management, and internal control. In the main this is achieved through an annual programme of reviews, following a detailed risk assessment of audit need.

Development of the Internal Audit Plan

8. Global Internal Audit Standards Principle 9.4 states that “the Chief Audit Executive must create an internal audit plan that supports the achievement of the organisations objectives.”

9. To enable Internal Audit to be flexible and responsive to ongoing changes in priorities, strategy, operational arrangements, external factors that may increase the Council’s exposure to risk and keep pace with to emerging risks across the organisation, the Internal Audit Plan is only developed for April to September. The process is then to revisit the audit needs analysis and to liaise with key stakeholders to consider any new and emerging risks to identify the work plan for October to March 27.

Compilation of the Audit Plan

10. The Internal Audit Plan April – September has been constructed after taking into consideration the following: • The Council’s priorities / strategic plan • A review of corporate strategies • The corporate risk register • Information taken from other assurance processes within, and external to, the Council, including External Audit and inspection reports • Direct engagement with Directors • The skills, knowledge, and experience of audit staff • Professional judgement on the risk of fraud and error • Annual Governance Statement and Service Assurance Statements.

11. The Internal Audit Plan contains the programme of audit engagements for the period of April 26 to September 26 and is shown at Appendix A. This clearly shows the link between the work of Internal Audit, strategic and operational risks, and corporate objectives. The engagements are clearly highlighted with the quarter for completion. The plan also details our involvement with key project teams assisting with advice and guidance on risk management, internal control, and governance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Plan April: September 2026Appendix A 15 KB Download
PDF
Internal Audit Plan April: September 2026Report 105 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 24 attended
AP
Councillor Alan PlattChair, present
MC
Councillor Mark CliffordVice-Chair, present
MB
Councillor Michelle BeachCommittee Member, present
JB
Councillor Julia BerryCommittee Member, present
MB
Councillor Michelle BrownCommittee Member, present
GF
Councillor Gordon FranceCommittee Member, expected
CH
Councillor Christine HeydonCommittee Member, present
DM
Councillor Dedrah MossCommittee Member, present
CA
Craig AinsworthCo-Optee, apologies
CF
Charlotte Fitch Independent MemberCo-Optee, apologies
PR
Peter Ripley Independent PersonObserver, in attendance
NH
Neil HaltonOfficer, in attendance

All 24 on the meeting page

On this subject at Chorley

Search all
  1. Internal Audit Plan April - September 2026This decision
  2. Internal Audit Annual Report and Opinion 2025-2026 ~ Chorley LeisureNoted
  3. Internal Audit Charter and Strategy UpdateApproved
  4. Internal Audit Annual Report and Opinion 2025/2026Noted
  5. Internal Audit - Compliance with the Global Internal Audit StandardsNoted
  6. Internal Audit Strategy and CharterApproved

More from Chorley Audit and Governance Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 Minutes of meeting Wednesday, 27 May 2026 of Audit and Governance CommitteeResolved (unanimously) – That the minutes of the meeting held on Wednesday, 27 May 2025, be agreed as an accurate rec... Agreed Open
22 Jul 2026 External Audit UpdateResolved – That the report be noted . Noted Open
22 Jul 2026 Proposed updates and changes to the Council's ConstitutionResolved – i) It was noted that, following consideration by this Committee, the proposed changes to the Constitution ... Noted Open
22 Jul 2026 Internal Audit Annual Report and Opinion 2025-2026 ~ Chorley LeisureResolved – That the report for the year ended 31 March 2026 be noted. Noted Open
22 Jul 2026 Health and Safety Annual Report 2025/26Resolved – 1. That the Health and Safety Annual Report 202/25 be noted; 2. That the Health and Safety Team Leader con... Noted Open