Risk Management Annual Report

Noted Finance 2 papers

AI summaryChorley Council's Audit and Governance Committee noted the Risk Management Annual Report covering 2025/2026, with no financial implications identified.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAnnual risk management report received and noted by committee
MoneyNoneNo direct financial implications from the report
What happens nextPlans for 2026/2027Embed risk management in all council activities
Who it affectsCouncil-wide risk managementCovers both corporate and operational objectives

What was decided

The committee noted the Risk Management Annual Report for the year ended 31 March 2026. Report P3

Members were informed of risk management activity delivered during 2025/2026 and given an overall conclusion on the effectiveness of current arrangements. Report P1, P9, P10

Why

The committee's terms of reference require it to monitor the effective development and operation of risk management in the council, and this report fulfils that requirement. Report P4

The approach to risk management is considered to comply with the applicable regulatory and statutory framework. Report P20

What happens next

The council will work to ensure risk management is embedded within all council activities during 2026/2027. Report P10

The next annual report is expected to be presented to the committee for the 2026/2027 financial year. Report P9, P10

Options considered

  • Chosen: Note the report. Fulfils the committee's terms of reference to monitor risk management Report P3, P4
  • Rejected: None. No other options were considered Report P6

Implications

  • Risk: Management of risk throughout the council is a key aspect of the governance framework, and the report highlights differing arrangements to manage risk and mitigations. Report P16
  • Legal: The risk management approach is considered to comply with the applicable regulatory and statutory framework. Report P20
  • Equalities: There are no equality implications or considerations contained within the report. Report P14
  • Climate: The report does not impact on climate change, and all environmental considerations are in place. Report P12

Who and where

  • Chorley Borough Council's governance framework and risk management arrangements Report P9, P16
  • All council directorates responsible for corporate and operational objectives Report P9

Timeline

  • Year ended 31 March 2026: Reporting period covered by the annual report Report P1, P3, P9
  • 2026/2027: Forward year in which risk management will continue to be embedded in council activities Report P10
  • Thursday, 28 April 2026: Date the report was authored by the Head of Audit and Risk Report P24
  • 2026-05-27: Date the Audit and Governance Committee met and noted the report Report P3
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Resolved – that the report be noted.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Audit and Governance Committee

Purpose of the report

1. The purpose of this report is to inform members of the risk management related activity which has taken place or been delivered during 2025/2026. It provides an overall conclusion on the effectiveness of the risk management arrangements that are in place within the Council.

Recommendations to Committee

2. The Committee is asked to note the report for the year ended 31 March 2026.

Reasons for recommendations

3. The Audit and Governance Committee terms of reference require the Committee to monitor the effective development and operation of risk management in the council. This report fulfils that requirement.

Other options considered and rejected

4. None.

Corporate priorities

5. The report relates to the following corporate priorities Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities Background to the report

6. The Annual Risk Management report provides the Audit and Governance Committee with a summary of the risk management activity that has taken place across the Council for the year ended 31 March 2026. The Risk Management Strategy and associated systems and procedures should ensure that the Council has adequate and effective risk management in place ensuring that both corporate and operational objectives are met.

7. The report also sets an overall conclusion of the current arrangements and plans for 2026/2027 to ensure that risk management is embedded within all council activities.

Climate change and air quality

8. This report does not impact on climate change and all environmental considerations are in place.

Equality and diversity

9. There are no equality implications or considerations contained within this report.

Risk

10. The management of risk throughout the Council is a key aspect of the governance framework. The Annual Report highlights the differing arrangements the Council has in place to effectively manage risk and mitigations.

Comments of the Statutory Finance Officer

11. There are no direct financial implications arising from this report.

Comments of the Monitoring Officer

12. The approach to the Council’s risk management as set out in this report is considered to comply with the applicable regulatory/statutory framework.

Background documents

There are no background papers to this report

Appendices

Appendix A Risk Management Annual Report 2025/2026

Report Author: Dawn Highton Head of Audit and Risk Email dawn.highton@chorley .gov.uk Telephone: 01772 376639 Date: Thursday, 28 April 2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management Annual ReportAppendix A 420 KB Download
PDF
Risk Management Annual ReportReport 57 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 27 attended
AP
Councillor Alan PlattChair, present
MC
Councillor Mark CliffordVice-Chair, present
JB
Councillor Julia BerryCommittee Member, present
MB
Councillor Michelle BrownCommittee Member, present
GF
Councillor Gordon FranceCommittee Member, present
CH
Councillor Christine HeydonCommittee Member, present
DM
Councillor Dedrah MossCommittee Member, present
MT
Councillor Martin ToppCommittee Member, present
CA
Craig AinsworthCo-Optee, apologies
CF
Charlotte Fitch Independent MemberCo-Optee, in attendance
PR
Peter Ripley Independent PersonObserver, in attendance
NH
Neil HaltonOfficer, in attendance

All 27 on the meeting page

On this subject at Chorley

Search all
  1. Risk Management Annual ReportThis decision
  2. Risk Management Strategy - Annual ReviewApproved
  3. Risk Management Annual ReportNoted
  4. Annual Review of Risk Management StrategyApproved
  5. Risk Management StrategyApproved
  6. Risk Management StrategyNoted

More from Chorley Audit and Governance Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 Minutes of meeting Wednesday, 27 May 2026 of Audit and Governance CommitteeResolved (unanimously) – That the minutes of the meeting held on Wednesday, 27 May 2025, be agreed as an accurate rec... Agreed Open
22 Jul 2026 External Audit UpdateResolved – That the report be noted . Noted Open
22 Jul 2026 Proposed updates and changes to the Council's ConstitutionResolved – i) It was noted that, following consideration by this Committee, the proposed changes to the Constitution ... Noted Open
22 Jul 2026 Internal Audit Annual Report and Opinion 2025-2026 ~ Chorley LeisureResolved – That the report for the year ended 31 March 2026 be noted. Noted Open
22 Jul 2026 Health and Safety Annual Report 2025/26Resolved – 1. That the Health and Safety Annual Report 202/25 be noted; 2. That the Health and Safety Team Leader con... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies