AI summaryChorley Council noted reports from its scrutiny committee covering Q4 2025/26 performance, leisure company progress, suicide prevention work and a new scrutiny work programme for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCouncil received scrutiny reports without amendment
Money(£35k) extra DFG admin incomeFrom higher Disabled Facilities Grants delivery in 2025/26
What happens nextNeurodiversity Forum on 28 JulyTask Group to host forum with invited organisations
Who it affectsChorley residents and council staffIncluding NEETs young people and leisure users

What was decided

Council noted the report summarising scrutiny work, performance monitoring, leisure company update, task group progress and the 2026/27 work programme. Report P2, P41

Three new scrutiny reviews were agreed: NEETs with South Ribble, unadopted roads, and women's safety and misogyny. Report P43

Two additional 'spotlight' reports were added to the work programme covering customer services and discretionary funding with partners. Report P42

Why

The Overview and Scrutiny Committee had reviewed Q4 2025/26 performance, found most indicators on track but flagged NEETs and visitor numbers as underperforming. Report P7, P8, P10

The Panel also received the revenue and capital outturn for 2025/26, noting projects including the Woodlands site, CCTV, food waste service and All Seasons Leisure Centre refurbishment. Report P21, P22, P27, P28

The Committee received updates on Chorley Leisure Ltd, the Suicide Bereavement and Prevention Task Group and the Neurodiversity Task and Finish Group, all showing progress. Report P29, P40, P49, P50

What happens next

The Neurodiversity Task Group will hold a forum on 28 July with organisations including the Chorley Together Network. Report P51

Monitoring reports on recruitment and staff retention, and on empty properties, are due at the next Committee meeting in October 2026. Report P46

Executive Member to share information on businesses signed up to the 'Healthy Minds' Charter, and members will receive more leisure company communications. Report P40, P35

The money

  • £35k Additional DFG admin income from more Disabled Facilities Grants delivered in year Report P25
  • 1.4% Increase in visitor numbers against a 2% target Report P10
  • 12.84 days Average time to process council tax support and housing benefit new claims, against 9.61 day target Report P15

Implications

  • Financial: Chorley Leisure Ltd continues to rely on council subsidy, with Brinscall Swimming Pool expected to need ongoing support to remain viable. Report P34
  • Equalities: A scrutiny review on women's safety and misogyny was agreed, and a Neurodiversity Task Group is gathering evidence through staff, councillors and a public forum. Report P43, P49, P50, P51
  • Staffing: Local Government Reform is not seen as an immediate risk to most staff but may affect senior management and create shortages in some areas. Report P23
  • Risk: Members asked for a progress update on embedding GDPR across the council after concerns were raised in the leisure company context. Report P35
  • Other: Targeted one-to-one support will replace group-based work for NEETs after research showed young people were dropping out of groups. Report P9

Who and where

  • 16 to 17 year olds who are NEETs, with new one-to-one support being procured Report P8, P9
  • Visitors to Chorley, with the Destination Management Plan aiming to grow numbers over five years Report P10
  • Council tax and housing benefit claimants, with new staff recruited to speed up processing Report P15
  • Residents using bulky waste collections, who will get appointment times through a new online calendar Report P16
  • Chorley Leisure Ltd users, including over 65s where usage rose 37% through group activities Report P35
  • Neurodiverse residents and staff, the focus of a new Task and Finish Group Report P47, P49

Timeline

  • 25 June 2026: Overview and Scrutiny Performance Panel met Report P2, P4
  • 2 July 2026: Overview and Scrutiny Committee met Report P2, P28
  • 14 July 2026: Full Council received and noted the report
  • 28 July 2026: Neurodiversity Forum to be held by the Task Group Report P51
  • October 2026: Next Overview and Scrutiny Committee meeting to receive monitoring reports on recruitment and empty properties Report P46

Plain English for the jargon

  • NEETs: Young people Not in Education, Employment or Training
  • DFG: Disabled Facilities Grants
  • GDPR: General Data Protection Regulation, the UK data protection framework
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

Noted.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Council

Overview and Scrutiny – Report to Council

1. This report summarises the business considered at the meetings of the Overview and Scrutiny Performance Panel held on 25 June 2026 and the Overview and Scrutiny Committee held on 2 July 2026. It also includes an update on Overview and Scrutiny Task Groups.

2. Please note that the report may not reflect the wording used in the minutes. The You Tube stream and documents relating to the meeting can be found here: Chorley Council - YouTube

Overview and Scrutiny Performance Panel – 25 June 2026

Chorley Quarter Four Performance Monitoring Report 2025/26

3. The Executive Member for Resources, Councillor Peter Wilson presented a report providing a position statement for the Corporate Strategy for quarter four (January to March) 2025/26.

4. The Panel was pleased to note that overall the Council was performing well. The delivery of temporary accommodation at Gillibrand Street and the introduction of food waste collection had been successfully completed, and 15 projects were on track, such as the availability of affordable homes in the borough, decarbonisation of council buildings, and the refurbishment of All Seasons Leisure Centres.

5. It was highlighted that there were two under performing areas: • % of 16 -17 year olds who are NEETs; and • % increase in visitor numbers.

6. With regard to NEETs, the Executive Member for Early Intervention, Councillor Beverley Murray, indicated that a procurement exercise was currently underway to deliver targeted support. This followed an extensive research exercise to establish precisely was required, which revealed for example, that young people tended to drop out of group- based group work and so the focus was to shift to one-to-one support. There would also be an emphasis on local providers and providing support for young people who prefer an alternative to college.

7. As regards visitor figures, the council was underperforming slightly with an increase in only 1.4% against a target of 2%. The Council was seeking to address this through the Destination Management Plan which aimed to position Chorley as a premier destination over the next five years.

Performance Focus – Customer and Digital

8. The Executive Member for Customer, Streetscene and Environment, Cllr Adrian Lowe, presented a report focussed on the performance of the Customer and Digital Directorate, which included Streetscene and Waste, Customer Services and Digital Services.

9. The performance focus report included: • An overall summary of the services • An overview of performance to quarter four 2025/26 • An update on the Corporate Strategy project delivery for Customer and Digital.

10. Councillor Lowe praised all staff in the Customer and Digital Directorate for their hard work and dedication. There were many areas of high performance, often exceeding targets, such as: • Litter bin collections, grass cutting, street sweeping and winter work (hedges/shrubs) • Revenues collection and business rates collection • The high number of visits to the council website and that 100% of ICT digital strategy projects were rated green (on target) at the end of quarter four.

11. It was noted that an underperforming indicator was the “average days to process council tax support and housing benefit new claims”, 12.84 days against a target of 9.61 days. The Panel were assured that the council was now focussing on prioritising new claims and that new staff had been recruited to support this.

12. Other issues raised and responded to were: • Large bulky collections – although they were very often successfully collected on the date booked, it would also be helpful if residents were given an idea of the timeframe to expect before booking. The Panel were informed that a new online calendar system was soon to be implemented, giving an indication of the appointments available.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Overview and Scrutiny Committee and Task and Finish GroupsReport 85 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

38 of 58 attended
DP
Councillor Debra PlattMayor, present
AB
Councillor Aaron BeaverDeputy Mayor, present
SA
Councillor Sarah AinsworthCommittee Member, present
IA
Councillor Irene AmahweCommittee Member, present
JB
Councillor Julia BerryCommittee Member, present
AB
Councillor Alistair BradleyCommittee Member, present
MB
Councillor Michelle BrownCommittee Member, present
OC
Councillor Olga CashCommittee Member, present
MC
Councillor Mark CliffordCommittee Member, apologies
EC
Councillor Ellie CloseCommittee Member, present
JC
Councillor Jonathan CloseCommittee Member, present
LD
Councillor Lesley DuroseCommittee Member, present

All 58 on the meeting page

On this subject at Chorley

Search all
  1. Overview and Scrutiny Committee and Task and Finish GroupsThis decision
  2. Scrutiny Reporting Back - Annual Report of Overview and Scrutiny 2025-26Noted
  3. Minutes of meeting Thursday, 26 March 2026 of Overview and Scrutiny CommitteeApproved
  4. Minutes of the Overview and Scrutiny Performance Panel held on Thursday, 25 June 2026Noted
  5. Overview and Scrutiny Work Programme 2026/27 and Action Monitoring TrackerApproved
  6. Minutes of meeting Thursday, 5 March 2026 of Overview and Scrutiny Performance PanelAgreed

More from Chorley Council

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesApproved, as amended. Approved Open
22 Sep 2026 Executive CabinetNoted. Noted Open
22 Sep 2026 Audit and Governance CommitteeNoted. Noted Open
22 Sep 2026 Audit and Governance Committee Annual ReportNoted. Noted Open
22 Sep 2026 Proposed updates and changes to the Council's constitutionTo approve the proposed changes in Appendix 1 that fall outside of that delegation, for consideration by Council at i... Approved Open