Chorley Borough Council
Executive Cabinet, Thursday 17 September 2026 at 6.30pm

Chorley Quarter One Performance Monitoring Report 2026/27

Noted Executive 5 papers

AI summaryChorley Executive Cabinet noted the quarter one performance monitoring report for 2026/27, showing 88% of corporate strategy projects on track or complete, with three indicators below target by 5% or more.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExecutive Cabinet noted the quarter one performance monitoring report and provided feedback where required
MoneyNot stated
What happens nextOverview and Scrutiny reviewThe Overview and Scrutiny Performance Panel will review the report and make recommendations to Executive Cabinet
Who it affectsAll residents of Chorley boroughThe Corporate Strategy covers housing, green and sustainable borough, enterprising economy, and healthy safe communities

What was decided

Executive Cabinet noted the quarter one performance monitoring report for 2026/27 and provided feedback where required.

Why

The council's performance framework sets out the process for reporting progress against the priorities in the Corporate Strategy. Robust monitoring ensures that the council continues to deliver and achieve the best outcomes for residents. Report P6

A new Corporate Strategy was approved at Council on 18 November 2025 refreshing the delivery programme and performance indicators. This report highlights project delivery between 1 April and 30 June 2026 and performance progress at the end of quarter one 2026/27. Report P9

The overall performance of the corporate strategy delivery programme is good. Of the 17 projects in the strategy, 15 (88%) are rated on track (green), two (12%) are rated complete (blue), and none (0%) forecast delays or concerns (amber). Report P10

What happens next

Overview and Scrutiny Performance Panel is asked to review and make appropriate recommendations to Executive Cabinet. Report P5

The council is preparing a new business support programme, including grant funding for local businesses, which is expected to launch by the end of quarter two 2026/27. Report P68

Two organisations, Lancashire Community Foundation and First Kicks Foundation have been awarded Youth NEET and Resilience Support Grant funding, with grant agreements currently being finalised ahead of programme mobilisation in August 2026. Report P96

Options considered

  • Chosen: To note the report and provide feedback where required. This is the standard monitoring procedure for the Corporate Strategy performance framework Report P3
  • Rejected: No other options were considered. The council is required to report this information under its performance framework Report P7, P8

Implications

  • Financial: There are no direct financial implications arising from this report. The financial performance of the council is captured in the quarterly financial reports to Executive Cabinet. Report P139
  • Legal: There are no direct legal implications arising from this report. Report P141
  • Other: The work noted in this report has a positive impact on the council's carbon emissions and the wider climate emergency and sustainability targets of the council. Report P133
  • Risk: Risk registers are completed for each project, which ensures that risks are assessed and managed on an ongoing basis for the corporate strategy. The number of green rated projects provides a positive outlook and confidence in delivery. Report P137, P138

Who and where

  • All residents of Chorley borough Report P6
  • Local businesses seeking support Report P67
  • Young people aged 16-17 in Chorley Report P90
  • Suppliers of Chorley Council Report P115

Timeline

  • 18 November 2025: Corporate Strategy approved at Council Report P9, P16
  • May to June 2026: Chorley Resident Survey 2026 carried out by NWA Research Report P119
  • End of quarter two 2026/27: New business support programme expected to launch Report P68
  • 1 April to 30 June 2026: Quarter one 2026/27 reporting period Report P9
  • August 2026: Youth NEET and Resilience Support Grant programme mobilisation Report P96
  • Quarter three 2026/27 onwards: Council will start to explore options to extend NEET support beyond March 2027 Report P97

Plain English for the jargon

  • NEET: Not in Education, Employment, or Training
  • HMO: House of Multiple Occupancy
  • UKSPF: UK Shared Prosperity Fund
  • CIPFA: Chartered Institute of Public Finance and Accountancy
  • FTE: Full Time Equivalent
  • EET: Education, Employment or Training
  • NNDR: National Non-Domestic Rates (Business Rates)
  • EIA: Environmental Impact Assessment
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

To note the report and provide feedback where required.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. To provide Executive Cabinet with a position statement for the Corporate Strategy for quarter one (April to June) 2026/27.

Recommendations to Executive Cabinet

2. Executive Cabinet is asked to review the report and provide feedback where required.

Recommendations to Overview and Scrutiny Committee

3. Overview and Scrutiny Performance Panel is asked to review and make appropriate recommendations to Executive Cabinet.

Reasons for recommendations

4. The council’s performance framework sets out the process for reporting progress against the priorities in the Corporate Strategy. Robust monitoring ensures that the council continues to deliver and achieve the best outcomes for residents.

Other options considered and rejected

5. No other options were considered as we are required to report this information. Corporate priorities 6. The report relates to the following corporate priorities: • Housing where residents can live well • A green and sustainable borough • An enterprising economy with vibrant local centres in urban and rural areas • Healthy, safe and engaged communities

Executive Summary 7. A new Corporate Strategy was approved at Council on 18 November 2025 refreshing the delivery programme and performance indicators. This report highlights project delivery between 1 April and 30 June 2026 and performance progress at the end of quarter one 2026/27.

8. The overall performance of the corporate strategy delivery programme is good. Of the 17 projects in the strategy, 15 (88%) are rated on track (green), two (12%) are rated complete (blue), and none (0%) forecast delays or concerns (amber).

9. Performance against the Corporate Strategy and Key Organisational Indicators continues to be monitored. Of the indicators that can be reported at quarter one, 13 (87%) corporate strategy measures and five (83%) key organisational measures are performing on or above target (green) or within the 5% threshold (amber).

10. In accordance with the Performance Management Framework, reporting is done by exception, to draw attention to projects that are off track (rated red), forecast delays or concerns (rated amber) or to indicators where performance is below target by 5% or more (rated red). This report highlights the areas where improvement is most required.

11. Appendix A provides a visual presentation of overall performance and progress updates on all other projects and performance indicators.

12. This report also includes the findings of the Chorley Resident Survey 2026 which provides valuable insight into residents’ perceptions, priorities and satisfaction with the borough and council services.

13. The findings show that overall resident satisfaction has increased, demonstrating that the Corporate Strategy continues to reflect and address the needs of residents. Findings will be used to inform future planning and improvement activity.

Background to the report 14. The Corporate Strategy was approved by Council on 18 November 2025 with activity and resources targeted towards 17 priority projects, which are delivered over a period of 12-18 months. 15. The 22 Corporate Strategy and six Key Organisational performance indicators within this report reflect those agreed at Council as part of the refreshed 2025/26 Corporate Strategy.

16. A colour rating system is used to indicate status. A tolerance of 5% has been set for performance indicators as the accepted variance between actual performance and target, so that attention is paid to those indicators that are performing outside of the tolerance. Those that are outside of tolerance are significantly below target and where performance needs to improve the most. The colour rating system for performance is as follows:

Projects

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Chorley Quarter One Performance Monitoring Dashboard 2026/27Appendix A 1.2 MB Download
PDF
Chorley Resident Survey 2026 Topline FindingsAppendix B 102 KB Download
PDF
Chorley Resident Survey 2026 NWA Research ReportAppendix C 6.6 MB Download
PDF
Resident Satisfaction Polling: Round 40Appendix D 1.7 MB Download
PDF
Chorley Quarter One Performance Monitoring Report 2026/27Report 126 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 20 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, present
MF
Councillor Margaret FranceCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
CS
Chris SinnottOfficer, in attendance
VW
Vicky WillettOfficer, in attendance
KL
Kay LoveladyOfficer, expected
TS
Tasneem SafdarOfficer, in attendance
NH
Neil HaltonOfficer, in attendance
CW
Caroline WolfendenOfficer, expected

All 20 on the meeting page

On this subject at Chorley

Search all
  1. Chorley Quarter One Performance Monitoring Report 2026/27This decision
  2. Chorley Quarter Four Performance Monitoring Report 2025/26Decided
  3. Chorley Quarter Four Performance Monitoring Report 2025/26Decided
  4. Chorley Quarter Three Performance Monitoring Report 2025-26Decided
  5. Chorley Quarter Three Performance Monitoring Report 2025-26Noted
  6. Chorley Quarter Two Performance Monitoring Report 2025-26Agreed

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Strategic Risk RegisterTo note and comment on the strategic risks, control measures and planned actions as set out in the report. Noted Open