Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor application PA26/00949
MoneyNot stated
What happens nextNot stated
Who it affectsCarbis Bay housing siteLand south of Airvanlea, Carninney Lane
What was decided
Permission in Principle for application PA26/00949 was granted, allowing in principle the construction of up to 9 dwellings, with a stated minimum of 5 and maximum of 9.
Why
The officer recommended approval and the Committee granted permission on that basis, with the Proposer's reasons for approval recorded as set out in the report. Report P1
Who and where
The applicant (Commprop Ltd) for the Carbis Bay site
Timeline
2026-07-20: West Sub-Area Planning Committee decision
11.01 to 11.11am: Comfort break taken at the conclusion of the item
Plain English for the jargon
Permission in Principle: Planning consent that establishes whether a site is suitable for housing in principle, ahead of later technical approval.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemWPL/85
Resolved
RESOLVED that Permission in Principle for Application No. PA26/00949 be granted. The reasons given by the Proposer for wishing to approve the application were as set out in the report. Noted That the Committee adjourned for a comfort break at the conclusion of the above item between 11.01 and 11.11am.
Word for word from the decision Cornwall published for this meeting.Source: democracy.cornwall.gov.uk
Report to West Sub-Area Planning Committee, 12 pages
Information Classification: PUBLIC Information Classification: PUBLIC Information Classification: PUBLIC
Development Management Development Management Service
West Sub-Area Planning Committee Report 20 July 2026
Application number: PA26/00949 Site address: Land South Of Airvanlea Carninney Lane Carbis Bay Cornwall Proposal: Permission in principle for the construction of up to 9 dwellings (minimum of 5, maximum of 9) Application type: Permission in Principle Parish: St. Ives Applicant: Commprop Ltd Target date for decision: 20 March 2026, with Extension of Time agreed until 22nd July 2026 Reason for application being At the request of the Electoral Division Member, to address called to Committee: concerns raised over policy issues and other material planning considerations. Electoral Division Member: Luke Rogers CC Case Officer: Phil Brookes Link to view full documents: http://planning.cornwall.gov.uk/online- applications/applicationDetails.do?activeTab=summary&keyVal=TAAWJVFG1 YY00
RECOMMENDATION: Granted Report sign off Report cleared by: Date: Legal: Ben Curnow 01/07/26 Head of Service Mark Broomhead 06/07/26 representative:
Balance of Considerations and Conclusion
1. This application seeks 'Permission in Principle' (PIP) for the construction of a minimum of 5 and a maximum of 9 open-market dwellings at a site lying off Carninney Lane, just outside of the settlement at Carbis Bay. Information Classification: PUBLIC
2. Planning Practice Guidance advises that PIP is an alternative way of obtaining planning permission for housing-led development. The PIP consent route has two stages: the first (‘permission in principle’) establishes whether a site is suitable in principle and the second (‘technical details consent’) is when the detailed development proposals are assessed. This application relates to the first stage.
3. The scope of the considerations for PIP is limited to location, land use and the amount of development permitted. All other matters are considered as part of a subsequent technical details consent application if PIP is granted.
4. The Cornwall Local Plan is over 5 years old and the local planning authority (LPA) is unable to demonstrate a five-year supply of housing land against the relevant number of homes required. In these circumstances the NPPF (2024) states that 'policies that are most important for determining the application' are out of date and should be given little weight in decision making. The presumption in favour of sustainable development then applies, meaning that proposed developments should be granted planning permission unless their adverse impacts significantly and demonstrably outweigh their benefits when assessed against the policies of the Framework when taken as a whole, (this is also known as the 'tilted balance.’)
5. The site lies outside of the settlement and in terms of location its development for open market housing would not accord with current planning policies, notably polices 3 and 7 of the Cornwall Local Plan (2010-2030). However, the site is in close physical proximity to the urban area, is readily accessible by a wide range of transport options and is not overly prominent in the wider landscape. As such, notwithstanding that details of design and density of development would be determined under the technical details (2nd stage) of the PIP process, the adverse impacts resulting from the development are not, intrinsically, considered to be of such significance to overcome the housing need and as such it is recommended that the proposal is granted.
Proposal
6. This application seeks permission in principle for the erection of a minimum of 5 and and a maximum of 9 dwellings on agricultural land sited off Carninney Lane in Carbis Bay. The site comprises an area of agricultural land that extends over approx. 0.7 hectares.
7. There is a block built stable and associated hardstanding on the site, with the remainder of the land being undeveloped and used for grazing horses. Information Classification: PUBLIC
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies