Risk Update Report

Decided Finance 3 papers

AI summaryCornwall Council's Audit Committee took assurance on risk management and counter-fraud arrangements, noting that the Climate Change and Financial Sustainability strategic risks both increased in score this quarter.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedOn risk management and strategic and counter-fraud risk arrangements
MoneyNo direct financial implicationsCommittee is not being asked to approve spending
What happens nextWorkshop in October 2026Risk appetite statement to November Audit Committee
Who it affectsCouncil's customers and residentsThrough strengthened risk and counter-fraud controls

What was decided

The Committee took assurance that arrangements are in place to provide it with relevant risk management information in year, in line with its Terms of Reference. Report P1, P7

The Committee took assurance that arrangements for strategic risks and the fraud risk assessment framework are in place, and that these risks have been identified and assessed. Report P2, 2.1

Why

The Audit Committee's remit is to obtain assurance that risk management arrangements are in place and working effectively, including fraud risk assessment and monitoring of risk-related issues. Report 1.1, P4, 8.2

Two strategic risk scores rose this quarter: Climate Change and Ecological Breakdown moved from 16 to 20, and Financial and Economic Sustainability from 20 to 25, against a backdrop of a forecast Q1 overspend of £17.008m and £9.915m of red-rated financial risks. Report 2.10, P19

What happens next

A workshop with the Council Director's Team is planned for October 2026 to refresh the strategic risks, with any changes to be reported back to the Audit Committee. Report 2.11, P21

A draft risk appetite statement, including assessment of statutory officers' risk appetite, will be presented to the Audit Committee at its November meeting, alongside plans for member engagement. Report 2.11, P21

The strategic risks and priority risk narratives are to be considered by Cabinet on 23 September as part of the quarter one performance report. Report 2.9

The money

  • £17.008m Forecast Q1 overspend identified in the Financial and Economic Sustainability risk Report 2.10, P19
  • £9.915m Red-rated financial risks noted within the Financial and Economic Sustainability risk Report 2.10, P19
  • 83.7% Forecast saving delivery against the approved MTFP target Report 2.10, P19
  • 87.9% Saving delivery forecast when mitigated savings are included Report 2.10, P19
  • 14% Reduction in operational greenhouse gas emissions in the last financial year Report 2.10, P19
  • 45% Overall reduction in operational greenhouse gas emissions from the 2019 baseline Report 2.10, P19

Options considered

  • Chosen: Take assurance from the report's details on risk and counter-fraud arrangements. Preferred option as set out by officers; arrangements were judged adequate Report 10.1, P42, P44
  • Rejected: Decline to take assurance and request further information. Not taken up by the Committee Report P42, P44

Implications

  • Financial: No direct financial implications arise from the recommendations, though effective risk and counter-fraud arrangements support the Council's overall financial sustainability, including exposure to fraud, cyber incidents and economic volatility. Report 6.1, 6.2, 6.3, P30
  • Legal: The Accounts and Audit Regulations 2015 require adequate financial management and internal control arrangements, including risk management; no adverse legal or governance implications arise from this report. Report 7.1, 7.3, P34
  • Risk: Two of eight strategic risks have worsened in score this quarter, with continued reliance on external funding and new delivery partnerships flagged for the climate risk, and significant financial pressures flagged for the Financial and Economic Sustainability risk. Report 2.10, P19, 2.8
  • Staffing: Work to map the audit and fraud universe has begun within the Community and Wellbeing Directorate, with the aim of covering all directorates ahead of next year's audit planning process. Report 2.6, P13
  • Other: Data quality exceptions in the corporate risk dashboard will continue to be monitored, and a channel shift to a new risk data warehouse will allow a data cleansing exercise to be undertaken. Report 2.10, P19

Who and where

  • The Council's customers and the residents of Cornwall, who benefit from a strong control environment and effective risk and governance arrangements Report 3.1, P23, P25
  • Council officers and members, who can access the strategic risk dashboard Power BI through the performance hub Report 2.9
  • Service areas scheduled for 2026-2027 Counter Fraud reviews: Procurement, Housing Allocations, Concessionary Travel and School Placements Report P12

Timeline

  • 22 May 2026: Risk Management Framework approved by the Audit Committee at its previous meeting Report 2.8, P15, 4.1, P26
  • 23 September: Strategic risks and priority risk narratives to be considered by Cabinet as part of the quarter one performance report Report 2.9
  • 26 June 2026: Strategic risks and associated scores agreed by the Council Directors Team Report 5.1, P28
  • October 2026: Workshop planned with the Council Director's Team to refresh strategic risks against the latest global risk intelligence Report 2.11, P21
  • November: Draft risk appetite statement to be presented to the Audit Committee Report 2.11, P21
  • 2026-2027: Counter fraud reviews scheduled for Procurement, Housing Allocations, Concessionary Travel and School Placements Report P12

Plain English for the jargon

  • MTFP: Medium Term Financial Plan, the Council's multi-year spending and savings plan
  • NAFN: National Anti-Fraud Network, a body sharing fraud intelligence
  • CIFAS: Credit Industry Fraud Avoidance System, a fraud data sharing organisation
  • Three lines of assurance: Model mapping risk controls across operational management, oversight functions and independent internal audit
  • Residual risk: The level of risk remaining after controls and mitigations are applied
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemA/191

Resolved

RESOLVED that : 1. The Committee takes assurance that arrangements are in place to provide the Committee with the relevant information, in year, to allow them to discharge their duties in regard to Risk Management and in line with its Terms of Reference. 2. The Committee takes assurance that the arrangements in respect of the Council’s strategic risks and the framework by which fraud risks are assessed are in place and that all of these risks have been identified and assessed.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Audit Committee

Recommendations

1. That the Committee takes assurance that arrangements are in place to provide the Committee with the relevant information, in year, to allow them to discharge their duties in regard to Risk Management and in line with its Terms of Reference. Information Classification: PUBLIC

2. That the Committee takes assurance that the arrangements in respect of the Council’s strategic risks and the framework by which fraud risks are assessed are in place and that all of these risks have been identified and assessed.

Executive summary

1.1It is the remit of the Audit Committee to obtain assurance that risk management arrangements are in place and are working effectively. In line with the Committee’s terms of reference this includes:

• Considering the Council’s framework of assurance and ensure that it adequately addresses the risks and priorities of the Council • Reviewing the assessment of fraud risks and potential harm to the Council from fraud and corruption • Monitoring the effective development and operation of Risk Management in the Council • Monitoring progress in addressing risk-related issues reported to the Committee.

2. Purpose of Report and key information

2.1This report assists the Committee in that it provides assurance in respect of the arrangements currently in place to assess fraud risks to the Council and details plans to support services identify potential fraud risks and ensure that appropriate counter fraud controls are in place. It also provides assurance that the Council has identified, assessed and reviews its strategic risks to the delivery of the business plan and that these risks are aligned to its priorities.

Risk Management Assurance

2.2The Committee is in receipt of reports, in year, in regard to internal audit, risk and counter fraud activities which provide assurance that Risk Management arrangements are in place and working effectively. Together, these reports provide the required assurance as determined in the Committee’s Terms of Reference in relation to Risk management. The diagram below demonstrates the type of reports and details of activities the Committee receives linked to each of the responsibilities. Information Classification: PUBLIC

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Update Report: Appendix 1 /191Appendix 334 KB Download
PDF
Risk Update Report: Appendix 2 /191Appendix 412 KB Download
PDF
Risk Update ReportReport 358 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
LM
Laurie MagowanChair, present
NB
Nicola BoaseVice-Chair, present
PA
Paul AshtonCommittee Member, present
RB
Richard BarkerCommittee Member, present
KL
Karen La BordeCommittee Member, present
MB
Mark BurnettCommittee Member, present
JC
Jim CandyCommittee Member, apologies, sent representative
JG
Julian GermanCommittee Member, present
RP
Rob ParsonageCommittee Member, apologies
GM
George Masters Independent Lay MemberCo-Optee, present
ES
Elizabeth Seale Independent Lay MemberCo-Optee, present
SW
Steven WebbSubstitutes, present as substitute

On this subject at Cornwall

Search all
  1. Risk Update ReportThis decision
  2. Individual Decision - Key Performance Indicators for Cornwall Fire and Rescue Service as part of the Community Risk Management PlanApproved
  3. Unserviceable Vessels, at Risk and WrecksAgreed
  4. Cornwall Fire and Rescue Service Community Risk Management Plan 2026-2030 Draft DocumentDecided
  5. Cornwall Fire and Rescue Service - Community Risk Management Plan 2026-2030Approved

More from Cornwall Audit Committee

All decisions
MeetingDecisionOutcome
25 Sep 2026 Minutes of the Meeting Held on 22 May 2026RESOLVED that the minutes of the meeting of the Audit Committee held on 22 May 2026 were correctly recorded and that ... Decided Open
25 Sep 2026 Audit Update and Sector BriefingRESOLVED that: That the Audit Committee reviews the External Auditor’s Update and Sector Briefing for Cornwall Counci... Decided Open
25 Sep 2026 Internal Audit Plan Refresh & Progress ReportRESOLVED that: 1. That the Committee notes the delivery against the Key Performance Indicators for internal audit and... Decided Open
22 May 2026 Election of ChairmanRESOLVED that Cllr Magowan be re-elected as Chairman of the Audit Committee. Decided Open