AI summaryCornwall Harbours Board committed up to £23,440.89 for fixed lighting improvements on South Pier in Penzance and delegated an additional £25,000 from the Cornwall Harbours General Reserve Fund for expedited works. [D]
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSouth Pier fixed lighting receives a reserve fund commitment. [D][2.1]
Money£23,440.89 maximum; £25,000 additional [D]Project funding, plus delegated funding for other works. [D][6.2]
What happens nextComplete lighting and delegated works [D]Chairman consultation is required before delegated works. [D]
Who it affectsSouth Pier users and visitors [3.1]Harbour must stay safe, open and efficient. [3.1]
What was decided
The Board committed up to £23,440.89 from the Cornwall Harbours General Reserve Fund to improve fixed lighting on South Pier. Report 2.1
It delegated power, in consultation with the Chairman, to use an additional £25,000 for other works that can be expedited as a one off project.
Why
A survey found that the existing lighting installation did not meet the required standard. Report 1.1, P2
The works are needed to maintain the harbour's statutory duty to provide a safe, open and efficient facility for users and visitors. Report 3.1, 7.1
Without approval, the harbour would breach the Health and Safety at Work Act, fail to comply with the Port and Marine Facilities Safety Code, and require continued hiring of mobile tower lighting. Report 7.1, 8.1
What happens next
Deliver the groundworks and National Grid connection, and install three additional lighting columns with lanterns and isolators. Report 1.2, 2.1, 6.2
Consult the Chairman before using the additional £25,000 for other works that can be expedited.
The money
£23,440.89 Maximum lighting commitment and total project cost Report 2.1, 6.2
£25,000 Additional General Reserve Fund authority for expedited works
£21,417.18 Groundworks and connection to the National Grid Report 2.1, 6.2
£2,023.71 Supply and installation of lighting columns, lanterns and isolators Report 2.1, 6.2
£242,669 Balance after previously approved expenditure on 31 March 2026 Report 6.3
£219,228 Remaining fund balance if the lighting expenditure is approved Report 6.3
£913,919 General Reserve Fund balance on 31 March 2026 Report 6.3
Chosen: Fund South Pier lighting improvements. The existing lighting did not meet the required standard, and the works would bring South Pier into line with lighting requirements. Report P23, 1.1, P2, 7.1
Rejected: Withhold funding for the proposed works. The berth would not meet lighting requirements and would require continued hired mobile tower lighting. Report P24, 8.1
Implications
Financial: The stated total project cost is £23,440.89. Groundworks and the National Grid connection cost £21,417.18, while the lighting columns, lanterns and isolators cost £2,023.71. Report 2.1, 6.2
Financial: The report projected a remaining General Reserve Fund balance of £219,228 after the lighting expenditure. Report 6.3
Financial: The delegation permits an additional £25,000 to be used for other works that can be expedited, following consultation with the Chairman.
Legal: If the works were not approved, the harbour would breach the Health and Safety at Work Act and would not comply with the Port and Marine Facilities Safety Code. Report 7.1
Risk: If funding was withheld, the berth would not meet lighting requirements and would need continued hired mobile tower lighting. Report 8.1
Other: The harbour must continue to provide a safe, open and efficient facility for users and visitors. Report 3.1
Other: Mobile tower lighting supports operations during the hours of darkness. Report 1.1
Other: The proposal supplements existing lighting with three additional columns; replacement heads on existing poles are already completed. Report 1.2
31 March 2026: The General Reserve Fund balance was £913,919 before £671,250 of previously approved expenditure. Report 6.3
2026-11-12: The Board committed the lighting funding and delegated additional General Reserve Fund use.
completed: Replacement heads on existing poles had been completed. Report 1.2
Plain English for the jargon
Cornwall Harbours General Reserve Fund: Reserve used to finance the South Pier lighting works. [2.1][6.1]
Fixed lighting: Lighting requested for South Pier to supplement the existing installation. [1.2][2.1]
Mobile tower lighting units: Units deployed during darkness to support operations. [1.1]
Statutory duty: Providing a safe, open and efficient harbour facility for users and visitors. [3.1]
HSE ACOP: Safety in Docks, listed as a background paper. [12.1]
PSS SIP009: Guidance on Lighting, listed as a background paper. [12.2]
Health and Safety at Work Act: The legislation the harbour would breach if the works were not approved. [7.1]
Port and Marine Facilities Safety Code: The code the harbour would not comply with if the works were not approved. [7.1]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCHB53
Resolved
RESOLVED to commit to fund improvements to lighting on South Pier in Penzance Harbour from the Cornwall Harbours General Reserve Fund to a maximum of £23,440.89, and, in consultation with the Chairman, delegate the power to use an additional £25,000 of General Reserve Fund to complete other works that can be expedited as a one-off project.
Word for word from the decision Cornwall published for this meeting.Source: democracy.cornwall.gov.uk
1.1Mobile tower lighting units have been deployed on South Pier, Penzance, to support operations during the hours of darkness after a survey identified that Information Classification: CONTROLLED
the existing lighting installation did not meet the required standard (see background papers).
1.2Cornwall Council’s lighting contractor, Enverveo, undertook a site visit and drafted a proposal to supplement existing lighting. This proposal includes replacement heads on existing poles (completed) and 3 additional columns. 2 Purpose of Report and key information
2.1The purpose of this report is to request use of the Cornwall Harbours General Reserve Fund to improve fixed lighting on South Pier. 2.2 The cost of the groundworks and connection to the National Grid is £21,417.18, with an additional £2,023.71 required for the supply and installation of lighting columns, lanterns and isolators, resulting in a total project cost of £23,440.89. The balance of the Cornwall Harbours General Reserve Fund as of 31 March 2026, after accounting for previously approved expenditure, is £242,669. Should this expenditure be approved, the remaining fund balance will reduce to £219,228.
3 Benefits for Customers/Residents
3.1By undertaking the lighting improvements, the harbour will continue to meet its statutory duty of providing a safe, open and efficient facility for users and visitors. 4 Relevant Previous Decisions
4.1None
5 Consultation and Engagement
5.1Cornwall Harbours Board
5.2Penzance Stakeholders Group
5.3Isles of Scilly Steamship Group (principal user of South Pier)
6 Financial Implications of the proposed course of action/decision
6.1This report seeks approval from the Board to fund these works from The Cornwall Harbours General Reserve.
6.2The cost of the groundworks and connection to the National Grid is £21,417.18, with an additional £2,023.71 required for the supply and installation of lighting columns, lanterns and isolators, resulting in a total project cost of £23,440.89. Information Classification: CONTROLLED
6.3The balance of the Cornwall Harbours General Reserve Fund as of 31 March 2026 was £913,919. After accounting for previously approved expenditure of £671,250, the balance is £242,669. Should this expenditure be approved, the remaining fund balance will reduce to £219,228.
7 Legal/Governance Implications of the proposed course of action/decision
7.1The works will bring South Pier in line with the standard of lighting required. Should the works not be approved harbour will remain non-compliant with lighting requirements. This would be in breach of the Health and Safety at Work Act and will mean non-compliance with the Port and Marine Facilities Safety Code. 8 Risk Implications of the proposed course of action/decision
8.1If Cornwall Harbours Board do not commit to fund these works, the berth will remain non-compliant and require continued mobile tower lighting to be hired.
9 Cornwall Development and Decision Wheel
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.