Contribution towards a business case for the restoration of the former rail connection between Kemble and Cirencester

Agreed Executive 1 paper

Cabinet agreed this item on Monday 12 April 2021. Below is the council's own wording, with the papers it was decided on.

Item136

Resolved

RESOLVED that Cabinet agree to contribute £10,000 towards the cost of the Strategic Outline Business Case and a Secondary Phase Feasibility Study. Record of Voting - for 7, against 0, abstention 0, absent 1.
Word for word from the decision Cotswold published for this meeting. Source: meetings.cotswold.gov.uk

Follow this further

Built from Cotswold's papers

What the report saysPro

Report to Cabinet

COTSWOLD DISTRICT COUNCIL

Name and date of CABINET - 12 APRIL 2021 Committee Report Number AGENDA ITEM 11 Subject CONTRIBUTION TOWARDS A BUSINESS CASE FOR THE RESTORATION OF THE FORMER RAIL CONNECTION BETWEEN KEMBLE AND CIRENCESTER Wards affected ALL Accountable member Cllr. Rachel Coxcoon - Cabinet Member for Planning Policy, Climate Change and Energy Email: [email protected] Accountable officer James Brain (Forward Planning Manager) Tel: 01285 623540 Email: [email removed] Summary/Purpose The Cirencester Community Rail Project has been successful in a bid to the government’s Reopening of Railways Fund. The government will fund 75% of costs, up to £50,000, to prepare a Strategic Outline Business Case (SOBC) for the restoration of passenger rail services between Kemble Station and Cirencester Town Centre. Cotswold District Council has been asked for a contribution towards the feasibility study.

Annexes NONE Recommendation/s That Cabinet agrees to contribute £10,000 towards the cost of the Strategic Outline Business Case and a Secondary Phase Feasibility Study. Corporate priorities ● Responding to the challenges presented by the climate change and ecological emergencies ● Presenting a Local Plan which is green to the core Key Decision ● NO Exempt ● NO Consultees/ Consultation between Cotswold District Council officers, Senior Management Consultation and the Cabinet Members for Planning Policy, Climate Change and Energy and Development Management 1. BACKGROUND

1.1The Kemble to Cirencester line was closed between 1964 and 1965. The Cirencester Community Railway Group has been set up with the aim to reconnecting Cirencester with the national rail network.

1.2The group has uploaded a video promoting the project on youtube https://www.youtube.com/watch?v=A302xdBZMFo

1.3The Council continues to demonstrate its support for the project and has provided financial (£13,000) and political support which has assisted the group to achieve a share of government funding from the Department for Transport’s Reopening of Railways Fund. This funding supported the delivery of the group’s Primary Phase Feasibility Study, which is now complete. This study provides a significant source of evidence in which to deliver the SOBC. The Primary Phase Feasibility Study will be followed by a Secondary Phase Feasibility Study.

1.4A significant proportion of the Department for Transport’s ‘Restoring your Railway’ funding and CDC funding will be used to commission the Secondary Phase Feasibility Study, which is estimated to cost £130,000 and will take approximately nine months to deliver.

1.5The Council’s Forward Planning Manager and Sustainable Transport Lead Officer are active members of the Cirencester Community Railway Group and its newly formed Board; providing the group with access to officer resource, knowledge and experience. This is a mutually beneficial partnership as it ensures key Council projects such as the Cirencester Town Centre Masterplan, the Cotswold Sustainable Transport Strategy and the revised Cotswold District Local Plan are well integrated with the group’s proposal.

2. SUMMARY OF PROPOSALS

2.1The Government explains that the SOBC is the first of three stages in business case development. The SOBC will be expected to answer the following questions:

● What is the transport issue under consideration and case for intervention? ● What is the scope of this intervention and/or constraints on the approach? ● Why is rail the preferred mode? ● What are the options? ● How does each option perform in delivering benefits? ● Other strategic considerations – regional/local socio-economic evidence/data, levelling up, re-balancing etc. 2.2. Assuming the group’s SOBC is successful, the group will be expected to prepare an Outline Business case (OBC). This will contain more detail and information on the project and it is envisaged that the Secondary Phase Feasibility Study will play a significant role when drafting the OBS.

3. KEY CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contribution towards a business case for the restoration of the former rail connection between Kemble and CirencesterReport 303 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
SA
Stephen AndrewsAssociate Member, in attendance
TB
Tony BerryAssociate Member, in attendance
PC
Patrick ColemanAssociate Member, in attendance
RC
Rachel CoxcoonCommittee Member, apologies
TD
Tony DaleCommittee Member, present
AD
Andrew DohertyCommittee Member, present
ME
Mike EvemyCommittee Member, present
JF
Jenny FordeCommittee Member, present
JH
Joe HarrisCommittee Member, present
NI
Nikki IndAssociate Member, in attendance
LS
Lisa SpiveyCommittee Member, present
CW
Clive WebsterCommittee Member, present

More from Cotswold Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 MinutesThe purpose of this item was to consider the minutes of the previous two meetings of Cabinet of the meeting of Cabine... Noted Open
10 Sep 2026 Schedule of Decisions taken by the Leader of the Council and/or Individual Cabinet MembersDecision Meeting 30 June 2026 Deputy Leader and Cabinet Member for Housing and Planning Delegated Decision Meeting 3 ... Decided Open
10 Sep 2026 Suitable Alternative Natural Greenspace Spending 2026The purpose of this item was to ask Cabinet to consider officer recommendations on external bids for funding from the... Noted Open
10 Sep 2026 Corporate Performance Report - Q1 2026/27The purpose of this item was to provide an update on Corporate Performance from April to the end of June 2026. Counci... Noted Open
10 Sep 2026 Establishing a Voluntary Joint Committee - Local Government ReorganisationThe Leader announced that this item was being withdrawn from the agenda in light of the government’s announcements on... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies