RESOLVED that Council: a) proceed with the planned decarbonisation installation noting the financial risks surrounding withdrawal of funding should delivery fail to meet the grant funding completion deadline; b) allocate a contingency sum of £120,000 (12.5% of works capital costs) to support delivery and avoid unnecessary delays if costs exceed initial estimates and grant funding provided - any expenditure of this contingency to be agreed by the Deputy Chief Executive/Chief Finance Officer in consultation with the Cabinet Member for Finance; c) £120,000 be reallocated in the Capital Programme from the £980,000 available for “Acquisition of a Strategic site at Moreton-in-Marsh” to the contingency for the decarbonisation scheme; d) note that a variation to the SLM leisure services contract is necessary to enable utility costs to be paid by the Council and agrees that management fees payable to the Council are adjusted accordingly. Record of Voting - for 33, against 0, abstentions 0, absent 1.
Word for word from the decision Cotswold published for this meeting.Source: meetings.cotswold.gov.uk
1.1The Public Sector Decarbonisation Scheme (PSDS) is a £1bn (initial allocation) capital investment scheme operated through the Government Department for Business, Energy and Industrial Strategy (BEIS). The aim of the scheme is to invest (as grant) in the public sector estate to substantially reduce energy use and carbon emissions, reduce running costs, and contribute to the growth in capacity and skills for installation of carbon reduction measures across the economy.
1.2On March 1st Cabinet noted that the Council's bid for funding had been successful and agreed to progress with the installation of carbon reduction measures in Cirencester and Bourton on the Water leisure centres together with the Moreton Area Centre.
1.3The grant offer of £1.237m requires a number of criteria to be satisfied including; Completion of works by 30th September 2021 Financial benefits from any measures installed to be received by the Council.
1.4On 13th May 2021 Cabinet agreed to a series of delegations to enable swift progression with this project to meet the criteria in 1.3 above. Council are now asked to agree the continued delivery of this carbon reduction scheme, noting the risks and to allocate contingency funding for capital works. Delegation is also sought to enable a variation to the leisure services contract with SLM, an explanation of which is contained within this report.
2. Project delivery
2.1The timeline is extremely challenging particularly as contractors need to be procured and some specialist equipment has a substantial lead time from placement of orders to delivery which may impact on the Council's ability to meet completion deadlines.
2.2The Council filed its first monthly return to Salix, the grant administering body, in April highlighting a commitment to work towards completion by the end of September but highlighting concerns regarding potential delays which may be beyond the Councils control.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment to Committees 2026-27RESOLVED to: 1. DETERMINE that, in accordance with Section 15 of the Local Government and Housing Act 1989 (“the Act”...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.