That Council approved the use of funds from the Capital Programme and the following recommendation(s): a) That SLM is given approval to complete the Capital Investment project. b) That SLM’s proposed Option (1) as set out in Annex A is approved with the remainder of the Capital budget being retained for investment in Leisure Equipment. c) That the authority approve expenditure of the retained balance of the Capital budget, if Option (1) was supported, and final approval would be delegated to the Cabinet Member for Health and Wellbeing once the procurement has been completed. Voting Record – For 30, Against 0, Abstentions 0, Absent 4,
Word for word from the decision Cotswold published for this meeting.Source: meetings.cotswold.gov.uk
Subject APPROVAL OF THE CABINET DECISION (Cabinet Meeting 4th April 2022) FOR USE OF FUNDS FROM THE CAPITAL PROGRAMME
Wards affected ALL
Accountable member Cllr Jenny Forde Cabinet Member for Health & Wellbeing Email: [email protected]
Accountable officer Scott Williams Business Manager - Contracts Email: [email removed]
Summary/Purpose To approve the use of funds in the Capital Programme for the delivery of a Capital Investment project, as detailed in this report and supporting documentation, by SLM Everyone Active (SLM)
Annexes Annex A – SLM Health & Wellbeing Strategy and Facility Improvement Proposal Annex B – Technogym Equipment Update 2022 Annex C – Technogym Update/Sector Information
Recommendation(s) That Council approves the use of funds from the Capital Programme and the following recommendation(s), following Cabinet Approval of the proposal. a) That SLM is given approval to complete the Capital Investment project. b) That SLM’s proposed Option (1) as set out in Annex A is approved with the remainder of the Capital budget being retained for investment in Leisure Equipment. c) That the authority approve expenditure of the retained balance of the Capital budget, if Option (1) is supported and final approval is delegated to the Cabinet Member for Health and Wellbeing once the procurement has been completed.
Corporate priorities (Select which ones apply from the list below:) Delivering our services to the highest standards Helping residents and communities access the support they need for good health and wellbeing
Key Decision NO
Exempt YES (Annexes exempt)
Consultees/ CDC Cabinet Consultation Cllr Jenny Forde Senior Officers – CDC/Publica Project Team; Pete Williams, Business Development Director SLM Jamie Nesbit, Partnership Manager SLM Dan Carvell, Regional H&F Manager SLM Technogym 1. BACKGROUND
1.1As part of the Leisure Management Contract with SLM Everyone Active (SLM) a schedule of agreed contributions towards Capital Replacement of Fitness Equipment was included. The investment was scheduled to take place at prescribed time intervals, however, due to the forced closures and disruption of 2020/21 the programme was put on pause until a clearer understanding of the emerging Leisure Sector could be gained following the stabilisation of the Country after the pandemic.
1.2To help to minimise disruption to customers during periods of closure for the works in the Main Gym areas temporary/alternative Gym provision will be explored for Cirencester and Bourton Leisure Centres. Provisional sums have been included for this within the project funding breakdown.
1.3The Café service will re-open from May 2022 - this will re-instate the Café and social area which can be used by the whole community. The café area refurbishment will include redecoration, new furniture, removal of radiators that obstruct pool viewing, and provision of additional/improved spectator seating for the swimming pool.
1.4As part of the overall improvement project SLM will invest in the replacement of new Group Exercise equipment and Group Cycling bikes to enhance the customer experience for members that participate in the Group Exercise Programme.
1.5The table below shows the original schedule for the Capital Investments for fitness equipment.
Year (Contract Value £? Who is What is the investment for? Year) responsible?
Appointment to Committees 2026-27RESOLVED to: 1. DETERMINE that, in accordance with Section 15 of the Local Government and Housing Act 1989 (“the Act”...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.