Use of Unilateral Undertaking Funding for Moreton-in-Marsh Integrated Transport Hub

Agreed Executive 1 paper

Cabinet agreed this item on Monday 5 September 2022. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

Cabinet agreed and would recommend to full Council that the Council entered into a grant agreement with Moreton-in-Marsh Town Council to provide a contribution of £250,000 to the Moreton-In Marsh community infrastructure schemes as Annex A, and noted that the £250,000 was funded from a developer contribution which was received by the Council under a Unilateral Undertaking agreement entered into in 2014 Record of Voting – for: 7, against: 0, abstention: 0, absent: 1
Word for word from the decision Cotswold published for this meeting. Source: meetings.cotswold.gov.uk

Follow this further

Built from Cotswold's papers

What the report saysPro

Report to Cabinet

Council Name COTSWOLD DISTRICT COUNCIL

Name and Date of Cabinet – 5th September 2022 Committee

Report Number AGENDA ITEM 11

Subject Unilateral Undertaking Contribution – Moreton-in-Marsh

Wards Affected Moreton East, Moreton West

Accountable Member Cllr Juliet Layton Email: [email removed]

Accountable Officer Jo Moore, Deputy Chief Executive Email: [email removed]

Summary/Purpose To seek approval to contribute £250,000 to the Moreton-in-Marsh Town Council community infrastructure schemes.

Annexes Annex A – Moreton-in-Marsh Town Council Unilateral Undertaking Contribution improvement plans.

Recommendation(s) That Cabinet: a) Agrees and recommends to full Council that the Council enters into a grant agreement with Moreton-in-Marsh (MIM) Town Council to provide a contribution of £250,000 to the MIM community infrastructure schemes as Annex A; b) Notes that the £250,000 is funded from a developer contribution which was received by the Council under a Unilateral Undertaking agreement entered into in 2014.

Corporate priorities  Responding to the challenges presented by the climate crisis.  Helping residents and communities access the support they need for good health and wellbeing.

Key Decision YES

Exempt Report – NO // Annexes – YES

Consultees/ Chief Executive, Monitoring Officer, Leader, Deputy Leader, CDC Ward Consultation Cllrs – Rachel Coxcoon (Cabinet Member for Climate Change and Forward Planning) and Clive Webster, Moreton-In-Marsh Town Council, James Brain (Forward Planning Manager) and Hannah Fountain (Sustainable Transport Lead). 1. BACKGROUND

1.1In December 2014, Cotswold District Council entered in a Unilateral Undertaking agreement with the Fire Service College Ltd under which the College agreed to pay a £250,000 contribution towards certain qualifying improvements to the Moreton-in-Marsh area.

1.2Under this agreement, the Council is required to have spent or committed the funds to a Community Infrastructure scheme by the fifth anniversary of the date the funds were received which is the 17th November 2022.

1.3This report seeks approval to now pay the £250,000 to Moreton-in-Marsh Town Council as a contribution towards the improvement schemes as set out in the Town Council report at Annex A.

2. KEY MATTERS

2.1The Unilateral Undertaking agreement specified that the £250,000 contribution was to be for a Community Infrastructure Purpose which was defined as being towards:

“The improvement of the highways and transportation network and/or the promotion or improvement of the economic and/or social and/or the environmental wellbeing of the Parish of Moreton-in-Marsh”

2.2The agreement also specified a 5-year period in which the contributions must be “spent or committed” otherwise the £250,000 (or any unspent portion) would need to be repaid to the Fire Service College plus repayment interest (calculated on an annual basis and compounded).

2.3The contribution can be spent by the Council itself or passed to the Town Council but it is the Council’s responsibility, under the terms of the agreement, that any use is consistent with the intended purpose as outlined in paragraph 2.1.

3. PROPOSED USE

3.1The Moreton-in-Marsh Town Council (MIMTC) scheme proposals are set out at Annex A and broadly consist of two main schemes: the refurbishment of Redesdale Hall and the development of an integrated transport hub.

3.2The Town Council jointly purchased, with Great Western Railway (GWR), land adjacent to the railway station with a view to joining this site with the existing car park to create an integrated transport hub. The main benefits of this hub are set out in section 4 of the plans at Annex A. 3.3 As set out in Annex 1 to the plans, the total estimated costs for the development of the integrated transport hub are in the region of £3.5m. Of this c£0.5m is required to progress the project to a stage where there is a suitable design for the hub for which planning approval has been given.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Use of Unilateral Undertaking Funding for Moreton-in-Marsh Integrated Transport HubReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
AB
Amy Bridgewater-CarnallSecretary, expected
JB
Jan BrittonCouncil Staff, expected
AC
Angela ClaridgeCouncil Staff, expected
RC
Rachel CoxcoonCommittee Member, apologies
TD
Tony DaleCommittee Member, present
JD
Julie DixonSecretary, expected
AD
Andrew DohertyCommittee Member, present
ME
Mike EvemyCommittee Member, present
JF
Jenny FordeCommittee Member, present
JH
Joe HarrisCommittee Member, present
CH
Claire HughesCouncil Staff, expected
JL
Juliet LaytonCommittee Member, present

All 17 on the meeting page

On this subject at Cotswold

Search all
  1. Use of Unilateral Undertaking Funding for Moreton-in-Marsh Integrated Transport HubThis decision
  2. Use of Unilateral Undertaking Funding for Moreton-in-Marsh Integrated Transport HubAgreed

More from Cotswold Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 MinutesThe purpose of this item was to consider the minutes of the previous two meetings of Cabinet of the meeting of Cabine... Noted Open
10 Sep 2026 Schedule of Decisions taken by the Leader of the Council and/or Individual Cabinet MembersDecision Meeting 30 June 2026 Deputy Leader and Cabinet Member for Housing and Planning Delegated Decision Meeting 3 ... Decided Open
10 Sep 2026 Suitable Alternative Natural Greenspace Spending 2026The purpose of this item was to ask Cabinet to consider officer recommendations on external bids for funding from the... Noted Open
10 Sep 2026 Corporate Performance Report - Q1 2026/27The purpose of this item was to provide an update on Corporate Performance from April to the end of June 2026. Counci... Noted Open
10 Sep 2026 Establishing a Voluntary Joint Committee - Local Government ReorganisationThe Leader announced that this item was being withdrawn from the agenda in light of the government’s announcements on... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies