Resolved
RESOLVED : That Cabinet 1) NOTE the publication of the Infrastructure Funding Statement
Cabinet noted this item on Monday 17 July 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That Cabinet 1) NOTE the publication of the Infrastructure Funding Statement
Council name COTSWOLD DISTRICT COUNCIL
Name and date of Cabinet Meeting 17 July 2023 Committee
Subject Infrastructure Funding Statement 2022/23
Wards affected All
Accountable member Councillor Juliet Layton Cabinet Member for Planning and Regulatory Services Email: [email protected]
Accountable officer Andy Barge – Assistant Director for Communities Email: [email protected]
Report author Jasper Lamoon – Infrastructure Delivery Lead Email: [email protected]
Summary/Purpose To notify Cabinet of the Infrastructure Funding which provides an overview of all Community Infrastructure Levy (CIL) and Section106 monies collected, held and spent.
Annexes Annex A – Infrastructure Funding Statement 2022/23
Recommendation(s) That Cabinet resolves to note publication of the Infrastructure Funding Statement
Corporate priorities Delivering our services to the highest standards Responding to the challenges presented by the climate crisis Providing good quality social rented homes Presenting a local plan that’s green to the core
Key Decision NO
Exempt NO
Consultees None 1. BACKGROUND
1.1In the CIL legislation changes of September 2019, the government introduced a requirement for Councils to produce a yearly ‘Infrastructure Funding Statement’ (IFS). The first statement, covering the financial year 2019/20 was published in December 2020. Annex A provides the fourth edition of the report covering the 2022/23 financial year.
1.2The aim of the IFS is to increase transparency by providing a statement of accounts of all financial and non-financial developer contributions relating to S106 Agreements and CIL collected, held and spent by a Local Authority per financial year. The report has therefore been kept succinct and factual.
1.3The IFS is split into three sections: The Infrastructure List, the CIL Report and the S106 Report. The CIL and S106 Reports contain factual data about the collection and spending of funding for infrastructure in the District as set out in the CIL regulations, while the Infrastructure List is a statement of infrastructure projects that the Council expects to be wholly or partly funded by CIL. This is an evidence based list derived from infrastructure needs identified in the Council’s adopted Local Plan.
1.4This IFS also contains information on the neighbourhood proportion (the element of funding given to Town and Parish Councils) of CIL. Please note that it is the Town and Parish Councils responsibility to report on any expenditure of their neighbourhood proportion although CDC does provide them with a template to do so. A summary of expenditure that we have been informed of can be found under Appendix D of the IFS.
2. CIL Report
2.1CIL is a non-negotiable rate on new development which is indexed each year. The rate for 2023 is set at £89.31/sqm for residential developments and £66.98/sqm for retail developments.
2.2In March 2023, the Council launched a call for bids from infrastructure providers to access collected CIL funds. The deadline for submitting bids is 31 May 2023 and it is anticipated that a spending proposal will be brought to Cabinet and Full Council (as required) in September this year.
2.3The Community Infrastructure Levy Regulations 2010 (as amended) set out which figures need to be reported on in the IFS. The full IFS can be found at Appendix A, but the main figures are as follows: in 2022/23, the Council collected £1,581,247.85 and issued Demand Notices for a total value of £1,958,874.50. A Demand Notice is issued when a development commences and the CIL becomes due in line with the instalment policy. £261,103.61 was collected for Town and Parish Councils and a total of £2,047,757.96 in CIL reliefs was granted (set by national legislation). At 1 April 2023 the CIL Strategic Fund held £1,991,618.04.
3. S106 Report
3.1The Community Infrastructure Levy Regulations 2010 (as amended) specify which figures need to be reported. The full IFS with all figures can be found at Appendix A.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Infrastructure Funding Statement 2022 23Appendix A | 804 KB | Download |
PDF |
Infrastructure Funding Statement 2022/23Report | 106 KB | DownloadRead as text |
Follow Cabinet at Cotswold and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | MinutesThe purpose of this item was to consider the minutes of the previous two meetings of Cabinet of the meeting of Cabine... | Noted | Open |
| 10 Sep 2026 | Schedule of Decisions taken by the Leader of the Council and/or Individual Cabinet MembersDecision Meeting 30 June 2026 Deputy Leader and Cabinet Member for Housing and Planning Delegated Decision Meeting 3 ... | Decided | Open |
| 10 Sep 2026 | Suitable Alternative Natural Greenspace Spending 2026The purpose of this item was to ask Cabinet to consider officer recommendations on external bids for funding from the... | Noted | Open |
| 10 Sep 2026 | Corporate Performance Report - Q1 2026/27The purpose of this item was to provide an update on Corporate Performance from April to the end of June 2026. Counci... | Noted | Open |
| 10 Sep 2026 | Establishing a Voluntary Joint Committee - Local Government ReorganisationThe Leader announced that this item was being withdrawn from the agenda in light of the government’s announcements on... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.