Neighbourhood Planning: Regulation 15 Decision for the Down Ampney Neighbourhood Development Plan
AgreedPlanning5 papers
Planning and Regulatory Services Decision Meeting agreed this item on Wednesday 16 August 2023. Below is the council's own wording, with the papers it was decided on.
Decision The Cabinet Member considered the recommendations of the officer and agreed to the officer's recommendations that; 1) That the submitted documents meet the requirement of Regulation 15 of the Neighbourhood Planning Regulations 2012; 2) Consequently, the Council will launch the statutory 'Regulation 16' publicity period for the standard six week period. Reason for Decision of the Cabinet Member for Planning and Regulatory Services The Cabinet Member agreed to the decision as it was deemed that the documents met the statutory requirements for Neighbourhood Plans and therefore it could proceed to the 'Regulation 16' publicity period. ACTIONS BY: Joseph Walker Tel: 01285 623146 Date of Publication: 16 August 2023 Closing Date for Call-In: 24 August 2023 (5.00pm) Action Embargoed until: 25 August 2023
Word for word from the decision Cotswold published for this meeting.Source: meetings.cotswold.gov.uk
Report to Planning and Regulatory Services Decision Meeting
Council name COTSWOLD DISTRICT COUNCIL
Name and date of CABINET MEMBER FOR PLANNING AND REGULATORY SERVICES Committee DECISION MEETING– 10th August 2023
Subject NEIGHBOURHOOD PLANNING: REGULATION 15 DECISION FOR THE DOWN AMPNEY NEIGHBOURHOOD DEVELOPMENT PLAN
Wards affected The Ampneys and Hampton
Accountable member Juliet Layton, Cabinet Member for Planning and Regulatory Services Email: [email protected]
Accountable officer Charlie Jackson, Assistant Director, Planning and Sustainability Email: [email removed]
Report author Joseph Walker, Community Partnerships Officer Email: [email protected]
Summary/Purpose To consider whether a Neighbourhood Plan submitted by Down Ampney Parish Council meets the legal criteria necessary to progress to public consultation, and subsequent independent examination.
Annexes Annex A Down Ampney Neighbourhood Plan A1: Down Ampney Neighbourhood Plan Regulation 16 Draft A2: Appendices A3: Annexes A4: Design Code Annex B: Basic Conditions Statement Annex C: Consultation Statement Annex D: Strategic Environmental Assessment and Habitat Regulations Assessment Screening
Recommendation(s) a) That the Cabinet Member agrees that the submitted documents meet the requirement of Regulation 15 of the Neighbourhood Planning Regulations 2012; b) Consequently, the Council will launch the statutory ‘Regulation 16’ publicity period for the standard six week period.
Corporate priorities ● Make our local plan green to the core ● Support health and wellbeing
Key Decision NO
Exempt NO
Consultees/ 1.1. The Plan has been consulted on by the Parish Council, and subsequent to Consultation this decision, will be subject to public consultation, following a statutory process. The Council will have the opportunity to make representations on the content of the Plan, for the consideration of an Independent Examiner. 1. EXECUTIVE SUMMARY 1.1 The purpose of this report is to consider whether a Neighbourhood Development Plan, submitted by Down Ampney Parish Council, meets the necessary conditions set out in the Neighbourhood Planning Regulations 2012 to proceed to the Regulation 16 publicity period and subsequently independent examination.
2. BACKGROUND 2.1 Down Ampney Parish Council (DAPC) applied to this Council in 2018 to designate a neighbourhood area. The area applied for, and subsequently approved, was the boundaries of the parish. Since that date, volunteers and councillors in Down Ampney have been working up the Plan, a process delayed by Covid 19 restrictions. Nevertheless, they carried out a statutory Regulation 14 consultation from February to March 2022. Following some redrafting, and notably the creation of a Design Guide, a second Regulation 14 consultation was conducted from April to May 2023. Representations to these consultations have been considered in preparing a submission draft, which has recently been received by this Council. 3. MAIN POINTS 3.1 At this stage, the Local Planning Authority (LPA) has a duty to assess the Plan for its compliance with the requirements of the Regulations and determine if it can proceed for Regulation 16 Consultation and Examination. 3.2 The assessment requires consideration of: ● whether the ‘qualifying body’ (a parish council or neighbourhood forum) is authorised to act; ● whether the proposal and accompanying documents comply with rules of submission to the LPA, whether it meets the definition of a Neighbourhood Development Plan (NDP), and whether it meets the ‘scope’ of NDP provisions; and ● whether the parish council or neighbourhood forum has undertaken the correct procedures in relation to consultation and publicity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Regulatory Services Decision Meeting at Cotswold and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.