What was decided
Cabinet approved an addition to the Regulation 18 Preferred Options consultation document for the Cotswold District Council Local Plan Review.
Cabinet approved the start of a seven week public consultation on the Preferred Options, running from 14 November 2025 to 2 January 2026.
The vote was 6 for, 0 against, 0 abstentions.
Why
The government's December 2024 housing target for Cotswold rose by more than 100% to 1,036 homes a year, and the Council lost its five year housing land supply. Report 1.6, 1.7
The Local Plan must look at least 15 years from the expected 2027 adoption, so the plan period runs to 2043 and 18,650 additional new homes are needed. Report 1.9, 2.2
The Council is putting forward Scenario 5, which adds new settlements or strategic extensions on top of the current strategy, as the evidence based preferred option. Report 2.17
What happens next
The public consultation opens on 14 November 2025 and closes at midnight on 2 January 2026. Report 1.15
The Council is commissioning evidence on employment, town centres, gypsy and traveller needs, and an Infrastructure Delivery Plan. Report 4.4
A Regulation 19 draft Local Plan is to be published for further consultation in summer 2026, with adoption targeted for 2027. Report 3.9, 1.9
Options considered
- Rejected: Scenario 1: allocate sites in Principal, Non Principal and Village Clusters, support Rural Exception Sites in Rural Settlements. Estimated 7,840 homes, only 42% of 18,650 target Report P33, P38
- Rejected: Scenario 2: add a dispersed approach across Rural Settlements. Estimated 8,230 homes, only 44% of target Report P39, P41
- Rejected: Scenario 3: focus growth at main service centres. Estimated 9,420 homes, only 51% of target Report P42, P45
- Rejected: Scenario 4: focus growth around public transport nodes. Estimated 9,190 homes, only 49% of target Report P46, P49
- Chosen: Scenario 5: add new settlements or strategic extensions to existing settlements. Estimated 14,660 homes, 79% of target, the highest sustainable option Report P50, P54, 2.17
- Rejected: Scenario 6: as Scenario 5 but include major development in the Cotswolds National Landscape. Contrary to national policy and not considered viable Report P55, P56, P57
- Rejected: Scenario 7: maximise growth including sites assessed as unsuitable for development. Not considered sustainable Report P58, P59, P60
Implications
- Legal: An independent Inspector at the Examination in Public will assess the plan's soundness; without an up to date plan the Council cannot refuse unsuitable applications under national policy. Report 1.2, 3.14
- Risk: The Council has lost its five year housing land supply, reducing its power to refuse planning applications for new homes. Report 1.7
- Risk: Thames Water's financial difficulties may delay water and wastewater upgrades, holding back housing delivery. Report 3.12
- Risk: Realistically about 20% fewer than 14,660 homes may be delivered in the plan period if large sites are delayed, leaving around 11,730 homes. Report 3.12
- Financial: An Infrastructure Delivery Plan is being commissioned to identify and cost infrastructure for each allocation. Report 4.9
- Climate: The draft vision commits the district to zero carbon new development, renewable energy, reduced transport emissions, and Biodiversity Net Gain. Report 5.2, P127, P128
- Equalities: The draft vision and objectives include a diverse housing mix and a focus on socially rented and affordable homes. Report 5.2, P133
- Other: Plan must look at least 30 years ahead for strategic sites; some allocated homes would be delivered beyond 2043. Report 1.9
Who and where
- Residents, businesses, landowners, developers, and town and parish councils across Cotswold District Report 1.3
- Sixteen Principal Settlements and thirteen Non Principal Settlements or Village Clusters named in the strategy Report P35
- Proposed strategic growth locations: Ampney Crucis, The Steadings in Cirencester, Driffield, Fairford, Kemble, Moreton in Marsh, Preston, and Siddington Report P103, P106
- Cotswolds National Landscape area, where major development is restricted to exceptional circumstances
- Neighbouring local authorities who may be asked to help meet any unmet housing need Report 2.4, P31, 3.13
Timeline
- 14 November 2025: Seven week public consultation opens Report 1.15
- 2 January 2026: Public consultation closes at midnight Report 1.15
- End of 2025: Gloucestershire Housing and Employment Needs Assessment, Town Centres Study, and Gypsy and Traveller Accommodation Assessment expected to complete Report 4.4
- Spring 2026: Gloucestershire Housing and Economic Needs Assessment reassessment expected Report P30
- Summer 2026: Regulation 19 draft Local Plan to be published for further consultation Report 3.9
- 2027: Expected adoption of the Local Plan Update Report 1.9
- 2043: End of the proposed Local Plan period Report 1.9
Plain English for the jargon
- Regulation 18: First formal stage of Local Plan preparation, when the council consults on issues, options and policy proposals.
- Regulation 19: Pre-submission draft Local Plan stage, requiring a further public consultation before examination.
- Examination in Public: Independent Inspector from the Planning Inspectorate assesses whether the Local Plan is sound and legally compliant.
- Five year housing land supply: Requirement to have enough land available for five years of housing; loss of this supply weakens the Council's control over planning applications.
- Standard methodology: The government's formula for calculating the annual housing need for each local planning authority.
- Cotswolds National Landscape: Protected area where major development is restricted to exceptional circumstances and must be shown to be in the public interest.
- Principal, Non Principal and Village Cluster Settlements: Settlement tiers defined by the Council's Settlement Role and Function Study based on size, services, facilities and employment.
- Rural Exception Sites: Small affordable housing sites in rural settlements that would not normally be permitted for development.