Resolved
RESOLVED, that the Cabinet Member approves the list of schemes to be included in the 2013/14 Verge Programme (detailed in Appendix A to the report).
Public Services approved this item on Monday 8 July 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, that the Cabinet Member approves the list of schemes to be included in the 2013/14 Verge Programme (detailed in Appendix A to the report).
On 5 March 2013 Cabinet approved the 2013/14 Transportation and Maintenance Capital Programme. The basic principle of the programme was to carry out packages of complementary schemes, linking where possible works such as safety and traffic management schemes with maintenance schemes to maximise savings and efficiency.
The approval delegated authority to Cabinet Member (Public Services) to approve verge parking/protection schemes not specifically approved by Cabinet for implementation in 2013/14.
In accordance with the Cabinet approval this report seeks Cabinet Member approval for the 2013/14 prioritisation of verge parking/protection schemes.
The Cabinet Member is recommended to approve the list of schemes to be included in the 2013/14 Verge Programme (detailed in Appendix A).
List of Appendices included:
Appendix A - Proposed 2013/14 Verge Programme Other useful papers:
Cabinet Report Date: 5 March 2013. Title: 2013/14 Transportation and Maintenance Capital Programme http://democraticservices.coventry.gov.uk/documents/s9418/2013- 14%20Transportation%20and%20Maintenance%20Capital%20Programme.pdf
Cabinet Member (City Services) Report Date: 10 July 2012. Title: Revisions to Verge Parking Policy – http://democraticservices.coventry.gov.uk/Data/Cabinet%20Member%20(City%20Services)/2012 07101000/Agenda/Document%2011.pdf
Has it or will it be considered by Scrutiny? No
Has it, or will it be considered by any other Council Committee, Advisory Panel or other body? No
Will this report go to Council? No
2 Report title: Report – Verge Scheme Programme 2013/14
1. Context (or background)
1.1At the Cabinet meeting on 05 March 2013 approval was granted for the 2013/14 Transportation and Maintenance Capital Programme and for authority to be delegated to Cabinet Member (City Services) to approve verge parking/protection schemes not specifically approved by Cabinet for implementation in 2013/14.
2. Options considered and recommended proposal
2.1At the Cabinet Member (City Services) meeting of 12 July 2011 the revisions to the Verge Parking Policy were approved. The revisions to the policy assist to overcome competing demands on whether to assist parking on the verge or to protect the verge and determines the action to be undertaken, ether enhanced parking facilities or legal/ physical enforcement.
2.2There are a number of verges on which measures have been requested, originating either from highways inspectors/maintenance issues, individual members of the public or petitions. The proposed 2013/14 Verge Programme will utilise the approved budget of £125,000. £10,000 has been allocated to 'general' action, this is for works at various small sites which will assist to reduce on-going maintenance demands.
2.3An initial estimate is provided for each potential Verge scheme (Appendix A). However, these are estimates only and may change as detailed designs are completed and items such as the location of utility services and whether they will be required to be diverted is confirmed.
2.4The proposed Verge programme exceeds the available budget due to the high level of demand and requests received. The over prioritisation of schemes enables works to be undertaken to fully utilise the available budget, any schemes which are not completed will be carried forward for prioritisation in the next financial year.
3. Results of consultation undertaken
3.1Consultation with residents will be undertaken utilising Street news.
4. Timetable for implementing this decision
4.1If approved schemes, utilising the available budget, will be implemented by end of March 2014.
5. Comments from Director of Finance and Legal Services
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Verge Parking Schemes 2013-14Report | 53 KB | DownloadRead as text |
Follow Public Services at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Mar 2016 | Petition - Request for Traffic Lights at Junction of Longford Road and Oakmoor RoadRESOLVED that: (1) The concerns and requests of the petitioners be noted. (2) Approval be given that option 4 (southb... | Noted | Open |
| 15 Mar 2016 | Petitions Determined by Letter and Petitions Deferred Pending Further InvestigationsRESOLVED that: (1) Approval be given that, where appropriate, a summary of petitions received which are determined by... | Approved | Open |
| 22 Feb 2016 | Petition - The Management of Trees in Loudon AvenueRESOLVED that: (1) Approval be given to the reduction in the number of trees in the southern section of Loudon Avenue... | Approved | Open |
| 22 Feb 2016 | e-petition - Reopen Stoney Road to all TrafficIt was agreed that the bus gate would remain and monitoring would be undertaken. In July, 2013, following analysis of... | Agreed | Open |
| 22 Feb 2016 | Civil Parking Enforcement - Annual Report 2014 / 2015RESOLVED that the Civil Parking Enforcement Annual Report 2014/ 2015, as set out at the appendix, be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.