RESOLVED that the Cabinet : 1) Approves the completion of preparatory work to progress the re-build of the Gypsy and Traveller Site at Siskin Drive, Coventry, including site surveys and application for planning permission. 2) Following completion of preparatory work, approves the issuing of an order for a construction contract for the re-build of the Site, following a tender for the works. The value of the order for construction contract is not to exceed the value of the grant available from the Homes and Communities Agency. 3) Approves that in the event that the grant available from the Homes and Communities Agency is withdrawn, or the work not completed by 31 March 2015, and the City Council has incurred expenditure, that this expenditure is incurred from the City Councils Capital Budget. 4) Approves inclusion of the Project in the Capital Programme for 2014/15 as part of the City Council’s annual budget setting process. 5) Delegate authority to the Cabinet Member (Housing and Heritage) and the Cabinet Member (Community Safety and Equalities) to take decisions as to how both the re-build and other issues in relation to ... view the full minutes text for item 127.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Local Authorities are required to undertake a Gypsy and Traveller Accommodation Needs Assessment when carrying out a periodical review of housing needs under section 8 of the Housing Act 1985, this being a statutory requirement under section 225 of the Housing Act 2004.
The Council discharges this duty through the provision of a site in Siskin Drive, Coventry which currently contains 18 pitches. A Gypsy and Traveller Accommodation Assessment (GTAA) undertaken in 2008 concluded that this site was adequate in terms of numbers of pitches to fulfil the City Council’s obligations in this regard. However, the site is in poor condition and is in need of redevelopment in order to provide a suitable standard of accommodation for the Gypsy and Traveller Community.
In December 2012, the City Council secured grant funding totalling £1.073m from the Homes and Communities Agency to re-build the site to bring it up to modern standards. The funding is payable on practical completion of the works, with all works to be completed by 31 March 2015. There is currently no provision through the Homes and Communities Agency for funding to be available beyond this date. In addition to this the Council has previously identified £0.191m of unringfenced capital grant to enhance the site.
There have been a number of issues in relation to the management of the site which have contributed to the re-build work not being progressed. These issues are being proactively managed by Officers with political oversight from Cabinet Member (Housing and Heritage) and Cabinet Member (Community Safety and Equalities).
In order to progress the re-build of the site the City Council is required to obtain planning permission and then secure a contractor through tender to undertake the work. Recommendations:
Cabinet is recommended to:
1. Approve the completion of preparatory work to progress the re-build including site surveys and application for planning permission.
2. Following completion of preparatory work, approve the issuing of an order for a construction contract for the re-build of the site, following a tender for the works. The value of the order for construction contract is not to exceed the value of the grant available from the Homes and Communities Agency.
3. Approve that in the event that the grant available from the Homes and Communities Agency is withdrawn, or the work not completed by 31 March 2015, and the City Council has incurred expenditure that this expenditure is incurred from the City Councils capital budget.
4. Approve inclusion of the project in the Capital programme for 2014/15 as part of the City Councils annual budget setting process.
5. Delegate authority to Cabinet Member (Housing and Heritage) and Cabinet Member (Community Safety and Equalities) to take decisions as to how both the re-build and other issues in relation to the management of the site are progressed.
6. To accept further reports, as required regarding the progression of the redevelopment of the site.
List of Appendices included:
None
Background papers
None
Other Useful Documents:
Gypsy and Traveller Accommodation Assessment 2008
Joint Cabinet Members (Community Safety and Equalities) and (Housing and Heritage), Public Report 4 December 2013, Management of Council Land
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
No
Will this report go to Council?
No
2 Report title: Management of Council Land
1. Context (or background)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.