RESOLVED that the Council be requested to: 1. Approve that the Council, acting as landowner, enter into the Coventry and Warwickshire Gateway Section 106 Planning Agreement with Warwickshire County Council and Warwick District Council, provided that all the financial liabilities imposed on the Council in that agreement are indemnified by the Developer in the land agreement and backed by a bank guarantee. 2. Delegate authority to the Executive Director, Resources and the Executive Director, Place, in consultation with Cabinet Member (Business Enterprise and Employment), to negotiate the final terms of the Section 106 Planning Agreement, the indemnity from the Developer and the Bank Guarantee and to conclude all necessary legal documents in relation to the Section 106 Planning Agreement.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
In October 2012, Council approved the disposal of land around Coventry Airport to form part of a commercial development scheme known as The Coventry & Warwickshire Gateway.
A condition of the disposal required the developer to secure an acceptable planning consent for the proposed commercial development. An outline planning application for the proposed development was submitted by Coventry & Warwickshire Development Partnership LLP to Warwick District Council ref: W/12/1143 and Coventry City Council ref: OUT/2012/1791.The scheme covers both administrative areas, with the majority of the land falling within Warwick District and having some highway related matters within Coventry. At their respective planning committees both authorities resolved their intention to grant consent.
The Secretary of State for the Department for Communities and Local Government called in the application and a planning inspector was appointed to hold a public planning enquiry which commenced on the 21st April 2014 and was scheduled to last for 15 days. The evidence heard at the public inquiry is currently being considered by the inspector. As a number of significant impacts of the proposed development are mitigated by a section 106 planning agreement, a completed agreement will have a strong bearing on the Inspector's recommendation to the Secretary of State and on the Secretary of State's decision on the outline planning applications. Planning requirements proposed by the local planning authority, seek to impose obligations on the landowners, of which Coventry City Council is one. These obligations require certain relevant works to be carried out and financial payments to be made during the development and prior to occupation of the development. These obligations are to be secured and documented by way of a legally enforceable section 106 planning agreement.
The purpose of this report is to outline the financial liability potentially being imposed on Coventry City Council and how the liability is intended to be indemnified by the Coventry & Warwickshire Development Partnership as developer for the scheme, underwritten by a bank guarantee and to be documented as part of the land agreement.
Recommendations
The Cabinet is requested to recommend that the Council:
1. Approve that the Council, acting as landowner, enter into the Coventry & Warwickshire Gateway Section 106 Planning Agreement with Warwickshire County Council and Warwick District Council, provided that that all the financial liabilities imposed on the Council in that agreement are indemnified by the Developer in the land agreement and backed by a bank guarantee.
2. Delegate authority to the Executive Director, Resources and the Executive Director of Place, in consultation with Cabinet Member (Business Employment & Enterprise), to negotiate the final terms of the Section 106 Planning Agreement, the indemnity from the Developer and the Bank Guarantee and to conclude all necessary legal documents in relation to the Section 106 Planning Agreement.
The Council is recommended to:
1. Approve that the Council, acting as landowner, enter into the Coventry & Warwickshire Gateway Section 106 Planning Agreement with Warwickshire County Council and Warwick District Council, provided that that all the financial liabilities imposed on the Council in that agreement are indemnified by the Developer in the land agreement and backed by a bank guarantee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.