Proposed Rebuilding and Expansion of Edgewick Primary School: Increasing Primary Places for 2015

Approved Executive 1 paper

Cabinet approved this item on Tuesday 2 September 2014. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

RESOLVED that the Cabinet: 1. Approve plans for the rebuilding of Edgewick Primary School as part of the Increasing Pupil Places Programme. 2. Approve total expenditure of £5.45m for the rebuilding of the school to be funded by the Department for Education capital grant allocations as set out in section 5.1 of the report submitted. 3. Delegate authority to the Executive Director, Place, Cabinet Member (Education) and Cabinet Member (Culture, Leisure, Sports, Parks and Events) to determine the temporary use by the school of part of Edgewick Park during the construction period.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Cabinet

Executive summary

The redevelopment of Edgewick Primary School is proposed to replace the existing buildings and provide 30 additional places per year group, as part of the Increasing Pupil Places Programme 2015. Following public consultation, an Official Journal of the European Community (OJEU) tender process was carried out to select a consultant design team and partnering contractor. IDP Architects and Farrans Construction were appointed. The design proposal has been developed with the school and a planning application submitted in May 2014. Subject to approvals construction work is planned to commence in October 2014 for the new school building to become operational in September 2015. The estimated total costs based on the scheme proposals total £5,450,000 to be funded by Department for Education grant allocations. A more detailed breakdown of the costs and funding is outlined in section 5.1 of this report.

Recommendations

Cabinet is requested to:

1. Approve plans for the rebuilding of Edgewick Primary School as part of the Increasing Pupil Places Programme 2015.

2. Approve total capital expenditure of £5.45m for the rebuilding of the school to be funded by DfE capital grant allocations as set out in section 5.1 of this report.

3. Delegate authority to the Executive Director Place, Cabinet Member (Education and Cabinet Member (Culture, Leisure, Sports, Parks and Events) to determine the temporary use by the School of part of Edgwick Park during the construction period. List of Appendices included:

Appendix 1 –Edgewick Primary School – layout drawings Appendix 2 – Edgewick Primary School – schedule of accommodation

Background papers

None

Other useful documents

Report to Cabinet Member (Education) 19th December 2013 - Proposed Expansion of Edgewick Primary School 2015/16

Report to Cabinet 13th May 2014 - Proposed Expansion and Change to the Admission Number of Edgewick Primary School: Determination of Statutory Notice

All of the above are available from the Council’s website:

http://moderngov.coventry.gov.uk/ieListMeetings.aspx?CommitteeId=124

Has it or will it be considered by scrutiny?

No

Has it, or will it be considered by any other council committee, advisory panel or other body?

No

Will this report go to Council?

No

2 Report title: Proposed Rebuilding and Expansion of Edgewick Primary School: Increasing Primary Places for 2015

1. Context (or background)

1.1Under Section 14 of the 1996 Education Act, the City Council has a statutory responsibility to provide sufficient places for pupils in the City. In response to a significant rise in birth rate and inward migration the Council has been increasing primary admission numbers and providing additional permanent classrooms since 2008. During the period 2008 to 2014 an additional 945 reception places have been created in over 30 schools across the City. Numbers of pupils requiring reception places are continuing to rise and the number of reception places available in September 2015 will be insufficient to meet local demand.

1.2In order to increase the size of a school, formal procedures need to be carried out, in accordance with Schedules 2 and 4 of the School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2007 (as amended). On 13th May 2014, Cabinet granted approval to expand Edgewick Primary School from 1 to 2 Forms of Entry (210 to 420 Year R to Year 6 places) with effect from September 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Rebuilding and Expansion of Edgewick Primary School: Increasing Primary Places for 2015Report 668 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 15 attended
AR
Councillor Allan Robert AndrewsNon Voting Opposition Member, present
JB
Councillor John BlundellNon Voting Opposition Member, present
DG
Councillor Damian GannonCommittee Member, present
AG
Councillor Alison GingellCommittee Member, apologies, sent representative
AS
Councillor Abdul Salam KhanCommittee Member, present
RL
Councillor Rachel LancasterCommittee Member, present
AE
Councillor Ann Evelyn Lucas OBEChair, present
PD
Councillor Philip David TownshendDeputy Chair, expected
ER
Councillor Ed RuaneCommittee Member, present
FA
Councillor Faye AbbottCommittee Member, present
KM
Councillor Kevin MatonCommittee Member, present
KC
Councillor Kamran CaanDeputy Cabinet Member, present

All 15 on the meeting page

More from Coventry Cabinet

All decisions
MeetingDecisionOutcome
7 Jul 2026 Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S... Approved Open
7 Jul 2026 Acceptance of the Music Hub Revenue Grant for the Strategic Area of Coventry, Warwickshire and SolihullRESOLVED that, the Cabinet: 1. Approve acceptance of the revenue grant for the academic year 2026/27 from ACE of £1,7... Approved Open
17 Mar 2026 Private Sector Housing Enforcement Policy 2026-31RESOLVED that the Cabinet recommend that the policy be reviewed by full Council for approval. Approved Open
17 Mar 2026 Coventry: City of Movement Strategy 2026-2031RESOLVED that, the Cabinet: 1. Note and accept the additional recommendation from the Scrutiny Co-ordination Committe... Approved Open
17 Mar 2026 Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies