Communities and Neighbourhoods Scrutiny Board (4) decided this item on Wednesday 26 November 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED, that the Scrutiny Board: - 1. Support the continuation of the Cycle Coventry programme, seeking additional funding where possible. 2. Support the improvements and route provision on the network as set out in the proposed Cycling Strategy. 3. Support the provision of cycle training and bike maintenance courses to the population of Coventry, in particular focussing on those areas of the City in greatest need. 4. Requested that Officers explore setting aspirational targets for cycle route usage through regular monitoring. 5. Requested Officers to send the “Light Fabulous” leaflet to Members of the Board.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Report to Communities and Neighbourhoods Scrutiny Board (4)
Recommendations
2.1To support the continuation of the Cycle Coventry programme, seeking additional funding where possible; and to support the improvements and route provision on the network as set out in the proposed Cycling Strategy. In addition to support the provision of cycling training and bike maintenance courses to the population of Coventry, in particular focussing on those areas of the city in greatest need.
3 Information/Background
3.1Cycle Coventry has funding from the Department for Transport Local Sustainable Transport Fund, part directly and part via Centro through a West Midlands Regional bid. As shown in the table below this is for a period of 3 years which is coming to an end in March 2015.
3.2All of the infrastructure planned for in the bid will be completed by March 2015. A map of completions to date will be displayed at the meeting. Just under half of the funding has been to work with local people on education and promotion activity. Evidently it would be advantageous to continue promoting the routes and working with people across the city to encourage further cycling, particularly as some routes will only be completed towards the end of the 3yr programme.
3.3Whilst this programme has been successful so far, it is a relatively short period to achieve long term changes, therefore we are looking to continue. There are some funding commitments just agreed which carry us forward into the next 12 months, and we are working to gain more funding where available. As a Marmot City the ongoing public health aims are to get more people active, and the need to reduce motorised travel and improve air quality is still an issue for Coventry, therefore increasing the number travelling on foot or by bike through a continued Cycle Coventry programme can help to meet both of these objectives of the Council.
3.4A full year 1 monitoring report was presented to Scrutiny Board in February. A further 12 months of data will be reported at the end of the programme, showing levels of participation and monitoring of numbers cycling around the city.
Table 1. Funding Commitment for Cycle Coventry
£,000’s 2012/13 2013/14 2014/15 Total North Coventry Revenue funding 274.1 550.8 705.1 1,530 Capital funding 500 760 640 1,900 774.1 1310.8 1,345.10 3,430
South Coventry Revenue funding 275 379.5 379.5 1,034 Capital funding 195 1,319 948 2,462 Total 470 1,698.50 1,327.50 3,496
4 Cycle Coventry current programme 2011/12-2014/15.
Infrastructure completions
4.1All infrastructure work in the current programme is due to be completed by March 2015. Map 1 shows the 7 routes we are working on at present. We have completed some of the major sections, Charter Avenue and Hearsall Common in the south, and a route through Sowe Valley which extends from Eburne Road through to Wyken Croft and Anstey Road to connect with the hospital.
4.2When complete all the routes will be properly signed, and the key has been on providing a much safer environment particularly for cyclists who are less confident. Therefore we have been focussing on safer crossings on many routes, with Toucan controlled crossings, central refuges and new zebra/tiger crossings (all of which benefit pedestrians as well).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities and Neighbourhoods Scrutiny Board (4) at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
Severe Weather Emergency Protocol UpdateRESOLVED The Communities and Neighbourhoods Scrutiny Board (4) noted the content of the briefing note made the follow...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.