RESOLVED that the Cabinet Member for Policing and Equalities notes the progress made since the last report dated 18 December 2014 and directs that a further report be submitted for consideration at the Cabinet Member meeting on 26 February 2015.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
When the Council constructed the Coventry Magistrates' Court building in the 1980s, the premises included a "Probation Suite" whose construction cost of around £1.2 million was to be met by the Council initially but repaid by the Probation Service over a period of some 40 years. Annual repayments were made until 2007. However, the Probation Service now disputes liability to make any further payments.
This matter was considered by Cabinet on 11 December 2012, where authorisation was given to commence legal proceedings to recover the outstanding loan monies. The Cabinet Member (Community Safety & Equalities) was given delegated authority to determine alternative strategies or decisions as the matter progresses and the matter was considered at Cabinet Member meetings on 24th February 2014, 1st May 2014, 14th November 2014, and 18th December 2014. This report is an update as to the progress of the proceedings to date and considers the options going forward. Recommendations:
Cabinet Member is recommended to:
(1) Note the progress made since the last report dated 18 December 2014 and direct that a further report be submitted for consideration at the Cabinet Member meeting on 26 February, 2015.
List of Appendices included: None.
Other useful background papers:
None.
Has it been or will it be considered by Scrutiny? No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body? No
Will this report go to Council? No
2 Page 3 onwards Report title: Magistrates' Court Building
1. Context (or background)
1. Dispute History-During the 1980s, the Council constructed the Coventry Magistrates' Court, which included a Probation Suite. A proportion of the construction cost of the Suite (approximately £1.2 million) was to be met by the Council initially but repaid by the Probation Service over a period of some 40 years. However, the Probation Service disputes liability to make any payment after 2007, when ownership of the court building was transferred to Central Government.
2. The arrears of annual debt payments up to and including the financial year 2012/13 amount to a total of £491,571, and on 21st January 2013 the Council issued High Court proceedings for that sum plus interest.
3. The local Probation Service has operated through a large number of different bodies since 1990. Therefore, the Council took the precaution of naming as defendants all of the bodies identified as possibly liable, a total of 9 defendants. It then became clear that the active Defendants were the 6th to 9th defendants i.e. Staffordshire and West Midlands Probation Trust, the Secretary of State for Communities and Local Government, the Lord Chancellor and the Secretary of State for Justice, and the National Offender Management Service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.